Synchronization, Commissioning and Commercial Operation. 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.
Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SECI and also Buying Entity at least sixty (60) days’ advanced preliminary written notice and at least thirty (30) days’ advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.
Synchronization, Commissioning and Commercial Operation. 3.10.1 The Solar Power Developer shall give a written notice to the concerned SLDC and DISCOM, at least sixty (60) days in advance to the date on which it intends to synchronize the Project to the grid system.
Synchronization, Commissioning and Commercial Operation. 5.1.1 The WPD shall give the concerned RLDC/SLDC and SECI and also Buying Entity at least sixty (60) days’ advanced preliminary written notice and at least thirty (30) days’ advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.
Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPG shall give PGVCL at least thirty (30) days’ advanced preliminary written notice and at least fifteen (15) days’ advanced final written notice, of the date on which it intends to synchronize the Solar Power Project to the Grid System.
Synchronization, Commissioning and Commercial Operation. 8.1 The Solar Power Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to APDCL of the date on which it intends to synchronize the Power Project to the Grid System.
Synchronization, Commissioning and Commercial Operation. 5.1.1 The HPD shall give the concerned RLDC/SLDC and SECI and also Buying Entity at least sixty (60) days’ advanced preliminary written notice and at least thirty (30) days’ advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.
Synchronization, Commissioning and Commercial Operation. 3.9.1 The Power Project may be synchronized by Solar Power Developer to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
Synchronization, Commissioning and Commercial Operation. 5.1.1 The BESSD shall give the concerned SLDC, GEDA, GETCO and GUVNL at least sixty (60) days’ advanced preliminary written notice and at least thirty (30) days’ advanced final written notice, of the date on which it intends to synchronize the Project to the Grid System.
Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned UPLDC/SLDC and Procurer and SPIA at least sixty (60) days‟ advanced preliminary written notice and at least thirty