RIGHT OF THE OWNER TO DO WORK. Section 18.01. Right of the Owner to do Work. If the Contractor should neglect to perform the Work properly or fails to do anything required by the Contract Documents, and the Contractor does not correct the untimely or improper performance within seven (7) days after written demand is made, the Owner may, without prejudice to any other remedy it may have under this Contract or at law or in equity, make good any deficiencies in the Work, including, but not limited to, supplementing the workforces of the Contractor and deduct all costs of doing so from the payment then due or thereafter due the Contractor. The Owner shall not be required to give multiple notices to the Contractor in order to exercise its rights under this paragraph.
Appears in 4 contracts
Samples: Lump Sum Construction Contract, Lump Sum Construction Contract, Construction Contract