Programme. 13.1 Within the time stated in the Contract Data, the Contractor shall submit to the Engineer for approval a Programme showing the general methods, arrangements,' order and timing for all the activities for the construction of works.
13.2 The program shall be supported with all the details regarding key personnel, equipment and machinery proposed to be deployed on the works for its execution. The contractor shall submit the list of equipment and machinery being brought to site, the list of key personnel being deployed, the list of machinery/equipment being placed in field laboratory and the location of field laboratory along with the Programme.
Programme. Please provide a suggested construction programme in bar chart form for the construction works necessary to install the User Development indicating the anticipated date when the connection will be required to be made.
1. We hereby apply to use the NGC GB Transmission System from our connection to [ ] Distribution System.
2. We will promptly inform NGC of any change in the information given in this application as quickly as practicable after becoming aware of any such change.
3. If we are not already a CUSC Party we undertake for the purposes of this application to be bound by the terms of the Grid Code from time to time in force and to sign a CUSC Accession Agreement.
4. We authorise the release of certain information, on the grounds of commercial confidentiality, to the appropriate Public Distribution System Operator(s) or Relevant Transmission Licensees should it be considered necessary.
5. We confirm that we do/do not meet the Approved Credit Rating [and
6. We confirm that we are applying in the category of [please insert appropriate description from table in paragraph 1.2.4 of the CUSC∗]. Signed: ......................................................................... For and on behalf of the Applicant Date:....................................................................... ∗ Delete if no associated Construction Works The Company Secretary Date: [ ] Dear Sirs Set out below is our offer for use of the NGC GB Transmission System at [site/substation]. Please note that certain expressions which are used in this Offer are defined in the Interpretation and Definitions (contained in Section 11 of the CUSC) and when this occurs the expressions have capital letters at the beginning of each word and are in bold.
1 NGC offers to enter into a Bilateral Embedded Generation Agreement [and Construction Agreement] reference number [ ] in the form and terms attached as Section A. 2 It is a condition of this offer that:
(i) if not already a CUSC Party you enter into a CUSC Accession Agreement;
(ii) you satisfy NGC that you have entered into a Distribution Agreement with the owner/operator of the Distribution System for the connection of the User’s Plant to and the use of such Distribution System;
Programme. 27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a Programme showing the general methods, arrangements, order, and timing for all the activities in the works along with monthly cash flow forecast.
27.2 An update of the Programme shall be a Programme showing the actual progress achieved on each activity and the effect of the progress achieved on the timing of the remaining work including any changes to the sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval, an updated Programme at intervals no longer than the period stated in the Contract Data. If the Contractor does not submit an updated Programme within this period, the Engineer may withhold the amount stated in the Contract Data from the next payment certificate and continue to withhold this amount until the next payment after the date on which the overdue Programme has been submitted.
27.4 The Engineer’s approval of the Programme shall not alter the Contractor’s obligations. The Contractor may revise the Programme and submit it to the Engineer again at any time. A revised Programme is to show the effect of Variations and Compensation Events.
Programme. The Contractor shall submit a time programme to the Contract Awarder after the Commencement Date. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with actual progress or with the Contractor's obligations. Unless otherwise stated in the Contract, each programme shall include:
(a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each major stage of the Works,
(b) the periods for reviews under Sub-Clause 5.2 [Contractor's Documents],
(c) the sequence and timing of inspections and tests specified in the Contract, and
(d) a supporting report which includes:
(i) a general description of the methods which the Contractor intends to adopt for the execution of each major stage of the Works, and
(ii) the approximate number of each class of Contractor's Personnel and of each type of Contractor's Equipment for each major stage. Unless the Contract Awarder, within 21 days after receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance with the programme, subject to his other obligations under the Contract. The Contract Awarder's Personnel shall be entitled to rely upon the programme when planning their activities. The Contractor shall promptly give notice to the Contract Awarder of specific probable future events or circumstances which may adversely affect or delay the execution of the Works. In this event, or if the Contract Awarder gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor's stated intentions, the Contractor shall submit a revised programme to the Contract Awarder in accordance with this Sub-Clause.
Programme. The Commonwealth is undertaking the Community Development Grants programme, which was to support needed infrastructure that promotes stable, secure and viable local and regional economies.
Programme. The IG Marketing Partnership programme, as may be amended from time to time at IG’s sole and absolute discretion, located at any Site.
Programme. The IDOH+ Consortium offers a two-year (120 ECTS) Erasmus Mundus International Master of Science in Infectious Diseases and One Health (610556-EPP-1-2019-1-FR-EPPKA1-JMD-MOB - 2019 Erasmus+: Erasmus Mundus Joint Master Degrees) (the “Programme”), which is approved and managed by the Education, Audiovisual and Culture Executive Agency (EACEA) and funded by the European Commission under the Erasmus + programme.
Programme. The start-up and test schedule for the Complex required by Sections 1 and 2 of this Schedule 4 shall include a time schedule, detailed procedures including settings for devices, and tests to be conducted.
Programme. Weekly coaching between the months of MONTH and MONTH. Events during MONTHS. Other programme activity e.g. coach education, Adults Other Than Teachers Programme.