Replacement of the Members of the Project Team. 8.2.1. Unless otherwise expressly provided, the Supplier must obtain the IAA’s prior written approval before appointing any employees and/or subcontractors to carry out the Works or any part thereof. The Supplier shall not replace any subcontractor and/or member of the Project's Team, except under exceptional circumstances and subject to the receipt of the IAA's prior written approval. Without limiting the generality of the foregoing, it is hereby clarified that any such substitute subcontractor shall be required to comply with the provisions of this Section 8. 8.2.2. The IAA reserves the right to demand, at any time, at its sole discretion, the replacement and/or removal of any subcontractor and/or member of the Project Team, by an advance written notice of 45 days. Such replacement and/or removal will not derogate from any of the Supplier's obligations under the Contract, and in particular the Supplier’s obligation to meet the Schedule. 8.2.3. Without derogating from the above, any refusal by the IAA to approve any of the Supplier's subcontractors and/or request to replace any member of the Project Team shall be for reasonable grounds, such as, but not limited to, the security regulations and instructions of any governmental authority by which the IAA is bound, however the IAA shall not be required to disclose the reasoning behind such decision to the Supplier.
Appears in 1 contract
Samples: Contract for Design, Supply, Installation, Commissioning and Support of Passenger Boarding Bridges
Replacement of the Members of the Project Team. 8.2.19.2.1. Unless otherwise expressly provided, the Supplier must obtain the IAA’s prior written approval before appointing any employees and/or subcontractors to carry out the Works or any part thereof. The Supplier shall not replace any subcontractor and/or member of the Project's Project Team, except under exceptional circumstances and subject to the receipt of the IAA's prior written approval. Without limiting the generality of the foregoing, it is hereby clarified that any such substitute subcontractor shall be required to comply with the provisions of this Section 89.
8.2.29.2.2. The IAA reserves the right to demand, at any time, at its sole discretion, the replacement and/or removal of any subcontractor and/or member of the Project Team, by an advance written notice of 45 days. Such replacement and/or removal will not derogate from any of the Supplier's obligations under the Contract, and in particular the Supplier’s obligation to meet the Scheduleschedule.
8.2.39.2.3. Without derogating from the provisions of this section 9 above, any refusal by the IAA to approve any of the Supplier's subcontractors and/or request to replace any member of the Project Team shall be for reasonable grounds, such as, but not limited to, subject to the security regulations and instructions of any governmental authority by which the IAA is bound, however the IAA shall not be required to disclose the reasoning behind such decision to the Supplier.
Appears in 1 contract
Replacement of the Members of the Project Team. 8.2.110.2.1. Unless otherwise expressly provided, the Supplier must obtain the IAA’s prior written approval before appointing any employees and/or subcontractors to carry out the Works or any part thereof. The Supplier shall not replace any subcontractor and/or member of the Project's Team, except under exceptional circumstances and subject to the receipt of the IAA's prior written approval. Without limiting the generality of the foregoing, it is hereby clarified that any such substitute subcontractor shall be required to comply with the provisions of this Section 810.
8.2.210.2.2. The IAA reserves the right to demand, at any time, at its sole discretion, the replacement and/or removal of any subcontractor and/or member of the Project Team, by an advance written notice of 45 days. Such replacement and/or removal will not derogate from any of the Supplier's obligations under the Contract, and in particular the Supplier’s obligation to meet the Schedule.
8.2.310.2.3. Without derogating from the provisions of this section 10 above, any refusal by the IAA to approve any of the Supplier's subcontractors and/or request to replace any member of the Project Team shall be for reasonable grounds, such as, but not limited to, subject to the security regulations and instructions of any governmental authority by which the IAA is bound, however the IAA shall not be required to disclose the reasoning behind such decision to the Supplier.
Appears in 1 contract
Replacement of the Members of the Project Team. 8.2.19.2.1. Unless otherwise expressly provided, the Supplier must obtain the IAA’s prior written approval before appointing any employees and/or subcontractors to carry out the Works or any part thereof. The Supplier shall not replace any subcontractor and/or member of the Project's Project Team, except under exceptional circumstances and subject to the receipt of the IAA's prior written approval. Without limiting the generality of the foregoing, it is hereby clarified that any such substitute subcontractor shall be required to comply with the provisions of this Section 89.
8.2.29.2.2. The IAA reserves the right to demand, at any time, at its sole discretion, the replacement and/or removal of any subcontractor and/or member of the Project Team, by an advance written notice of 45 days. Such replacement and/or removal will not derogate from any of the Supplier's obligations under the Contract, and in particular the Supplier’s obligation to meet the Schedule.
8.2.39.2.3. Without derogating from the provisions of this section 9 above, any refusal by the IAA to approve any of the Supplier's subcontractors and/or request to replace any member of the Project Team shall be for reasonable grounds, such as, but not limited to, subject to the security regulations and instructions of any governmental authority by which the IAA is bound, however the IAA shall not be required to disclose the reasoning behind such decision to the Supplier.