Provisional Certificate. Upon completion of Tests, the Authority Engineer shall satisfy itself that the Tests have been successful and the Railway Project is fit for opening to traffic. A list of outstanding items signed jointly by the Authority Engineer and the Contractor (called the “Punch List”) shall be prepared in two parts. The Part-1 showing the critical/safety items and the Part-2 showing non-critical/non- safety items. The Authority Engineer may issue a Provisional Certificate to the Contractor and the Authority in the form set forth in Schedule-K (the “Provisional Certificate”), provided the items figuring in the Punch List of critical/safety items (Part-1) have been fully completed/attended to. The items figuring in the Punch List (Part-2) of non-critical/non-safety should be completed by contractor in a time frame as stipulated in Clause 12.3.
Appears in 4 contracts
Samples: And Construction Agreement, And Construction Agreement, And Construction Agreement
Provisional Certificate. 12.2.1 Upon completion of Tests, the Authority Engineer shall satisfy itself that the Tests have been successful and the Railway Project is fit for opening to traffic. A list of outstanding items signed jointly by the Authority Engineer and the Contractor (called the “Punch List”) shall be prepared in two parts. The Part-1 part -1 showing the critical/safety items and the Part-2 part-2 showing non-critical/non- non-safety items. The Authority Engineer may issue a Provisional Certificate to the Contractor and the Authority in the form set forth in Schedule-K (the “Provisional Certificate”), provided the items figuring in the Punch List of critical/safety items (Part-1part-1) have been fully completed/attended to. The items figuring in the Punch List (Part-2part-2) of non-critical/non-safety should be completed by contractor in a time frame as stipulated in Clause 12.3.
Appears in 2 contracts
Samples: Engineering, Procurement and Construction, Procurement and Construction Agreement