Schedule Update Requirements. Construction Contractor shall update the schedules monthly to show actual, current progress. The schedule updates shall be submitted within seven (7) calendar days of the data dates. The updates shall include:
Appears in 4 contracts
Samples: Construction Management Contract, Construction Management Contract, Construction Management Contract
Schedule Update Requirements. The Construction Contractor Manager shall update the schedules monthly to show actual, current progress. The submission date of the updates shall be determined by the OWNER, as outlined in Section 3.2 above. The schedule updates shall be submitted within seven (7) calendar days of the data dates. The updates shall include:seven
Appears in 3 contracts
Samples: Construction Of, www.naplesgov.com, www.naplesgov.com
Schedule Update Requirements. The Construction Contractor shall update the schedules monthly to show actual, current progress. The schedule updates shall be submitted within seven (7) calendar days of the data dates. The updates shall include:
Appears in 2 contracts
Samples: Project Construction Management Contract, Project Construction Management Contract
Schedule Update Requirements. Construction Contractor Manager shall update the schedules monthly to show actual, current progress. The schedule updates shall be submitted within seven (7) calendar days of the data dates. The updates shall include:
Appears in 1 contract
Schedule Update Requirements. The Construction Contractor Manager shall update the schedules monthly to show actual, current progress. The schedule updates shall be submitted within seven (7) calendar days of the data dates. The updates shall include:
Appears in 1 contract
Samples: Construction Management Agreement
Schedule Update Requirements. The Construction Contractor shall update the schedules monthly to show actual, current progress. The schedule updates shall be submitted within seven (7) calendar days of the data dates. The updates shall include:seven
Appears in 1 contract