Common use of Project Specific Milestones Clause in Contracts

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15, 2011, Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

Appears in 1 contract

Samples: Interconnection Service Agreement

AutoNDA by SimpleDocs

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15September 30, 20112012, Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 130, 20112012, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 1531, 2011, 2018 Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011At this time, Interconnection Customer must demonstrate that all generating units have been delivered submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Customer’s project siteFacilities.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15January 1, 2011, 2021 Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011At this time, Interconnection Customer must demonstrate that all generating units have been delivered submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Customer’s project siteFacilities.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15January 1, 2011, 2016 Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011At this time, Interconnection Customer must demonstrate that all generating units have been delivered submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Customer’s project siteFacilities.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15January 1, 2011, 2013 Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September March 1, 20112013, Interconnection Customer must demonstrate that all 2 generating units have been delivered to Interconnection Customer’s project site.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15March 1, 20112019, Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011At this time, Interconnection Customer must demonstrate that all generating units have been delivered submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Customer’s project siteFacilities.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15June 1, 20112022 December 1, 2022, Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011At this time, Interconnection Customer must demonstrate that all generating units have been delivered submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Customer’s project siteFacilities.

Appears in 1 contract

Samples: Interconnection Service Agreement

AutoNDA by SimpleDocs

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15November 30, 2011, 2012 Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1December 31, 20112012, Interconnection Customer must demonstrate that all 50 generating units have been delivered to Interconnection Customer’s project site.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15March 31, 2011, 2016 Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011At this time, Interconnection Customer must demonstrate that all generating units have been delivered submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Customer’s project siteFacilities.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15May 1, 2011, 2016 Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011At this time, Interconnection Customer must demonstrate that all generating units have been delivered submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Customer’s project siteFacilities.

Appears in 1 contract

Samples: Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15December 31, 20112017, Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011At this time, Interconnection Customer must demonstrate that all generating units have been delivered submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Customer’s project siteFacilities.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before August 15December 1, 2011, 2020 Interconnection Customer must demonstrate completion of at least 20% of project site construction. 6.2 Delivery of major electrical equipment. On or before September 1, 2011At this time, Interconnection Customer must demonstrate that all generating units have been delivered submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Customer’s project siteFacilities.

Appears in 1 contract

Samples: Interconnection Service Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!