Common use of REQUIREMENTS FOR SUBMISSION OF DOCUMENTS Clause in Contracts

REQUIREMENTS FOR SUBMISSION OF DOCUMENTS. INFORMATION ANDDATA BY THE CONTRACTOR 3.2.1. The Contractor shall submit to the Employer all documents in accordance with an approved schedule of submissions and shall submit any further information (in the form of drawings, documents, manuals, literature, reports etc.) when asked by the Employer while commenting/approving any drawings/documents etc. 3.2.2. The documents which are subject to the approval of the Employer shall be identified by the Contractor with the stamp "FOR APPROVAL". All other documents shall be submitted to the Employer for information and shall be identified by the Contractor with the stamp "FOR INFORMATION". 3.2.3. The sequence of submission of the documents shall be subject to the approval of the Employer. The sequence of submissions of all documents shall be such that the necessary information is available to enable the Employer to approve or comment the document. 3.2.4. The Contractor shall supply 4 hard copies of all drawings and documents. 3.2.5. In case a "SUBSEQUENT" revision of any document is made due to any reason whatsoever, a revision of the same, highlighting the changes shall be resubmitted for the Employer's specific approval/ information.

Appears in 26 contracts

Samples: Full Turnkey Contract, Turnkey Contract, Full Turnkey Contract

AutoNDA by SimpleDocs

REQUIREMENTS FOR SUBMISSION OF DOCUMENTS. INFORMATION ANDDATA BY THE CONTRACTOR 3.2.1. The Contractor shall submit to the Employer all documents in accordance with an approved schedule of submissions and shall submit any further information (( in the form of drawings, documents, manuals, literature, reports etc.) when asked by the Employer while commenting/commenting/ approving any drawings/drawings/ documents etc. 3.2.2. The documents which are subject to the approval of the Employer shall be identified by the Contractor with the stamp "FOR APPROVAL". All other documents shall be submitted to the Employer for information and shall be identified by the Contractor with the stamp "FOR INFORMATION". 3.2.3. The sequence of submission of the documents shall be subject to the approval of the Employer. The sequence of submissions of all documents shall be such that the necessary information is available to enable the Employer to approve or comment the document. 3.2.4. The Contractor shall supply 4 hard copies of all drawings and documents. 3.2.5. In case a "SUBSEQUENT" revision of any document is made due to any reason whatsoever, a revision of the same, highlighting the changes shall be resubmitted for the Employer's specific approval/ information.

Appears in 1 contract

Samples: Partial Turnkey Contract

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!