Common use of Right to Carry Out Work Clause in Contracts

Right to Carry Out Work. If Contractor defaults or persistently fails or neglects to carry out work in accordance with the contract documents, the Tribe, after 10 days’ written notice to Contractor and without prejudice to other remedies, may make good such deficiencies and may deduct the reasonable cost thereof from payment then or thereafter due to Contractor.

Appears in 6 contracts

Samples: Construction Contract, Construction Contract, Road Construction Contract