Separable Portions. The ALT may determine that any part of the Alliance Works will be a Separable Portion and the interpretations of: (a) Certificate of Completion; (b) Completion; (c) Date for Completion; (d) Date of Completion; and (e) Alliance Works, will apply separately to each Separable Portion.
Appears in 5 contracts
Samples: Project Alliance Agreement, Project Alliance Agreement, Project Alliance Agreement
Separable Portions. The ALT may determine that any part of the Alliance Works will be a Separable Portion and the interpretations of:
(a) Certificate of Opening Completion;
(b) Opening Completion;
(c) Date for Opening Completion;
(d) Date of Opening Completion
(e) Certificate of Completion;
(f) Completion;
(g) Date for Completion;
(h) Date of Completion; and
(ei) Alliance Works, will apply separately to each Separable Portion.
Appears in 2 contracts
Samples: Project Alliance Agreement, Project Alliance Agreement