Schedule Update Requirements. Following development and approval of the construction schedule, Contractor shall, at the end of each calendar weekly occurring thereafter during the period of time required to finally complete the Project, or at such earlier intervals as circumstances may require, update and/or revise the construction schedule which shall be submitted to Owner in duplicate. No additional compensation will be due Contractor for making such updates. Contractor shall update the schedules monthly to show actual, current progress. The schedule updates shall include: 4.2.5.2.1 Dates of activities’ actual starts and completions; 4.2.5.2.2 Percent of Work remaining for activities started but not completed as of the update date; 4.2.5.2.3 Narrative report including a listing of monthly progress, the activities that define the critical path and any changes to the path of critical activities from the previous update, sources of delay, any potential problems, requested logic changes, and Work planned for the next month; 4.2.5.2.4 A bar chart comparison of the updated schedule to the initial schedule. This diagram shall show actual and planned performance dates for all completed activities; and 4.2.5.2.5 All update information shall be an accurate representation of the actual Work progress.
Appears in 2 contracts
Samples: General Contractor Services Agreement, General Contractor Services Agreement
Schedule Update Requirements. Following development and approval of the construction schedule, Contractor shall, at the end of each calendar weekly month occurring thereafter during the period of time required to finally complete the Project, or at such earlier intervals as circumstances may require, update and/or revise the construction schedule which shall be submitted to Owner in duplicate. No additional compensation will be due Contractor for making such updates. Contractor shall update the schedules monthly to show actual, current progress. The schedule updates shall include:
4.2.5.2.1 4.2.4.2.1 Dates of activities’ actual starts and completions;
4.2.5.2.2 4.2.4.2.2 Percent of Work remaining for activities started but not completed as of the update date;
4.2.5.2.3 4.2.4.2.3 Narrative report including a listing of monthly progress, the activities that define the critical path and any changes to the path of critical activities from the previous update, sources of delay, any potential problems, requested logic changes, and Work planned for the next month;
4.2.5.2.4 4.2.4.2.4 A bar chart comparison of the updated schedule to the initial schedule. This diagram shall show actual and planned performance dates for all completed activities; and
4.2.5.2.5 4.2.4.2.5 All update information shall be an accurate representation of the actual Work progress.
Appears in 1 contract
Samples: Construction Agreement
Schedule Update Requirements. Following development and approval of the construction scheduleConstruction Schedule, Contractor Construction Manager shall, at the end of each calendar weekly month occurring thereafter during the period of time required to finally complete the Project, or at such earlier intervals as circumstances may require, update and/or revise the construction schedule Construction Schedule which shall be submitted to Owner in duplicate. No additional compensation will be due Contractor Construction Manager for making such updates. Contractor Construction Manager shall update the schedules monthly to show actual, current progress. The schedule updates shall include:
4.2.5.2.1 3.6.4.3.1 Dates of activities’ actual starts and completions;.
4.2.5.2.2 3.6.4.3.2 Percent of Work remaining for activities started but not completed as of the update date;.
4.2.5.2.3 3.6.4.3.3 Narrative report including a listing of monthly progress, the activities that define the critical path and any changes to the path of critical activities from the previous update, sources of delay, any potential problems, requested logic changes, and Work planned for the next month;.
4.2.5.2.4 3.6.4.3.4 A bar chart comparison of the updated schedule to the initial schedule. This diagram shall show actual and planned performance dates for all completed activities; and.
4.2.5.2.5 3.6.4.3.5 All update information shall be an accurate representation of the actual Work progress.
Appears in 1 contract