REVISED PROGRAMME Sample Clauses

REVISED PROGRAMME. Add at the end of the first paragraph; ‘Failure by the Contractor to submit the Revised Work Program in the prescribed format and within the stipulated period shall be considered a violation of his contractual obligations and a Notice for Termination shall be issued to the Contractor.’ SUBCLAUSE 14.3- CASHFLOW ESTIMATE The time within which the detailed cash flow estimate shall be submitted shall be as specified in the Appendix to the Form of Bid.
REVISED PROGRAMME. If at any time it should appear to the Engineer that the actual progress of the Works does not conform to the programme to which consent has been given under Sub- Clause 4.9.1, the Contractor shall produce, at the request of the Engineer, a revised programme showing the modifications to such programme necessary to ensure completion of the Works within the Time for Completion.
REVISED PROGRAMME. If at any time it should appear to the EIC that the actual progress of the Works does not conform to the programme to which consent has been given under Sub-Clause 4.9 (a), the Contractor shall produce, at the request of the EIC, a revised programme showing the modifications to such programme necessary to ensure completion of the Works within the Time for Completion.

Related to REVISED PROGRAMME

  • Research Plan The Parties recognize that the Research Plan describes the collaborative research and development activities they will undertake and that interim research goals set forth in the Research Plan are good faith guidelines. Should events occur that require modification of these goals, then by mutual agreement the Parties can modify them through an amendment, according to Paragraph 13.6.

  • Development Plan document specifying the work program, schedule, and relevant investments required for the Development and the Production of a Discovery or set of Discoveries of Oil and Gas in the Concession Area, including its abandonment.

  • Development Program A. Development activities to be undertaken (Please break activities into subunits with the date of completion of major milestones) B. Estimated total development time

  • Programme 13.1 Within the time stated in the Contract Data, the Contractor shall submit to the Engineer for approval a Programme showing the general methods, arrangements,' order and timing for all the activities for the construction of works. 13.2 The program shall be supported with all the details regarding key personnel, equipment and machinery proposed to be deployed on the works for its execution. The contractor shall submit the list of equipment and machinery being brought to site, the list of key personnel being deployed, the list of machinery/equipment being placed in field laboratory and the location of field laboratory along with the Programme.

  • Commercialization Plan At such times as the JGC will deem appropriate, the JGC will direct the Parties to mutually prepare a Worldwide Commercialization Plan, and the JGC will review and approve such initial Worldwide Commercialization Plan. Thereafter, the JGC will have one or the other Party (or both) update the Worldwide Commercialization Plan each calendar year, and the JGC will review and approve any such update or any other amendment to the Worldwide Commercialization Plan. Notwithstanding anything in this CCPS Agreement to the contrary, the Parties acknowledge and agree that (i) Bluebird may decline to perform any Commercialization activity proposed to be conducted by Bluebird in the Worldwide Commercialization Plan (other than Manufacturing of Vectors and associated Payloads), and (ii) the Worldwide Commercialization Plan will not include, and Bluebird will have no obligation to perform, any such Commercialization activity that Bluebird has declined to perform, provided that once Bluebird has agreed to perform a Commercialization activity, it will be obligated to perform, and cannot decline to perform, such activity. In addition, either Party may request at any time that the JGC consider and approve other updates to the Worldwide Commercialization Plan. Further: (a) The JGC will set the required form and contents of the Worldwide Commercialization Plan. The Worldwide Commercialization Plan will reflect a singular marketing and sales approach worldwide, and will specify, among other things, the number of sales reps in the U.S. for each Party, allocation of regions in the U.S. for each Parties’ sales force, creation of marketing materials, planning for conferences, and other marketing activities. CERTAIN CONFIDENTIAL PORTIONS OF THIS EXHIBIT WERE OMITTED AND REPLACED WITH “[***]”. A COMPLETE VERSION OF THIS EXHIBIT HAS BEEN FILED SEPARATELY WITH THE SECRETARY OF THE SECURITIES AND EXCHANGE COMMISSION PURSUANT TO AN APPLICATION REQUESTING CONFIDENTIAL TREATMENT PURSUANT TO RULE 406 PROMULGATED UNDER THE SECURITIES ACT OF 1933, AS AMENDED. (b) Neither Party (itself or by or through any others, including any Affiliates or Sublicensees) will take any material action regarding the Commercialization of Licensed Product unless described in the Worldwide Commercialization Plan or approved by the JGC. (c) All Commercialization of Licensed Product for U.S. Administration will be conducted under the supervision of the JGC and as part of the U.S. Development & Commercialization Program. (d) Celgene will have final decision making authority for all Commercialization activities worldwide, including timing of launch and pricing and the Worldwide Development Plan.

  • Research Program The term “

  • Maintenance Programme (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following: (a) The condition of the road in the format prescribed by the Authority’s Engineer; (b) the proposed maintenance Works; and (c) deployment of resources for maintenance Works.

  • Project Plan Development of Project Plan Upon the Authorized User’s request, the Contractor must develop a Project Plan. This Project Plan may include Implementation personnel, installation timeframes, escalation procedures and an acceptance plan as appropriate for the Services requested. Specific requirements of the plan will be defined in the RFQ. In response to the RFQ, the Contractor must agree to furnish all labor and supervision necessary to successfully perform Services procured from this Lot. Project Plan Document The Contractor will provide to the Authorized User, a Project Plan that may contain the following items: • Name of the Project Manager, Contact Phone Numbers and E-Mail Address; • Names of the Project Team Members, Contact Phone Numbers and E-Mail Address; • A list of Implementation milestones based on the Authorized User’s desired installation date; • A list of responsibilities of the Authorized User during system Implementation; • A list of designated Contractor Authorized Personnel; • Escalation procedures including management personnel contact numbers; • Full and complete documentation of all Implementation work; • Samples of knowledge transfer documentation; and • When applicable, a list of all materials and supplies required to complete the Implementation described in the RFQ. Materials and Supplies Required to Complete Implementation In the event that there are items required to complete an Implementation, the Contractor may request the items be added to its Contract if the items meet the scope of the Contract. Negotiation of Final Project Plan If the Authorized User chooses to require a full Project Plan, the State further reserves the right for Authorized Users to negotiate the final Project Plan with the apparent RFQ awardee. Such negotiation must not substantively change the scope of the RFQ plan, but can alter timeframes or other incidental factors of the final Project Plan. The Authorized User will provide the Contractor a minimum of five (5) business days’ notice of the final negotiation date. The Authorized User reserves the right to move to the next responsible and responsive bidder if Contractor negotiations are unsuccessful.

  • Protocol No action to coerce or censor or penalize any negotiation participant shall be made or implied by any other member as a result of participation in the negotiation process.

  • Development Phase contractual phase initiated with the approval of ANP for the Development Plan and which is extended during the Production Phase while investments in xxxxx, equipment, and facilities for the Production of Oil and Gas according to the Best Practices of the Oil Industry are required.