Common use of Right of Access to the Site Clause in Contracts

Right of Access to the Site. The Employer shall give the Contractor right of access to and possession of, all parts of the Site within the entire period of Contract including extensions, if any. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received. If no such time is stated in the SCC, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employer. If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC and shall be entitled to: (a) an extension of time for any such delay, if completion is or will be delayed (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Employer / EIC shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.

Appears in 3 contracts

Samples: Tender for Procurement, Comprehensive Annual Maintenance Contract (Camc), Tender for Procurement of FRP Boats

AutoNDA by SimpleDocs

Right of Access to the Site. The Employer shall give the Contractor right of access to and possession of, all parts of the Site within the entire period of Contract including extensions, if anytime (or times) stated in the SCC. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received. If no such time is stated in the SCC, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employer. If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC EMPLOYER/ ENGINEER and shall be entitled to: (a) a. an extension of time for any such delay, if completion is or will be delayed (b) payment b. Payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Employer / EIC EMPLOYER/ENGINEER shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.

Appears in 3 contracts

Samples: Tender Agreement, Tender Agreement, Tender Agreement

Right of Access to the Site. The Employer shall give the Contractor right of access to and possession of, all parts of the Site within the entire period of Contract including extensions, if any. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received. If no such time is stated in the SCC, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employer. If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC and shall be entitled to: (a) an extension of time for any such delay, if completion is or will be delayed (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Employer / EIC shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.

Appears in 2 contracts

Samples: Tender Agreement, Tender Agreement

Right of Access to the Site. The Employer shall give the Contractor right of access to and possession of, all parts of the Site within the entire period of Contract including extensions, if anytime (or times) stated in the SCC. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received. If no such time is stated in the SCC, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employer. employer If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC EMPLOYER/ ENGINEER and shall be entitled to: (a) a. an extension of time for any such delay, if completion is or will be delayed (b) payment b. Payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Employer / EIC EMPLOYER/ENGINEER shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.

Appears in 2 contracts

Samples: Tender Agreement, Tender Agreement

Right of Access to the Site. The Employer shall give the Contractor right of access to and possession of, all parts of the Site within the entire period 15 days of Contract including extensions, if anysigning of agreement. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received. If no such time is stated in the SCC, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employer. received If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC EMPLOYER/ ENGINEER and shall be entitled to: (a) a. an extension of time for any such delay, if completion is or will be delayed (b) payment b. Payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Employer / EIC EMPLOYER/ENGINEER shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.

Appears in 2 contracts

Samples: Tender Agreement, Tender Document

Right of Access to the Site. The Employer shall give the Contractor right of access to to, and possession of, all parts of the Site within the entire period of Contract including extensions, if anytime (or times) stated In the Appendix to Tender. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the SpecificationEmployer's Requirements. However, the Employer may withhold any such right or possession until the Performance Security has been received. If no such time is stated in the SCCAppendix to Tender, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employersubmitted under Sub-Clause 8.3 [Programme]. If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to: (a) an extension of time for any such delay, if completion is or will be delayeddelayed under Sub-Clause 8.4 [Extension of Time for Completion], and , (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After After, receiving this notice, the Employer / EIC Engineer shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.accordance with Sub-Clause

Appears in 2 contracts

Samples: Contract Agreement, Contract Agreement

Right of Access to the Site. The Employer shall give the Contractor right of access to and possession of, all parts of the Site within the entire period of Contract including extensions, if anytime (or times) stated in the SCC. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received. received If no such time is stated in the SCC, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employer. employer If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC EMPLOYER/ ENGINEER and shall be entitled to: (a) a. an extension of time for any such delay, if completion is or will be delayed (b) payment b. Payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Employer / EIC EMPLOYER/ENGINEER shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.

Appears in 2 contracts

Samples: Tender Agreement, Tender Agreement

AutoNDA by SimpleDocs

Right of Access to the Site. The Employer shall give the Contractor right of access to to, and possession of, all parts of the Site within the entire period of Contract including extensions, if anytime (or times) stated In the Appendix to Tender. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in In the time and manner stated in the SpecificationEmployer's Requirements. However, the Employer may withhold any such right or possession until the Performance Security has been received. If no such time is Is stated in In the SCCAppendix to Tender, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employersubmitted under Sub-Clause 8.3 [Programme]. If the Contractor suffers delay and/or incurs Incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to: (a) an extension of time for any such delay, if completion is or will be delayeddelayed under Sub-Clause 8.4 [Extension of Time for Completion], and , (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After After, receiving this notice, the Employer / EIC Engineer shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.In accordance with Sub-Clause

Appears in 1 contract

Samples: Contract

Right of Access to the Site. The Employer shall give the Contractor right of access to and possession of, all parts of the Site within the entire period of Contract including extensions, if anytime (or times) stated in the SCC. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received. If no such time is stated in the SCC, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employeremployer. If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC EMPLOYER/ ENGINEER and shall be entitled to: (a) a. an extension of time for any such delay, if completion is or will be delayed (b) payment b. Payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Employer / EIC EMPLOYER/ENGINEER shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.

Appears in 1 contract

Samples: Tender Agreement

Right of Access to the Site. The Employer shall give the Contractor right of access to and possession of, all parts of the Site within the entire period of Contract including extensions, if anytime (or times) stated in the SCC. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received. If no such time is stated in the SCC, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted. The same shall be handed over to the Employer. If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer / EIC and shall be entitled to: (a) an extension of time for any such delay, if completion is or will be delayed (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Employer / EIC shall proceed to agree or determine these matters. However, if and to the extent that the Employer's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time Cost or profit.

Appears in 1 contract

Samples: Tender Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!