Remedial Work Sample Clauses

Remedial Work. (i) Notwithstanding any previous test or certification, the Authority’s Engineer may instruct the Contractor to: (a) remove from the Site and replace any Plant or Materials which are not in accordance with the provisions of this Agreement; (b) remove and re-execute any work which is not in accordance with the provisions of this Agreement and the Specification and Standards; and (c) execute any work which is urgently required for the safety of the Project Highway, whether because of an accident, unforeseeable event or otherwise; provided that in case of any work required on account of a Force Majeure Event, the provisions of Clause 21.6 shall apply. (ii) If the Contractor fails to comply with the instructions issued by the Authority’s Engineer under Clause 11.13 (i), within the time specified in the Authority’s Engineer’s notice or as mutually agreed, the Authority’s Engineer may advise the Authority to have the work executed by another agency. The cost so incurred by the Authority for undertaking such work shall, without prejudice to the rights of the Authority to recover Damages in accordance with the provisions of this Agreement, be recoverable from the Contractor and may be deducted by the Authority from any monies due to be paid to the Contractor.
AutoNDA by SimpleDocs
Remedial Work. If any investigation, site monitoring, containment, clean-up, Restoration or other remedial work (“Remedial Work”) is necessary to comply with any Hazardous Materials Law or order of any Governmental Authority that has or acquires jurisdiction over the Mortgaged Property or the use, operation or improvement of the Mortgaged Property, or is otherwise required by Lender as a consequence of any Prohibited Activity or Condition or to prevent the occurrence of a Prohibited Activity or Condition, Borrower will, by the earlier of (i) the applicable deadline required by Hazardous Materials Law, or (ii) 30 days after Notice from Lender demanding such action, begin performing the Remedial Work, and thereafter diligently prosecute it to completion, and must in any event complete the work by the time required by applicable Hazardous Materials Law. If Borrower fails to begin on a timely basis or diligently prosecute any required Remedial Work, Lender may, at its option, cause the Remedial Work to be completed, in which case Borrower will reimburse Lender on demand for the cost of doing so. Any reimbursement due from Borrower to Lender will become part of the Indebtedness as provided in Section 9.02.
Remedial Work. In the event any investigation or monitoring of site conditions or any clean-up, containment, restoration, removal or other remedial work (“Remedial Work”) is required (a) under any Environmental Law, (b) by any judicial, arbitral or administrative order, (c) in order to comply with any agreements affecting any of the Properties, or (d) to maintain any of the Properties in a standard of environmental condition which prevents the release or generation of any Hazardous Materials except for Permitted Hazardous Substances, Indemnitor shall perform or cause to be performed such Remedial Work; provided, however, that Indemnitor may withhold commencement of such Remedial Work pending resolution of any good faith contest regarding the application, interpretation or validity of any law, regulation, order or agreement, subject to the requirements of Section 7 below. All Remedial Work shall be conducted (i) in a diligent and timely fashion by a licensed environmental engineer, (ii) pursuant to a detailed written plan for the Remedial Work approved by any Governmental Agency with a legal or contractual right to such approval, (iii) with such insurance coverage pertaining to liabilities arising out of the Remedial Work as is then customarily maintained with respect to such activities and (iv) only following receipt of all required permits, licenses or approvals. In addition, Indemnitor shall submit to the Banks promptly upon receipt or preparation, copies of any and all reports, studies, analyses, correspondence, governmental comments or approvals, proposed removal or other Remedial Work contracts and similar information prepared or received by Indemnitor in connection with any Remedial Work or Hazardous Materials relating to any of the Properties. All costs and expenses of such Remedial Work shall be paid by Indemnitor, including, without limitation, the charges of the Remedial Work contractors and the consulting environmental engineer, any taxes or penalties assessed in connection with the Remedial Work and the Banks’ reasonable fees and costs incurred in connection with monitoring or review of such Remedial Work. In the event Indemnitor should fail to commence or cause to be commenced such Remedial Work, in a timely fashion, or fail diligently to prosecute to completion, such Remedial Work, the Administrative Agent following consent of the Required Lenders (following thirty (30) days written notice to Indemnitor) may, but shall not be required to, cause such Remedia...
Remedial Work. If any investigation, site monitoring, containment, clean-up, restoration or other remedial work ("Remedial Work") is necessary to comply with any Hazardous Materials Laws or order of any Governmental Authority that has or acquires jurisdiction over the Property, the Improvements or the use, operation or improvement of the Property under any Hazardous Materials Laws, Borrower shall, by the earlier of (1) the applicable deadline required by Hazardous Materials Laws or (2) 30 days after notice from Lender demanding such action, begin performing the Remedial Work, and thereafter diligently prosecute it to completion, and shall in any event complete such work by the time required by applicable Hazardous Materials Laws. If Borrower fails to begin on a timely basis or diligently prosecute any required Remedial Work, Lender may, at its option, cause the Remedial Work to be completed, in which case Borrower shall reimburse Lender on demand for the cost of doing so. Any reimbursement due from Borrower to Lender shall become part of the Loan Obligations.
Remedial Work. Notwithstanding any previous test or certification, the Engineer may instruct the Contractor to: (a) remove from the Site and redeliver and replace any Plant or Materials which is not in accordance with the Contract; (b) remove and re-execute any other work which is not in accordance with the Contract; and (c) execute any work which is urgently required for the safety of the Works, whether because of an accident, unforeseeable event or otherwise. The Contractor shall comply with the instruction within a reasonable time, which shall be the time (if any) specified in the instruction, or immediately if urgency is specified under sub-paragraph (c). If the Contractor fails to comply with the instruction, the Employer shall be entitled to employ and pay other persons to carry out the work. Except to the extent that the Contractor would have been entitled to payment for the work, the Contractor shall subject to sub-clause 2.5 [Employer's Claims] pay to the Employer all costs arising from this failure.
Remedial Work. If any investigation, site monitoring, containment, clean-up, restoration or other remedial work (“Remedial Work”) is necessary to comply with any Hazardous Materials Law or order of any Governmental Authority that has or acquires jurisdiction over the Property, the Improvements or the use, operation or improvement of the Property under any Hazardous Materials Law, Borrower shall, by the earlier of (a) the applicable deadline required by Hazardous Materials Law or (b) thirty (30) days after notice from Lender demanding such action, begin performing the Remedial Work, and thereafter diligently prosecute it to completion, and shall in any event complete such work by the time required by applicable Hazardous Materials Law. If Borrower fails to begin on a timely basis or diligently prosecute any required Remedial Work, Lender may, at its option and after five (5) days' prior written notice, cause the Remedial Work to be completed, in which case Borrower shall reimburse Lender on demand for the cost of doing so. Any reimbursement due from Borrower to Lender shall become part of the Loan Obligations.
Remedial Work. 36.1 The Design-Builder will do all remedial work that may be required to make the several parts of the Work comply with the Statement of Requirements. 36.2 The Design-Builder will coordinate the Time Schedule for the Work to ensure that the requirement under Section 36.1 is kept to a minimum. 36.3 Remedial work will be performed by specialists familiar with the materials affected and will be performed in a manner to neither damage nor endanger any Work.
AutoNDA by SimpleDocs
Remedial Work. If any investigation, site monitoring, containment, clean-up, removal, restoration or other remedial work of any kind or nature with respect to any Borrower Entity's Properties is required to be performed by them under any applicable local, state or federal law or regulation, any judicial order, or by any governmental or non-governmental entity or Person because of, or in connection with, the current or future presence, suspected presence, release or suspected release of a Hazardous Substance in or into the air, soil, groundwater, surface water or soil vapor at, on, about, under, or within any of a Borrower Entity's Property (or any portion thereof), Borrower shall within 30 days after written demand for performance thereof (or such shorter period of time as may be required under applicable law, regulation, order or agreement), commence and thereafter diligently prosecute to completion, all such remedial work.
Remedial Work. (i) StadCo Remedial Work. StadCo shall be responsible for performing or causing to be performed, and for paying the cost of performing, such corrective or remedial actions (including all investigations, monitoring, etc.) required by Applicable Law to be performed with respect to any Environmental Event or any Hazardous Materials present at, in, on or under the Premises (the “StadCo Remedial Work”); provided, however, under no circumstances shall StadCo’s Remedial Work include the Authority Remedial Work. Prior to undertaking any StadCo Remedial Work with an anticipated cost in excess of One Million and No/100 Dollars ($1,000,000.00), StadCo shall obtain the Approval of the Authority of the steps StadCo proposes to take with respect to any StadCo Remedial Work and StadCo shall select, subject to the Approval of the Authority, an environmental consultant or engineer to oversee the StadCo Remedial Work. To the extent the Authority has a claim against any third Person with respect to any Environmental Event that is included in the StadCo Remedial Work, the Authority hereby assigns to StadCo, as of the date StadCo is required to perform the related StadCo Remedial Work, such claim insofar as it relates to the cost of the StadCo Remedial Work or any damages suffered by StadCo in connection with such Environmental Event, and the Authority shall reasonably cooperate with StadCo and provide StadCo with such information as StadCo shall reasonably request in pursuing such claim against any such Person.
Remedial Work. (i) Notwithstanding any previous test or certification, the Authority’s Engineer may instruct the Contractor to: (a) remove from the Site and replace any Plant or Materials which are not in accordance with the provisions of this Agreement; (b) remove and re-execute any work which is not in accordance with the provisions of this Agreement and the Specification and Standards; and (c) execute any work which is urgently required for the safety of the Project Highway, whether because of an accident, unforeseeable event or otherwise; provided that in case of any work required on account of a Force Majeure Event, the provisions of Clause 21.6 shall apply. (ii) If the Contractor fails to comply with the instructions issued by the Authority’s Engineer under Clause 11.13 (i), within the time specified in the Authority’s
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!