Remedial Work. (i) Notwithstanding any previous test or certification, the Authority’s Engineer may instruct the Contractor to: (a) remove from the Site and replace any Plant or Materials which are not in accordance with the provisions of this Agreement; (b) remove and re-execute any work which is not in accordance with the provisions of this Agreement and the Specification and Standards; and (c) execute any work which is urgently required for the safety of the Project Highway, whether because of an accident, unforeseeable event or otherwise; provided that in case of any work required on account of a Force Majeure Event, the provisions of Clause 21.6 shall apply. (ii) If the Contractor fails to comply with the instructions issued by the Authority’s Engineer under Clause 11.13 (i), within the time specified in the Authority’s
Appears in 4 contracts
Samples: Contract Agreement, Construction Contract, Contract Agreement
Remedial Work. (i) Notwithstanding any previous test or certification, the Authority’s Authority Engineer may instruct mayinstruct the Contractor to:
(a) remove from the Site and replace any Plant or Materials which are not in accordance inaccordance with the provisions of this Agreement;
(b) remove and & re-execute any work which is not in accordance with the provisions of this ofthis Agreement and the Specification and Standards; and
(c) execute any work which is urgently required for the safety of the Project HighwayRailway Project, whether because of an accident, unforeseeable event or otherwise; provided that in thatin case of any work which is required on account of a Force Majeure Event, the provisions of Clause 21.6 19.6 shall apply.
(ii) If the Contractor fails to comply with the instructions issued by the Authority’s Engineer under Clause 11.13 (i), within the time specified in the Authority’s
Appears in 4 contracts
Samples: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement
Remedial Work. (i) Notwithstanding any previous test or certification, the Authority’s Engineer may instruct the Contractor to:
(a) remove from the Site and replace any Plant or Materials which are not in accordance with the provisions of this Agreement;
(b) remove and re-execute any work which is not in accordance with the provisions of this Agreement and the Specification and Standards; and
(c) execute any work which is urgently required for the safety of the Project Highway, whether because of an accident, unforeseeable event or otherwise; provided that in case of any work required on account of a Force Majeure Event, the provisions of Clause 21.6 shall apply.
(ii) If the Contractor fails to comply with the instructions issued by the Authority’s Engineer under Clause 11.13 (i), within the time specified in the Authority’sImprovement and widening to two lane with paved shoulder of road from Km 21.100 to Km
Appears in 1 contract
Samples: Contract Agreement