Recording of weather. The Contractor shall erect an effective rainfall gauge on the site and record the daily rainfall figures in a book. Such book shall be handed to the employer’s representative for his signature no later than 12 days after rain that is considered to justify an extension of time occurs.
Appears in 31 contracts
Samples: Bid Agreement, Bid Agreement, Bid Agreement
Recording of weather. The Contractor shall erect an effective rainfall gauge on the site and record the daily rainfall figures f igures in a book. Such book shall be handed to the employer’s representative for his signature no later than 12 days after rain that is considered to justify an extension of time occurs.