Study Requests for Changes in Delivery Facilities. The Customer shall make requests for changes in local delivery facilities, including facility upgrades, retirements and replacements, or the establishment of any new Delivery Point, in writing to AEP, delivered by post or electronic mail (email) to Director, Transmission and Interconnection Services, and Manager, East Area Transmission Planning. AEP shall likewise respond to such requests in writing, by post or email. A request for a new Delivery Point or modification of an existing Delivery Point should include, at a minimum, the following information: a) Nature of the change such as: modifications to an existing Delivery Point, new Delivery Point, increased capacity, and retirement, etc.; b) Location of the Delivery Point; c) Voltage class of the Delivery Point; d) Specific AEP transmission facility that the Delivery Point is to be connected to; e) Amount of load to be served by the Delivery Point for the first 5 years; f) Specific modifications to an existing Delivery Point, if applicable; and g) Desired in-service date.
Appears in 3 contracts
Samples: Facilities Agreement, Facilities Agreement, Facilities Agreement
Study Requests for Changes in Delivery Facilities. The Customer shall make requests for changes in local delivery facilities, including facility upgrades, retirements and replacements, or the establishment of any new Delivery Point, in writing to AEP, delivered by post or electronic mail (email) to DirectorManager, Transmission and Interconnection Services, and Manager, East Area Transmission Planning. AEP shall likewise respond to such requests in writing, by post or email. A request for a new Delivery Point or modification of an existing Delivery Point should include, at a minimum, the following information:
a) Nature of the change such as: modifications to an existing Delivery Point, new Delivery Point, increased capacity, and retirement, etc.;
b) Location of the Delivery Point;
c) Voltage class of the Delivery Point;
d) Specific AEP transmission facility that the Delivery Point is to be connected to;
e) Amount of load to be served by the Delivery Point for the first 5 years;
f) Specific modifications to an existing Delivery Point, if applicable; and
g) Desired in-service date.
Appears in 2 contracts
Samples: Facilities Agreement and Service Agreement, Facilities Agreement
Study Requests for Changes in Delivery Facilities. The Customer shall make requests for changes in local delivery facilities, including facility upgrades, retirements and replacements, or the establishment of any new Delivery Point, in writing to AEP, delivered by post or electronic mail (email) to Director, Transmission and Interconnection Services, and Manager, East Area Transmission Planning. AEP shall likewise respond to such requests in writing, by post or email. A request for a new Delivery Point or modification of an existing Delivery Point should include, at a minimum, the following information:
a) Nature of the change such as: modifications to an existing Delivery Point, new Delivery Point, increased capacity, and retirement, etc.;
b) Location of the Delivery Point;
c) Voltage class of the Delivery Point;
d) Specific AEP transmission facility that the Delivery Point is to be connected to;
e) Amount Non-binding good faith estimate of load to be served by the Delivery Point for the first 5 years;
f) Specific modifications to an existing Delivery Point, if applicable; and
g) Desired in-service date.
Appears in 1 contract
Samples: Second Revised Service Agreement
Study Requests for Changes in Delivery Facilities. The Customer shall make requests for changes in local delivery facilities, including facility upgrades, retirements and replacements, or the establishment of any new Delivery Point, in writing to AEP, delivered by post or electronic mail (email) to DirectorManager, Transmission and Interconnection Services, and the Manager, East Area Transmission Planning. AEP shall likewise respond to such requests in writing, by post or email. A request for a new Delivery Point or modification of an existing Delivery Point should include, at a minimum, the following information:
a) Nature of the change such as: modifications to an existing Delivery Point, new Delivery Point, increased capacity, and retirement, etc.;
b) Location of the Delivery Point;
c) Voltage class of the Delivery Point;
d) Specific AEP transmission facility that the Delivery Point is to be connected to;
e) Amount of load to be served by the Delivery Point for the first 5 years;
f) Specific modifications to an existing Delivery Point, if applicable; and
g) Desired in-service date.
Appears in 1 contract
Samples: Facilities Agreement