Purchaser’s Right to Suspend. (a) Purchaser may, at any time after Notice to Seller specifying the effective date of the suspension (a “Suspension Notice”), require Seller to suspend its installation and commissioning work, or any portion thereof. Upon receipt of a Suspension Notice, Seller shall take reasonable steps to suspend its work as soon as reasonably possible and to secure the Project Site for the expected period of the suspension. If Purchaser suspends Seller’s installation and commissioning work without cause (i.e., other than as a result of a Force Majeure Event or Seller Event of Default), Purchaser shall reimburse Seller for reasonable costs and expenses, subject to Cost Substantiation, actually incurred and payable by Seller to protect the Project Site and materials and equipment that would not have been incurred as part of its work. (b) Upon providing a Suspension Notice to Seller, Purchaser shall promptly arrange to discuss with Seller the specific requirements of the suspension and whether or not Purchaser anticipates that demobilization, remobilization, or idle equipment will occur as a result of the suspension. (c) Upon receiving a Suspension Notice, Seller shall discontinue the suspended work, place no further purchase orders (specific to the System) or subcontracts with respect to the suspended work, and promptly make reasonable efforts to obtain reasonably satisfactory suspension terms with respect to all purchase orders, subcontracts, supply contracts, and rental agreements specific to the suspended work. Seller shall continue to perform all other portions of the Services that have not been suspended by Purchaser. (d) Purchaser may, at any time, authorize the resumption of the suspended work or any part thereof, by giving Seller reasonable Notice specifying the part of the suspended work to be resumed and the effective date of such resumption. Seller shall resume the suspended work on the date and the extent specified in such Notice. (e) Seller shall use its employees, Subcontractors, equipment, and materials in such manner, and take such other steps as may be necessary or desirable to minimize the costs associated with the suspended work. During the period of the suspended work, Seller shall secure and protect the suspended work and all materials and equipment to be used or incorporated therein. (f) Purchaser’s suspension of the work as provided in this Section 5.11 shall extend the Project Schedule (including the Expected Commercial Operation Date) on a Day-for-Day basis, or as mutually agreed by the Parties.
Appears in 4 contracts
Samples: Solar Power Purchase Agreement, Solar Power Purchase Agreement, Solar Power Purchase Agreement Services
Purchaser’s Right to Suspend. (a) a. Purchaser may, at any time after Notice to Seller specifying the effective date of the suspension (a “Suspension Notice”), require Seller to suspend its installation and commissioning work, or any portion thereof. Upon receipt of a Suspension Notice, Seller shall take reasonable steps to suspend its work as soon as reasonably possible and to secure the Project Site for the expected period of the suspension. If Purchaser suspends Seller’s installation and commissioning work without cause (i.e., other than as a result of a Force Majeure Event or Seller Event of Default), Purchaser shall reimburse Seller for reasonable costs and expenses, subject to Cost Substantiation, actually incurred and payable by Seller to protect the Project Site and materials and equipment that would not have been incurred as part of its work.
(b) b. Upon providing a Suspension Notice to Seller, Purchaser shall promptly arrange to discuss with Seller the specific requirements of the suspension and whether or not Purchaser anticipates that demobilization, remobilization, or idle equipment will occur as a result of the suspension.
(c) c. Upon receiving a Suspension Notice, Seller shall discontinue the suspended work, place no further purchase orders (specific to the System) or subcontracts with respect to the suspended work, and promptly make reasonable efforts to obtain reasonably satisfactory suspension terms with respect to all purchase orders, subcontracts, supply contracts, and rental agreements specific related to the suspended work. Seller shall continue to perform all other portions of the Services that have not been suspended by Purchaser.
(d) d. Purchaser may, at any time, authorize the resumption of the suspended work or any part thereof, by giving Seller reasonable Notice specifying the part of the suspended work to be resumed and the effective date of such resumption. Seller shall resume the suspended work on the date and the extent specified in such Notice.
(e) e. Seller shall use its employees, Subcontractors, equipment, and materials in such manner, and take such other steps as may be necessary or desirable to minimize the costs associated with the suspended work. During the period of the suspended work, Seller shall secure and protect the suspended work and all materials and equipment to be used or incorporated therein.
(f) f. Purchaser’s suspension of the work as provided in this Section 5.11 shall extend the Project Schedule (including the Expected Commercial Operation Date) on a Day-for-Day basis, or as mutually agreed by the Parties.
Appears in 3 contracts
Samples: Solar Power Purchase Agreement, Solar Power Purchase Agreement Services, Solar Power Purchase Agreement
Purchaser’s Right to Suspend.
(a) Purchaser may, at any time after Notice to Seller specifying the effective date of the suspension (a “Suspension Notice”), require Seller to suspend its installation and commissioning work, or any portion thereof. Upon receipt of a Suspension Notice, Seller shall take reasonable steps to suspend its work as soon as reasonably possible and to secure the Project Site for the expected period of the suspension. If Purchaser suspends Seller’s installation and commissioning work without cause (i.e., other than as a result of a Force Majeure Event or Seller Event of Default), Purchaser shall reimburse Seller for reasonable costs and expenses, subject to Cost Substantiation, actually incurred and payable by Seller to protect the Project Site and materials and equipment that would not have been incurred as part of its work.
(b) Upon providing a Suspension Notice to Seller, Purchaser shall promptly arrange to discuss with Seller the specific requirements of the suspension and whether or not Purchaser anticipates that demobilization, remobilization, or idle equipment will occur as a result of the suspension.
(c) Upon receiving a Suspension Notice, Seller shall discontinue the suspended work, place no further purchase orders (specific to the System) or subcontracts with respect to the suspended work, and promptly make reasonable efforts to obtain reasonably satisfactory suspension terms with respect to all purchase orders, subcontracts, supply contracts, and rental agreements specific to the suspended work. Seller shall continue to perform all other portions of the Services that have not been suspended by Purchaser.
(d) Purchaser may, at any time, authorize the resumption of the suspended work or any part thereof, by giving Seller reasonable Notice specifying the part of the suspended work to be resumed and the effective date of such resumption. Seller shall resume the suspended work on the date and the extent specified in such Notice.
(e) Seller shall use its employees, Subcontractors, equipment, and materials in such manner, and take such other steps as may be necessary or desirable to minimize the costs associated with the suspended work. During the period of the suspended work, Seller shall secure and protect the suspended work and all materials and equipment to be used or incorporated therein.
(f) Purchaser’s suspension of the work as provided in this Section 5.11 shall extend the Project Schedule (including the Expected Commercial Operation Date) on a Day-for-Day basis, or as mutually agreed by the Parties.
Appears in 1 contract
Samples: Solar Power Purchase Agreement
Purchaser’s Right to Suspend. (a) Purchaser may, at any time after Notice to Seller specifying the effective date of the suspension (a “Suspension Notice”), require Seller to suspend its installation and commissioning work, or any portion thereof. Upon receipt of a Suspension Notice, Seller shall take reasonable steps to suspend its work as soon as reasonably possible and to secure the Project Site for the expected period of the suspension. If Purchaser suspends Seller’s installation and commissioning work without cause (i.e., other than as a result of a Force Majeure Event or Seller Event of Default), Purchaser shall reimburse Seller for reasonable costs and expenses, subject to Cost Substantiation, actually incurred and payable by Seller to protect the Project Site and materials and equipment that would not have been incurred as part of its work.
(b) Upon providing a Suspension Notice to Seller, Purchaser shall promptly arrange to discuss with Seller the specific requirements of the suspension and whether or not Purchaser anticipates that demobilization, remobilization, or idle equipment will occur as a result of the suspension.
(c) Upon receiving a Suspension Notice, Seller shall discontinue the suspended work, place no further purchase orders (specific to the System) or subcontracts with respect to the suspended work, and promptly make reasonable efforts to obtain reasonably satisfactory suspension terms with respect to all purchase orders, subcontracts, supply contracts, and rental agreements specific related to the suspended work. Seller shall continue to perform all other portions of the Services that have not been suspended by Purchaser.
(d) Purchaser may, at any time, authorize the resumption of the suspended work or any part thereof, by giving Seller reasonable Notice specifying Noticespecifying the part of the suspended work to be resumed and the effective date of such resumption. Seller shall resume the suspended work on the date and the extent specified in such Notice.
(e) Seller shall use its employees, Subcontractors, equipment, and materials in such manner, and take such other steps as may be necessary or desirable to minimize the costs associated with the suspended work. During the period of the suspended work, Seller shall secure and protect the suspended work and all materials and equipment to be used or incorporated therein.
(f) Purchaser’s suspension of the work as provided in this Section 5.11 shall equitably extend the Project Schedule (including the Expected Commercial Operation Date) on a Day-for-Day basis, or as mutually agreed by the Parties.
Appears in 1 contract
Purchaser’s Right to Suspend.
(a) Purchaser may, at any time after Notice to Seller specifying the effective date of the suspension (a “Suspension Notice”), require Seller to suspend its installation and commissioning work, or any portion thereof. Upon receipt of a Suspension Notice, Seller shall take reasonable steps to suspend its work as soon as reasonably possible and to secure the Project Site for the expected period of the suspension. If Purchaser suspends Seller’s installation and commissioning work without cause (i.e., other than as a result of a Force Majeure Event or Seller Event of Default), Purchaser shall reimburse Seller for reasonable costs and expenses, subject to Cost Substantiation, actually incurred and payable by Seller to protect the Project Site and materials and equipment that would not have been incurred as part of its work.
(b) Upon providing a Suspension Notice to Seller, Purchaser shall promptly arrange to discuss with Seller the specific requirements of the suspension and whether or not Purchaser anticipates that demobilization, remobilization, or idle equipment will occur as a result of the suspension.
(c) Upon receiving a Suspension Notice, Seller shall discontinue the suspended work, place no further purchase orders (specific to the System) or subcontracts with respect to the suspended work, and promptly make reasonable efforts to obtain reasonably satisfactory suspension terms with respect to all purchase orders, subcontracts, supply contracts, and rental agreements specific to the suspended work. Seller shall continue to perform all other portions of the Services that have not been suspended by Purchaser.
(d) Purchaser may, at any time, authorize the resumption of the suspended work or any part thereof, by giving Seller reasonable Notice specifying the part of the suspended work to be resumed and the effective date of such resumption. Seller shall resume the suspended work on the date and the extent specified in such Notice.
(e) Seller shall use its employees, Subcontractors, equipment, and materials in such manner, and take such other steps as may be necessary or desirable to minimize the costs associated with the suspended work. During the period of the suspended work, Seller shall secure and protect the suspended work and all materials and equipment to be used or incorporated therein.. DocuSign Envelope ID: B0A47EA5-ADDC-4324-853B-09D49711DBFF
(f) Purchaser’s suspension of the work as provided in this Section 5.11 shall extend the Project Schedule (including the Expected Commercial Operation Date) on a Day-for-Day basis, or as mutually agreed by the Parties.
Appears in 1 contract