Common use of Project Specific Milestones Clause in Contracts

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Local, county and state site permits. Interconnection Customer must obtain all necessary local, county and state site permits by January 31, 2021. 6.2 Substantial Site work completed. On or before November 30, 2021 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.3 Delivery of major electrical equipment. On or before November 30, 2021, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

Appears in 3 contracts

Samples: Interconnection Service Agreement, Interconnection Service Agreement, Interconnection Service Agreement

AutoNDA by SimpleDocs

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Local, county and state site permits. Interconnection Customer must obtain all necessary local, county and state site permits for the Interconnection Customer work scope by January December 31, 2021. 6.2 Substantial Site work completed. On or before November 30July 5, 2021 2022 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.3 Delivery of major electrical equipment. On or before November September 30, 20212022, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

Appears in 2 contracts

Samples: Interconnection Service Agreement, Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Local, county and state site permits. Interconnection Customer must obtain all necessary local, county and state site permits by January 31August 1, 20212019. 6.2 Substantial Site work completed. On or before November 30May 1, 2021 2020 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.3 Delivery of major electrical equipment. On or before November 30August 15, 20212020, Interconnection Customer must demonstrate that all 30 MW generating units have been delivered to Interconnection Customer’s project site.

Appears in 2 contracts

Samples: Interconnection Service Agreement, Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Local, county and state site permits. Interconnection Customer must obtain all necessary local, county and state site permits by January 31, 2021. 6.2 Substantial Site work completed. On or before November 30, 2021 2021, Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.3 Delivery of major electrical equipment. On or before November 30, 2021, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Local, county and state site permits. Interconnection Customer must obtain all necessary local, county and state site permits for the Interconnection Customer work scope by January 31December 1, 2021. 6.2 Substantial Site work completed. On or before November 30April 1, 2021 2022 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.3 Delivery of major electrical equipment. On or before November 30April 1, 20212022, Interconnection Customer must demonstrate that all 48 MW of generating units have been delivered to Interconnection Customer’s project site.

Appears in 1 contract

Samples: Interconnection Service Agreement

AutoNDA by SimpleDocs

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Local, county and state site permits. Interconnection Customer must obtain all necessary local, county and state site permits by January 31June 30, 20212019. 6.2 Substantial Site work completed. On or before November 30October 1, 2021 2019 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.3 Delivery of major electrical equipment. On or before November 30April 1, 20212020, Interconnection Customer must demonstrate that all 20 MW generating units have been delivered to Interconnection Customer’s project site.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Local, county and state site permits. Interconnection Customer must obtain all necessary local, county and state site permits by January 31March 1, 20212023. 6.2 Substantial Site work completed. On or before November 30July 1, 2021 2023 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.3 Delivery of major electrical equipment. On or before November 30September 1, 20212023, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

Appears in 1 contract

Samples: Interconnection Service Agreement

Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 LocalSite permits. On or before April 18, county 2022, Interconnection Customer must demonstrate that it has obtained any necessary local, county, and state site permits. Interconnection Customer must obtain all necessary local, county and state site permits by January 31, 2021. 6.2 Substantial Site work completed. On or before November 30January 14, 2021 2022, Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.3 Delivery of major electrical equipment. On or before November 30October 14, 20212022, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

Appears in 1 contract

Samples: Interconnection Service Agreement