Sealing and Marking of Bids. 19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as "ORIGINAL" and "COPY". These envelopes (called as inner envelopes) shall then be put inside one outer envelope. 19.2 The inner and outer envelopes shall (a) be addressed to the Employer at the following address: Additional Project Director, State Project Management Unit, Gujarat Ecology Commission, Udyog Bhavan, Block Xx. 00, 0xx Xxxxx, Xxxxxxxxxxx, Xxxxxxx, Xxxxx, and (b) bear the following identification: - Bid for [name of contract] - Bid Reference No [insert number] - DO NOT OPEN BEFORE [time and date for bid opening, per Clause 23] 19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause 21. 19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the misplacement or premature opening of the bid.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Sealing and Marking of Bids. 19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as "ORIGINAL" and "COPY". These envelopes (called as inner envelopes) shall then be put inside one outer envelope.
19.2 The inner and outer envelopes shall
(a) be addressed to the Employer at the following address: Additional National Project Director, State Project Management UnitSICOM, Gujarat Ecology CommissionMinistry of Environment and Forests, Udyog BhavanNo. 9, Block Xx. 00First Floor, 0xx XxxxxInstitutional Area, XxxxxxxxxxxLodhi Road, Xxxxxxx, Xxxxx, New Delhi-110003 and
(b) bear the following identification: - Bid for [name of contract] CONSTRUCTION OF BUILDING(including electrical and plumbing works) FOR NATIONAL CENTRE FOR SUSTAINABLE COASTAL MANAGEMENT,CHENNAI - Bid Reference No [insert number] No. NPMU/W/20a&20b - DO NOT OPEN BEFORE [time and date for bid opening, per Clause 23]10.30 HOURS ON 03.09.2013
19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause 21.
19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the misplacement or premature opening of the bid.
Appears in 1 contract
Samples: Construction Agreement
Sealing and Marking of Bids. 19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as "“ORIGINAL" ” and "“COPY"”. These envelopes (called as inner envelopes) shall then be put inside one outer envelope.
19.2 The inner and outer envelopes shall
(a) be Be addressed to the Employer C.E. Procurement and submitted at the following address: Additional Project DirectorOffice of The Executive Engineer, State Project Management UnitXxxxxx Xxxxx Xxxxxx Xxxxxxxxx, Gujarat Ecology CommissionSWaRA Bhawan Link Xxxx xx-0, Udyog BhavanWater Resources Department, Block Xx. 00, 0xx Xxxxx, Xxxxxxxxxxx, Xxxxxxx, Xxxxx, andBhopal (M. P.)
(b) bear Bear the following identification: - Bid for [name of contract] RESTRUCTURING & MODERNIZATION OF HEAD WORKS AND CANALS OF BIRHANA TANK - Bid Reference No [insert number] No- 61/MPWSRP dated 29.07.2013 - DO NOT OPEN BEFORE [time and date for bid opening, per Clause 23]10.09.2013 at 15:30 Hours.
19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause 21.
19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the misplacement or premature opening of the bid.
Appears in 1 contract
Sealing and Marking of Bids. 19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as "ORIGINAL" and "COPY". These envelopes (called as inner envelopes) shall then be put inside one outer envelope.
19.2 The inner and outer envelopes shall
(a) be addressed to the Employer Procurement Expert ,O/O The Project Director, W.B.P.,W.R.D. Bhopal and be submitted at the following address: Additional Project Director, State Project Management Unit, Gujarat Ecology Commission, Udyog Bhavan, Block Xx. 00, 0xx Xxxxx, Xxxxxxxxxxx, Xxxxxxx, Xxxxx, and
(b) bear the following identification: - Bid for [name of contract] RENOVATION OF XXXXXXX AQUEDUCT RD 0.60KM ON CHAMBAL RIGHT MAIN CANAL - Bid Reference No [insert number] No- 68/MPWSRP /30.11.2013 - DO NOT OPEN BEFORE [time and 15.30 hrs date for bid opening, per Clause 23]06.01.2014
19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause 21.
19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the misplacement or premature opening of the bid.
Appears in 1 contract
Samples: Renovation Agreement
Sealing and Marking of Bids. 19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as "“ORIGINAL" ” and "“COPY"”. These envelopes (called as inner envelopes) shall then be put inside one outer envelope.
19.2 The inner and outer envelopes shall
(a) be Be addressed to the Employer C.E. Procurement and submitted at the following address: Additional Project DirectorOffice of The Executive Engineer, State Project Management UnitXxxxxx Xxxxx Xxxxxx Xxxxxxxxx, Gujarat Ecology CommissionSWaRA Bhawan Link Xxxx xx-0, Udyog BhavanWater Resources Department, Block Xx. 00, 0xx Xxxxx, Xxxxxxxxxxx, Xxxxxxx, Xxxxx, andBhopal (M. P.)
(b) bear Bear the following identification: - Bid for [name Restructuring & Modernization of contract] Head works - Bid Reference No [insert number] No- 43/MPWSRP/28.02.2013 - DO NOT OPEN BEFORE [time and date for bid opening, per Clause 23]06.04.2013 at 15:30 Hours.
19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause 21.
19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the misplacement or premature opening of the bid.
Appears in 1 contract
Sealing and Marking of Bids. 19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as "“ORIGINAL" ” and "“COPY"”. These envelopes (called as inner envelopes) shall then be put inside one outer envelope.
19.2 The inner and outer envelopes shall
(a) be Be addressed to the Employer C.E. Procurement and submitted at the following address: Additional Project DirectorOffice of The Executive Engineer, State Project Management UnitXxxxxx Xxxxx Xxxxxx Xxxxxxxxx, Gujarat Ecology CommissionSWaRA Bhawan Link Xxxx xx-0, Udyog BhavanWater Resources Department, Block Xx. 00, 0xx Xxxxx, Xxxxxxxxxxx, Xxxxxxx, Xxxxx, andBhopal (M. P.)
(b) bear Bear the following identification: - Bid for [name of contract] RESTRUCTURING & MODERNIZATION OF HEAD WORKS AND CANALS OF HATHAIKHEDA TANK - Bid Reference No [insert number] No- 56/MPWSRP dated 18.06.2013 - DO NOT OPEN BEFORE [time and date for bid opening, per Clause 23]25.07.2013 at 15:30 Hours.
19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause 21.
19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the misplacement or premature opening of the bid.
Appears in 1 contract
Samples: Construction Contract
Sealing and Marking of Bids. 19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as "“ORIGINAL" ” and "“COPY"”. These envelopes (called as inner envelopes) shall then be put inside one outer envelope.
19.2 The inner and outer envelopes shall
(a) be Be addressed to the Employer Procurement Expert and submitted at the following address: Additional Project DirectorOffice of The Executive Engineer, State Project Management UnitXxxxxx Xxxxx Xxxxxx Xxxxxxxxx, Gujarat Ecology CommissionSWaRA Bhawan Xxxx Xxxx xx-0, Udyog Bhavan, Block Xx. 00, 0xx Xxxxx, Xxxxxxxxxxx, Xxxxxxx, Xxxxx, andXxxxx Xxxxxxxxx Department,
(b) bear Bear the following identification: - Bid for [name of contract] RESTRUCTURING & MODERNIZATION OF HEAD WORKS AND CANALS OF NAPANERA TANK - Bid Reference No [insert number] No- 54/MPWSRP/30.05.2013 - DO NOT OPEN BEFORE [time and date for bid opening, per Clause 23]05.07.2013 at 15:30 Hours.
19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause 21.
19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the misplacement or premature opening of the bid.
Appears in 1 contract
Sealing and Marking of Bids. 19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as "“ORIGINAL" ” and "“COPY"”. These envelopes (called as inner envelopes) shall then be put inside one outer envelope.
19.2 The inner and outer envelopes shall
(a) be Be addressed to the Employer Procurement Expert and submitted at the following address: Additional Project DirectorOffice of The Executive Engineer, State Project Management UnitXxxxxx Xxxxx Xxxxxx Xxxxxxxxx, Gujarat Ecology CommissionSWaRA Bhawan Xxxx Xxxx xx-0, Udyog Bhavan, Block Xx. 00, 0xx Xxxxx, Xxxxxxxxxxx, Xxxxxxx, Xxxxx, andXxxxx Xxxxxxxxx Department,
(b) bear Bear the following identification: - Bid for [name of contract] RESTRUCTURING & MODERNIZATION OF HEAD WORKS AND CANALS OF XXXXXXX XXX AND TINONIA TANK - Bid Reference No [insert number] No- 69/MPWSRP/19.12.2013 - DO NOT OPEN BEFORE [time and date for bid opening, per Clause 23]23.01.2014 at 15:30 Hours.
19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause 21.
19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the misplacement or premature opening of the bid.