Schedule Coordination. 11.10.1 Contractor shall schedule and coordinate the performance of the Work by Contractor’s personnel, and Subcontractors and Vendors of any tier, in a manner that will enable Contractor to achieve Interim Milestones by the respective Interim Milestone Dates and completion within the Contract Time. Contractor acknowledges that at least a portion of the Work will be performed under joint occupancy conditions at the Site. 11.10.2 Contractor shall cooperate with Owner and Owner’s other contractors so that both the Contractor’s Work and the work of others will progress smoothly with a minimum of disruptions and interference to any party. 11.10.3 Contractor shall schedule its Work and Project delivery of materials to comply with all reasonable requests and suggestions of Owner in order to maintain the Project Schedule within the limitations of all existing Site conditions and business operations of Owner. 11.10.4 Contractor shall use all best efforts to not utilize any labor, materials or means whose employment or utilization during the course of this Contract may tend to or in any way cause or result in strikes, work stoppages, delays, suspension of Work or similar trouble by xxxxxxx employed by its Subcontractors, or by any of the trades working in or about the Project and Site where Work is being performed under this Contract, or by other contractors or their subcontractors pursuant to other contracts, or on any other project and project site or premises owned or operated by Owner. Any violation by Contractor of this requirement may be considered as proper and sufficient cause for declaring Contractor to be in default, and for Owner to take action against Contractor as set forth in the Contract Documents. 11.10.5 In case of disagreements or disputes regarding the schedule of Work by other contractors or unnecessary interference to the Work caused by lack of cooperation between other contractors and Contractor, Contractor shall fully cooperate to resolve any disputes with or between other contractors. In case of disagreements or disputes between two or more contractors, Owner shall be consulted and Owner’s decisions as to proper methods for coordinating the Work shall be final.
Appears in 2 contracts
Samples: Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc), Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc)
Schedule Coordination. 11.10.1 Contractor shall schedule and coordinate the performance of the Work by Contractor’s 's personnel, and Subcontractors and Vendors of any tier, in a manner that will enable Contractor to achieve Interim Milestones by the respective Interim Milestone Dates and completion within the Contract Time. Contractor acknowledges that at least a portion of the Work will be performed under joint occupancy conditions at the Site.
11.10.2 Contractor shall cooperate with Owner and Owner’s 's other contractors so that both the Contractor’s 's Work and the work of others will progress smoothly with a minimum of disruptions and interference to any party.
11.10.3 Contractor shall schedule its Work and Project delivery of materials to comply with all reasonable requests and suggestions of Owner in order to maintain the Project Schedule within the limitations of all existing Site conditions and business operations of Owner.
11.10.4 Contractor shall use all best efforts to not utilize any labor, materials or means whose employment or utilization during the course of this Contract may tend to or in any way cause or result in strikes, work stoppages, delays, suspension of Work or similar trouble by xxxxxxx employed by its Subcontractors, or by any of the trades working in or about the Project and Site where Work is being performed under this Contract, or by other contractors or their subcontractors pursuant to other contracts, or on any other project and project site or premises owned or operated by Owner. Any violation by Contractor of this requirement may be considered as proper and sufficient cause for declaring Contractor to be in default, and for Owner to take action against Contractor as set forth in the Contract Documents.
11.10.5 In case of disagreements or disputes regarding the schedule of Work by other contractors or unnecessary interference to the Work caused by lack of cooperation between other contractors and Contractor, Contractor shall fully cooperate to resolve any disputes with or between other contractors. In case of disagreements or disputes between two or more contractors, Owner shall be consulted and Owner’s 's decisions as to proper methods for coordinating the Work shall be final.
Appears in 1 contract
Samples: Guaranteed Maximum Price Construction Services Agreement (Wynn Resorts LTD)
Schedule Coordination. 11.10.1 Contractor shall schedule and coordinate the performance of the Work by Contractor’s personnel, and Subcontractors and Vendors of any tier, and the performance of the Project-related work by Owner’s Consultants and Owner’s Contractors, in a manner that will enable Contractor to achieve Original Project Interim Milestones or Expansion Project Interim Milestones by the respective Original Project Interim Milestone Dates or Expansion Project Interim Milestone Dates and completion within the Contract Time. Contractor acknowledges that at least a portion of the Work will be performed under joint occupancy conditions at the Site.
11.10.2 Contractor shall cooperate with Owner Owner, Owner’s Consultants and Owner’s other contractors Contractors so that both the Contractor’s Work and the work of others will progress smoothly with a minimum of disruptions and interference to any party.
11.10.3 Contractor shall schedule its Work and Project delivery of materials to comply with all reasonable requests and suggestions of Owner in order to maintain the Original Project Schedule or Expansion Project Schedule (as applicable) within the limitations of all existing Site conditions and business operations of Owner.
11.10.4 Contractor shall use all best efforts to not utilize any labor, materials or means whose employment or utilization during the course of this Contract may tend to or in any way cause or result in strikes, work stoppages, delays, suspension of Work or similar trouble by xxxxxxx employed by its Subcontractors, or by any of the trades working in or about the Project and Site where Work is being performed under this Contract, or by other contractors or their subcontractors pursuant to other contracts, or on any other project and project site or premises owned or operated by Owner. Any violation by Contractor of this requirement may be considered as proper and sufficient cause for declaring Contractor to be in default, and for Owner to take action against Contractor as set forth in the Contract Documents.
11.10.5 In case of disagreements or disputes regarding the schedule of Work by other contractors Owner’s Consultants and Owner’s Contractors or unnecessary interference to the Work caused by lack of cooperation between other contractors Owner’s Consultants or Owner’s Contractors and Contractor, Contractor shall fully cooperate to resolve any disputes with or between other contractorssuch disputes. In case of disagreements or disputes between two or more contractors, Owner shall be consulted and Owner’s decisions as to proper methods for coordinating the Work shall be final, subject to any rights or remedies of Contractor under this Agreement or applicable Law.
Appears in 1 contract