Common use of Reporting Requirements and Documents to be provided Clause in Contracts

Reporting Requirements and Documents to be provided. During the Construction Period, the Concessionaire shall submit to the Project Engineer/ NNR, Monthly Progress Report (for each calendar month or part thereof) within 5 working days of the last day of the month. The report shall review the progress made, identify slippages, if any, and project the future activities to be undertaken (including rectifications), operations and maintenance activities undertaken and would, inter alia, include the following:

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Reporting Requirements and Documents to be provided. 4.6.1 During the Construction Period, the Concessionaire shall submit to the Project Engineer/ NNRSIIDCUL, Monthly Progress Report (for each calendar month or part thereof) within 5 working days of the last day of the month. The report shall review the progress made, identify slippages, if any, and project the future activities to be undertaken (including rectifications), operations and maintenance activities undertaken and would, inter alia, include the following:

Appears in 1 contract

Samples: Draft Concession Agreement

Reporting Requirements and Documents to be provided. 2.6.1 During the Construction Period, the Concessionaire shall submit to the Project Engineer/ NNROfficer / CoC, Monthly Progress Report (for each calendar month or part thereof) within 5 five working days of the last day of the monthMonth. The report shall review the progress made, identify identified slippages, if any, and project the future activities to be undertaken (including rectifications), operations and maintenance activities undertaken under taken and would, inter alia, include the following:

Appears in 1 contract

Samples: Draft Concession Agreement

Reporting Requirements and Documents to be provided. 2.6.1 During the Construction Period, the Concessionaire shall submit to the Project Engineer/ NNR, Independent Engineer/NHIDCL Monthly Progress Report (for each calendar month or part thereof) within 5 working days of the last day of the month. The report shall review the progress made, identify slippages, if any, and project the future activities to be undertaken (including rectifications), operations and maintenance activities undertaken and would, inter alia, include the following:

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Reporting Requirements and Documents to be provided. 6.1 During the Construction Period, the Concessionaire Developer shall submit to the Project Engineer/ NNRNRDA, Monthly Progress Report (for each calendar month or part thereof) within 5 (five) working days of the last day of the month. The report shall review the progress made, identify slippages, if any, and project the future activities to be undertaken (including rectifications), operations and maintenance activities undertaken and would, inter alia, include the following:

Appears in 1 contract

Samples: Project Development and Implementation Agreement