Schedule Impacts. Within five (5) Days after occurrence of an event that Contractor reasonably believes will have a material impact on the Work or any schedule, Contractor shall provide written notice to Owner Parties describing the nature and impact of the event, and propose methods of any necessary mitigation.
Appears in 10 contracts
Samples: Construction Manager at Risk and General Contractor Agreement, Construction Manager at Risk and General Contractor Agreement, Construction Manager at Risk and General Contractor Agreement
Schedule Impacts. Within five twenty-one (521) Days after occurrence of an event that Contractor reasonably believes will have a material impact on the Work or any schedule, Contractor shall provide written notice to Owner Parties describing the nature and impact of the event, and propose methods of any necessary mitigation.
Appears in 1 contract
Samples: Design Build Agreement