Provisional Certificate. 12.2.1 Upon completion of Tests, the Authority’s Engineer shall satisfy itself that the Tests have been successful and the Railway Project is fit for opening to traffic. Upon such determination, the Authority’s Engineer shall issue to the Contractor and the Authority a certificate substantially in the form set forth in Schedule-K (the “Provisional Certificate”). The Authority’s Engineer may issue a Provisional Certificate even if certain works forming part of the Railway Project are not yet completed and in such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Authority’s Engineer and the Contractor (the “Punch List”). For the avoidance of doubt and by way of illustration, the Punch List may include [fencing, tree plantation, rest areas, ***]. 12.2.2 Upon issuance of the Provisional Certificate, the Authority’s Engineer shall forward to the Authority (i) copies of all Test data including Test results, and
Appears in 4 contracts
Samples: Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects
Provisional Certificate. 12.2.1 13.2.1 Upon completion of Tests, the Authority’s Authority‟s Engineer shall satisfy itself that the Tests have been successful and the Railway Project is fit for opening to traffic. Upon such determination, the Authority’s Authority‟s Engineer shall issue to the Contractor Concessionaire and the Authority a certificate substantially in the form set forth in Schedule-K J (the “Provisional Certificate”). The Authority’s Authority‟s Engineer may issue a Provisional Certificate even if certain works Works forming part of the Railway Project are not yet completed and in such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Authority’s Authority‟s Engineer and the Contractor Concessionaire (the “Punch List”). For the avoidance of doubt and by way of illustration, the Punch List may include [fencing, tree plantation, rest areas, ***].
12.2.2 13.2.2 Upon issuance of the Provisional Certificate, the Authority’s Authority‟s Engineer shall forward to the Authority (i) copies of all Test data including Test results, and
Appears in 1 contract
Samples: Concession Agreement
Provisional Certificate. 12.2.1 13.2.1 Upon completion of Tests, the Authority’s Engineer shall satisfy itself that the Tests have been successful and the Railway Project is fit for opening to traffic. Upon such determination, the Authority’s Engineer shall issue to the Contractor Concessionaire and the Authority a certificate substantially in the form set forth in Schedule-K J (the “Provisional Certificate”). The Authority’s Engineer may issue a Provisional Certificate even if certain works forming part of the Railway Project are not yet completed and in such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Authority’s Engineer and the Contractor Concessionaire (the “Punch List”). For the avoidance of doubt and by way of illustration, the Punch List may include [fencing, tree plantation, rest areas, ***].
12.2.2 13.2.2 Upon issuance of the Provisional Certificate, the Authority’s Engineer shall forward to the Authority (i) copies of all Test data including Test results, and
Appears in 1 contract
Samples: Concession Agreement