RESOLUTION OF AGREEMENT CLAIMS. A. For purposes of this Section, the term "Claim" has the meaning as set forth in Public Contract Code section 20104(b)(2), as that section may be amended from time to time. Section 20104(b) (2) currently defines "claim" to mean a separate demand by the Contractor for (a) time extension, (b) payment of money or damages arising from work done by or on behalf of the Contractor pursuant to the Construction Services Agreement and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (c) an amount the payment of which is disputed by the District. B. Notwithstanding any other provision herein, all claims shall be resolved pursuant to the claims resolution process set forth in Public Contract Code section 9204. Furthermore, the resolution of all claims that are equal to or less than Three Hundred Seventy-five Thousand Dollars ($375,000) shall also comply with the claims resolution procedures set forth in Public Contract Code section 20104 et seq., as may be amended from time to time, and which provisions are incorporated herein by reference. C. For claims not addressed in Section 36 (A) and (B) above, the dispute review process set forth in this subsection (C) shall apply (1) The dispute review process set forth in this Section 36 shall be administered by the American Arbitration Association (AAA) and governed by their rules in effect at the time of filing, or by any other neutral organization agreed to by the parties (hereinafter called "Administrator".) (2) If a dispute arises out of, or relates to this Construction Services Agreement or the breach thereof, and if said dispute cannot be settled through normal contract negotiations, the parties agree to first endeavor to settle the dispute using mediation. (3) The costs for all mediation, including the Administrative fees and mediator compensation, will be shared equally by all parties. Fees shall be jointly negotiated by all parties directly with the Administrator. If all parties agree, then the mediation costs may increase as required for resolution of the dispute. The expenses of witnesses for any party shall be paid by the party producing such witnesses. (4) A single mediator, acceptable to all parties, shall be used to mediate the dispute. The mediator will be knowledgeable in construction aspects and will be selected from lists furnished by the Administrator. The initial mediation session shall commence within thirty (30) days of filing, unless otherwise agreed by the parties, or at the direction of the mediator. (5) Mediation hearings will be conducted in an informal manner and discovery will not be allowed unless agreed by all parties. All discussions, statements, or admissions will be confidential to the proceedings and will not be used for any other purpose as it relates to the party's legal position. (6) Spokespersons shall be limited to the District, Contractor, Subcontractor, and Supplier personnel and their consultants. Contractor, Subcontractor and Supplier may have an attorney present and shall advise the other parties no less than five
Appears in 4 contracts
Samples: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement
RESOLUTION OF AGREEMENT CLAIMS. A. For purposes of this Section, the term "Claim" has the meaning as set forth in Public Contract Code section 20104(b)(2), as that section may be amended from time to time. Section 20104(b) (2) currently defines "claim" to mean a separate demand by the Contractor for (a) time extension, (b) payment of money or damages arising from work done by or on behalf of the Contractor pursuant to the Construction Services Agreement and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (c) an amount the payment of which is disputed by the District.
B. Notwithstanding any other provision herein, all claims shall be resolved pursuant to the claims resolution process set forth in Public Contract Code section 9204. Furthermore, the resolution of all claims that are equal to or less than Three Hundred Seventy-five Thousand Dollars ($375,000) shall also comply with the claims resolution procedures set forth in be resolved pursuant to Public Contract Code section 20104 et seq., as may be amended from time to time, and which provisions are incorporated herein by reference.
C. For claims not addressed in Section 36 (A) and (B) above, the dispute review process set forth in this subsection (C) shall apply
(1) The dispute review process set forth in this Section 36 shall be administered by the American Arbitration Association (AAA) and governed by their rules in effect at the time of filing, or by any other neutral organization agreed to by the parties (hereinafter called "Administrator".)
(2) If a dispute arises out of, or relates to this Construction Services Agreement or the breach thereof, and if said dispute cannot be settled through normal contract negotiations, the parties agree to first endeavor to settle the dispute using mediation.
(3) The costs for all mediation, including the Administrative fees and mediator compensation, will be shared equally by all parties. Fees shall be jointly negotiated by all parties directly with the Administrator. If all parties agree, then the mediation costs may increase as required for resolution of the dispute. The expenses of witnesses for any party shall be paid by the party producing such witnesses.
(4) A single mediator, acceptable to all parties, shall be used to mediate the dispute. The mediator will be knowledgeable in construction aspects and will be selected from lists furnished by the Administrator. The initial mediation session shall commence within thirty (30) days of filing, unless otherwise agreed by the parties, or at the direction of the mediator.
(5) Mediation hearings will be conducted in an informal manner and discovery will not be allowed unless agreed by all parties. All discussions, statements, or admissions will be confidential to the proceedings and will not be used for any other purpose as it relates to the party's legal position.
(6) Spokespersons shall be limited to the District, Contractor, Subcontractor, and Supplier personnel and their consultants. Contractor, Subcontractor and Supplier may have an attorney present and shall advise the other parties no less than five
Appears in 3 contracts
Samples: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement
RESOLUTION OF AGREEMENT CLAIMS. A. For purposes of this Section, the term "Claim" has the meaning as set forth in Public Contract Code section 20104(b)(2), as that section may be maybe amended from time to time. Section 20104(b) (220104(b)(2) currently defines "“claim" ” to mean a separate demand by the Contractor for (a) a time extension, (b) payment of money or damages arising from work done by by, or on behalf of the of, Contractor pursuant to the Construction Services Agreement and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (c) an amount the payment of which is disputed by the District.
B. Notwithstanding any other provision herein, all claims shall be resolved pursuant to the claims resolution process set forth in Public Contract Code section 9204. Furthermore, the resolution of all claims that are equal to or less than Three Hundred Seventy-five Five Thousand Dollars ($375,000) shall also comply with the claims resolution procedures set forth in Public Contract Code section 20104 et seq., as may be amended from time to time, and unless in conflict with Public Contract Code section 9204 in which provisions are incorporated herein by referencecase section 9204 takes precedence.
C. For claims not addressed in Section 36 (A) and (B) 35, subsections A. or B. above, the dispute review process set forth in this subsection (C) C. shall apply.
(1) . The dispute review process set forth in this Section 36 35 shall be administered by the American Arbitration Association (AAA) and governed by their rules in effect at the time of filing, or by any other neutral organization agreed to by the parties (hereinafter called the "Administrator".)
(2) . If a dispute arises out of, or relates to this Construction Services Agreement or the breach thereof, and if said dispute cannot be settled through normal contract negotiations, the parties agree to first endeavor to settle the dispute using mediation.
(3) . The costs for all mediation, including the Administrative Administrator fees and mediator compensation, will be shared equally by all parties. Fees shall be jointly negotiated by all parties directly with the Administrator. If all parties agree, then the mediation costs may increase as required for resolution of the dispute. The expenses of witnesses for any party shall be paid by the party producing such witnesses.
(4) . A single mediator, acceptable to all parties, shall be used to mediate the dispute. The mediator will be knowledgeable in construction aspects and will be selected from lists furnished by the Administrator. The initial mediation session shall commence within thirty (30) days of filing, unless otherwise agreed by the parties, or at the direction of the mediator.
(5) Mediation . Mediator hearings will be conducted in an informal manner and discovery will not be allowed alloyed unless agreed by all parties. All discussions, statements, or admissions will be confidential to the proceedings and will not be used for any other purpose as it relates to the party's legal position.
(6) . Spokespersons shall be limited to the District, Contractor, Subcontractor, and Supplier personnel and their consultants. Contractor, Subcontractor and Supplier may have an attorney present and shall advise the other parties no less than fivefive (5) business days before the mediation so that the other parties may also have their attorneys' present.
7. Any resultant agreements from mediation shall be documented in writing, and may be used as the basis for a change order or other directive as appropriate. All mediation results and documentation shall be non-binding and inadmissible for any purpose in any legal proceedings, in accordance with Evidence Code section 1152, unless such admission is otherwise agreed to in writing by all parties. Mediators shall not be subject to any subpoena or liability and their actions shall not be subject to discovery.
8. If mediation is unsuccessful, the parties thereafter may, but are not required to, agree to submit the matter to the Administrator for binding arbitration. If the parties so agree to arbitrate, the following procedure shall govern such arbitration, unless the parties otherwise agree in writing. The parties agree that the matter shall be submitted to one (1) arbitrator, unless they agree in writing to three (3) arbitrators. A judgment of a court having competent jurisdiction may be entered upon the award, and such judgment shall be enforceable as a final judgment to the fullest extent under the law. The parties agree to evenly split all arbitration and arbitrator(s)' fees and expenses, subject to readjustment by the arbitrator as part of any award. The arbitration shall be subject to, and proceed in accordance with California Code of Civil Procedure sections 1280 through 1294.
Appears in 1 contract
Samples: Construction Services Agreement
RESOLUTION OF AGREEMENT CLAIMS. A. For purposes of this Section, the term "Claim" has the meaning as set forth in Public Contract Code section 20104(b)(2), as that section may be maybe amended from time to time. Section 20104(b) (220104(b)(2) currently defines "“claim" ” to mean a separate demand by the Contractor for (a) a time extension, (b) payment of money or damages arising from work done by by, or on behalf of the of, Contractor pursuant to the Construction Services Agreement and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (c) an amount the payment of which is disputed by the District.
B. Notwithstanding any other provision herein, all claims shall be resolved pursuant to the claims resolution process set forth in Public Contract Code section 9204. Furthermore, the resolution of all claims that are equal to or less than Three Hundred Seventy-five Five Thousand Dollars ($375,000) shall also comply with the claims resolution procedures set forth in Public Contract Code section 20104 et seq., as may be amended from time to time, and unless in conflict with Public Contract Code section 9204 in which provisions are incorporated herein by referencecase section 9204 takes precedence.
C. For claims not addressed in Section 36 (A) and (B) 35, subsections A. or B. above, the dispute review process set forth in this subsection (C) C. shall apply.
(1) . The dispute review process set forth in this Section 36 35 shall be administered by the American Arbitration Association (AAA) and governed by their rules in effect at the time of filing, or by any other neutral organization agreed to by the parties (hereinafter called the "Administrator".)
(2) . If a dispute arises out of, or relates to this Construction Services Agreement or the breach thereof, and if said dispute cannot be settled through normal contract negotiations, the parties agree to first endeavor to settle the dispute using mediation.
(3) . The costs for all mediation, including the Administrative Administrator fees and mediator compensation, will be shared equally by all parties. Fees shall be jointly negotiated by all parties directly with the Administrator. If all parties agree, then the mediation costs may increase as required for resolution of the dispute. The expenses of witnesses for any party shall be paid by the party producing such witnesses.
(4) . A single mediator, acceptable to all parties, shall be used to mediate the dispute. The mediator will be knowledgeable in construction aspects and will be selected from lists furnished by the Administrator. The initial mediation session shall commence within thirty (30) days of filing, unless otherwise agreed by the parties, or at the direction of the mediator.
(5) Mediation . Mediator hearings will be conducted in an informal manner and discovery will not be allowed unless agreed by all parties. All discussions, statements, or admissions will be confidential to the proceedings and will not be used for any other purpose as it relates to the party's legal position.
(6) . Spokespersons shall be limited to the District, Contractor, Subcontractor, and Supplier personnel and their consultants. Contractor, Subcontractor and Supplier may have an attorney present and shall advise the other parties no less than fivefive (5) business days before the mediation so that the other parties may also have their attorneys' present.
7. Any resultant agreements from mediation shall be documented in writing, and may be used as the basis for a change order or other directive as appropriate. All mediation results and documentation shall be non-binding and inadmissible for any purpose in any legal proceedings, in accordance with Evidence Code section 1152, unless such admission is otherwise agreed to in writing by all parties. Mediators shall not be subject to any subpoena or liability and their actions shall not be subject to discovery.
8. If mediation is unsuccessful, the parties thereafter may, but are not required to, agree to submit the matter to the Administrator for binding arbitration. If the parties so agree to arbitrate, the following procedure shall govern such arbitration, unless the parties otherwise agree in writing. The parties agree that the matter shall be submitted to one (1) arbitrator, unless they agree in writing to three (3) arbitrators. A judgment of a court having competent jurisdiction may be entered upon the award, and such judgment shall be enforceable as a final judgment to the fullest extent under the law. The parties agree to evenly split all arbitration and arbitrator(s)' fees and expenses, subject to readjustment by the arbitrator as part of any award. The arbitration shall be subject to, and proceed in accordance with California Code of Civil Procedure sections 1280 through 1294.2. If the parties do not agree to binding arbitration, neither party is prevented from pursuing other legal remedies.
Appears in 1 contract
Samples: Construction Services Agreement
RESOLUTION OF AGREEMENT CLAIMS. A. For purposes of this Sectionsection, the term "Claim" has the meaning as set forth in Public Contract Code section 20104(b)(2), as that section may be amended from time to time. Section 20104(b) (220104(b)(2) currently defines "claim" to mean a separate demand by the Contractor for (a) time extension, (b) payment of money or damages arising from work done by or on behalf of the Contractor pursuant to the Construction Services Agreement and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (c) an amount the payment of which is disputed by the District.
B. Notwithstanding any other provision herein, all claims shall be resolved pursuant to the claims resolution process set forth in Public Contract Code section 9204. Furthermore, the resolution of all claims that are equal to or less than Three Hundred Seventy-five Thousand Dollars ($375,000) shall also comply with the claims resolution procedures set forth in be resolved pursuant to Public Contract Code section 20104 et seq., as may be amended from time to time, and which provisions are incorporated herein by reference.
C. For claims not addressed in Section 36 34 (A) and (B) above, the dispute review process set forth in this subsection (C) shall apply
(1) The dispute review process set forth in this Section 36 34 shall be administered by the American Arbitration Association (AAA) and governed by their rules in effect at the time of filing, or by any other neutral organization agreed to by the parties (hereinafter called "Administrator".)
(2) If a dispute arises out of, or relates to this Construction Services Agreement or the breach thereof, and if said dispute cannot be settled through normal contract negotiations, the parties agree to first endeavor to settle the dispute using mediation.
(3) The costs for all mediation, including the Administrative fees and mediator compensation, will be shared equally by all parties. Fees shall be jointly negotiated by all parties directly with the Administrator. If all parties agree, then the mediation costs may increase as required for resolution of the dispute. The expenses of witnesses for any party shall be paid by the party producing such witnesses.
(4) A single mediator, acceptable to all parties, shall be used to mediate the dispute. The mediator will be knowledgeable in construction aspects and will be selected from lists furnished by the Administrator. The initial mediation session shall commence within thirty (30) days of filing, unless otherwise agreed by the parties, or at the direction of the mediator.
(5) Mediation hearings will be conducted in an informal manner and discovery will not be allowed unless agreed by all parties. All discussions, statements, or admissions will be confidential to the proceedings and will not be used for any other purpose as it relates to the party's legal position.
(6) Spokespersons shall be limited to the District, Contractor, Subcontractor, and Supplier personnel and their consultants. Contractor, Subcontractor and Supplier may have an attorney present and shall advise the other parties no less than fivefive (5) business days before the mediation so that the other parties may also have their attorneys present.
(7) Any resultant agreements from mediation shall be documented in writing, and may be used as the basis for a change order or other directive as appropriate. All mediation results and documentation shall be non-binding and inadmissible for any purpose in any legal proceedings, in accordance with Evidence Code Section 1152, unless such admission is otherwise agreed in writing by all parties. Mediators shall not be subject to any subpoena or liability and their actions shall not be subject to discovery.
(8) If mediation is unsuccessful, the parties thereafter may, but are not required to, agree to submit the matter to the Administrator for binding arbitration. If the parties so agree to arbitrate, the following provision shall govern such arbitration, unless the parties otherwise agree in writing. The parties agree that the matter shall be submitted to one (1) arbitrator, unless they agree in writing to three (3) arbitrators. A judgment of a court having competent jurisdiction may be entered upon the award, and such judgment shall be enforceable as a final judgment to the fullest extent under the law. The parties agree to split evenly all arbitration and arbitrator(s)' fees and expenses, subject to readjustment by the arbitrator as part of any award. The arbitration shall be subject to, and proceed in accordance with California Code of Civil Procedure, Sections 1280 through 1294.
Appears in 1 contract