Provisional Certificate. 14.3.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the "Provisional Certificate") if the Tests are successful and the Bus Terminal can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the "Punch List"); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority. 14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Bus Terminal, if at least 75% (seventy five per cent) works of the Bus Terminal has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part.
Appears in 16 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the "“Provisional Certificate"”) if the Tests are successful and the Bus Terminal can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the "“Punch List"”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Bus Terminal, if at least [75% (seventy five per cent) works cent works)] of the Bus Terminal has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part.
Appears in 16 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Provisional Certificate. from
14.3.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the "“Provisional Certificate"”) if the Tests are successful and the Bus Terminal can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the "“Punch List"”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Bus Terminal, if at least [75% (seventy five per cent) works cent works)] of the Bus Terminal has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part.
Appears in 10 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the "“Provisional Certificate"”) if the Tests are successful and the Bus Terminal Project Highway can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the "“Punch List"”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the AuthorityMPRDC.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Bus TerminalProject Highway, if at least 75% (seventy five per cent) works of the Bus Terminal total length of the Project Highway has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part.
Appears in 3 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the "“Provisional Certificate"”) if the Tests are successful and the Bus Terminal Project Highway can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the "“Punch List"”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the AuthorityGovernment.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Bus TerminalProject Highway, if at least 75% (seventy five per cent) works of the Bus Terminal total length of the Project Highway has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the "“Provisional Certificate"”) if the Tests are successful and the Bus Terminal can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the "“Punch List"”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.. Downloaded from
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Bus Terminal, if at least [75% (seventy five per cent) works cent works)] of the Bus Terminal has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-Schedule- J (the "Provisional Certificate") if the Tests are successful and the Bus Terminal Project Highway can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the "Punch List"); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Bus TerminalProject Highway, if at least 7575 % (seventy five per cent) works of the Bus Terminal total length of the Project Highway has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part.
Appears in 1 contract
Samples: Concession Agreement
Provisional Certificate. 14.3.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the "Provisional Certificate") if the Tests are successful and the Bus Terminal Project Road can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the "Punch List"); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Bus TerminalProject Road, if at least 75% (seventy five per cent) works of the Bus Terminal total length of the Project Road has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part.
Appears in 1 contract
Samples: Concession Agreement
Provisional Certificate. 14.3.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J I (the "“Provisional Certificate"”) if the Tests are successful and the Bus Terminal Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the "“Punch List"”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Bus TerminalProject, if at least 75% (seventy five per centcent in terms of investments) works of the Bus Terminal Project has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part.
Appears in 1 contract
Samples: Model Concession Agreement