Scheduled Outages and Maintenance Outages. (a) The Seller shall give a thirty (30) days advanced written notice of the date on which it intends to undertake Scheduled Outages except that the Seller may undertake Scheduled Outages for individual Arrays in a manner so that no more than one Array is undergoing a Scheduled Outage at any one time in such Month. The Seller shall consult the System Operator before developing the Scheduled Outage programme and shall carry out Scheduled Outages in accordance with the Scheduled Outage programme approved by the System Operator. To the extent possible, the Scheduled Outages of individual Arrays shall be phased for minimizing the reduction in the total available generation capacity of the Facility and, to the extent practicable, be conducted at night. (b) The Seller shall advise the Purchaser of the need for any Maintenance Outages, together with the proposed commencement date and estimated duration of the work to be undertaken. The Purchaser shall advise the Seller of the periods during which such Maintenance Outage may be undertaken, such periods to be reasonable in light of the Purchaser’s requirements for Net Delivered Energy and the necessity for the Maintenance Outage. The Seller shall, subject to the Technical Limits, and Prudent Utility Practices, use reasonable endeavours to carry out the Maintenance Outage at night or during the times provided by the Purchaser in accordance with this Section 5.5(b).
Appears in 2 contracts
Scheduled Outages and Maintenance Outages. (a) The Seller shall give a thirty (30) days advanced written notice Any elective maintenance of the date on which it intends to undertake Scheduled Outages except that entire Complex shall be taken by the Seller may undertake Scheduled Outages for individual Arrays only in a manner so that no more than one Array is undergoing a Scheduled Outage at any one time the three Months designated by the Purchaser as Maintenance Months in such Monthits Year Ahead Notification. The Seller shall consult the System Operator Purchaser before developing the Scheduled Outage programme and shall carry out Scheduled Outages in accordance with the Scheduled Outage programme approved by the System OperatorPurchaser. To the extent possible, the Scheduled Outages of individual Arrays and WTGs shall be phased for minimizing the reduction in the total available generation capacity of the Facility and, to the extent practicable, be conducted at night.Complex
(b) The Seller shall advise the Purchaser of the need for any Maintenance Outages, together with the proposed commencement date and estimated duration of the work to be undertaken. The Purchaser shall advise the Seller of the periods during which such Maintenance Outage may be undertaken, such periods to be reasonable in light of the Purchaser’s requirements for Net Delivered Energy and the necessity for the Maintenance Outage. The Seller shall, subject to the Technical Limits, Prudent Utility Practices and Prudent Utility Electrical Practices, use reasonable endeavours to carry out the Maintenance Outage at night or during the times provided by the Purchaser in accordance with this Section 5.5(b)5.5.
Appears in 1 contract
Samples: Energy Purchase Agreement
Scheduled Outages and Maintenance Outages. (a) The Seller shall give a thirty (30) days advanced written notice of the date on which it intends to not undertake Scheduled Outages in the daylight hours of May, June, July and August except that the Seller may undertake Scheduled Outages for individual Arrays in a manner so that no more than one Array is undergoing a Scheduled Outage at any one time in such Month. The Seller shall consult the System Operator before developing the Scheduled Outage programme and shall carry out Scheduled Outages in accordance with the Scheduled Outage programme approved by the System Operator. To the extent possible, the Scheduled Outages of individual Arrays shall be phased for minimizing the reduction in the total available generation capacity of the Facility and, to the extent practicable, be conducted at nightComplex.
(b) The Seller shall advise the Purchaser of the need for any Maintenance Outages, together with the proposed commencement date and estimated duration of the work to be undertaken. The Purchaser shall advise the Seller of the periods during which such Maintenance Outage may be undertaken, such periods to be reasonable in light of the Purchaser’s requirements for Net Delivered Energy and the necessity for the Maintenance Outage. The Seller shall, subject to the Technical Limits, Prudent Utility Practices and Prudent Utility Electrical Practices, use reasonable endeavours to carry out the Maintenance Outage at night or during the times provided by the Purchaser in accordance with this Section 5.5(b)5.5.
Appears in 1 contract
Samples: Energy Purchase Agreement
Scheduled Outages and Maintenance Outages. (a) a. The Seller shall give a thirty (30) days advanced written notice of the date on which it intends to undertake Scheduled Outages Outages, except that the Seller may undertake Scheduled Outages for individual Arrays Generating Units in a manner so that no more than one Array Generating Unit is undergoing a Scheduled Outage at any one time in such Month. The Seller shall consult the System Operator before developing the Scheduled Outage programme and shall carry out Scheduled Outages in accordance with the Scheduled Outage programme approved by the System Operator. To the extent possible, the Scheduled Outages of individual Arrays Generating Units shall be phased for minimizing the reduction in the total available generation capacity of the Facility and, to the extent practicable, be conducted at nightFacility.
(b) b. The Seller shall advise the Purchaser of the need for any Maintenance Outages, together with the proposed commencement date and estimated duration of the work to be undertaken. The Purchaser shall advise the Seller of the periods during which such Maintenance Outage may be undertaken, such periods to be reasonable in light of the Purchaser’s requirements for Net Delivered Energy and the necessity for the Maintenance Outage. The Seller shall, subject to the Technical Limits, Limits and Prudent Utility Practices, use reasonable endeavours to carry out the Maintenance Outage at night or during the times provided by the Purchaser in accordance with this Section 5.5(b)5.5.
Appears in 1 contract
Samples: Power Purchase Agreement