Repairs and maintenance works. 6.1. EUS shall inform the Shipper about relevant repair and maintenance works on the transmission system of EUS in writing by letter or e-mail at the latest forty-two (42) days before the beginning of such repair works. 6.2. If a previously defined and planned repair period has to be changed, then such a modification must be communicated to the Shipper as soon as possible. 6.3. As soon as EUS is aware of necessary but unforeseen repair works on a transmission network, which might limit or interrupt transmission for the Shipper, EUS is obliged to inform without any delay the Shipper on the duration of such works by a letter or an e-mail as well as to inform about the scope of such works.
Appears in 4 contracts
Samples: Framework Contract on Access to the Transmission Network and Gas Transmission, Framework Contract on Access to the Transmission Network and Gas Transmission, Framework Contract on Access to the Transmission Network and Gas Transmission
Repairs and maintenance works. 6.17.1. EUS shall inform the Shipper about relevant repair and maintenance works on the transmission system of EUS in writing by letter or e-mail at the latest forty-two (42) days Days before the beginning of such repair works.
6.27.2. If a previously defined and planned repair period has to be changed, then such a modification must be communicated to the Shipper as soon as possible.
6.37.3. As soon as EUS is aware of necessary but unforeseen repair works on a transmission network, which might limit or interrupt transmission for the Shipper, EUS is obliged to inform without any delay the Shipper on the duration of such works by a letter letter, email or an e-mail a fax as well as to inform about the scope of such works.
Appears in 1 contract
Samples: Framework Contract