Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest. 3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility will determine if the Generating Facility can be interconnected safely and reliably. 3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days. 3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost. 3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 5 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Procedures
Supplemental Review. If the Interconnection Customer Member agrees to a supplemental review, the Interconnection Customer Member shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawncosts. The Interconnection Customer Member shall be responsible for the Utility's Cooperative’s actual costs for conducting the supplemental review. The Interconnection Customer Member must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility Cooperative will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following 3.5.1 Following receipt of the deposit for a supplemental review, the Utility Cooperative will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 3.5.1.1 If so, the Utility Cooperative shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business DaysMember, to be completed in accordance with the timeline provided in Section 5.6.
3.4.1.2 3.5.1.2 If so, and Interconnection Customer Member facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall Cooperative will forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days Member after confirmation that the Interconnection Customer Member has agreed to make the necessary modifications at the Interconnection CustomerMember’s cost, to be completed in accordance with the timeline provided in Section 5.6.
3.4.1.3 3.5.1.3 If so, and minor modifications to the UtilityCooperative’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility Cooperative shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days Member that requires the Interconnection Customer Member to pay the costs of such System modifications prior to interconnection. , to be completed in accordance with the timeline provided in Section 5.6.
3.5.1.4 If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer Member indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 4 contracts
Samples: Interconnection Procedures, Interconnection Procedures, Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. .
3.4.1.4 If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 3 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Procedures, Generator Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawncosts. The Interconnection Customer shall be responsible for the Utility's ’s actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) five Business Days.
3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) five Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. .
3.4.1.4 If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 3 contracts
Samples: Interconnection Procedures, Interconnection Procedures, Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental reviewSupplemental Review, the Interconnection Customer shall agree in writing within 15 ten (10) Business Days of the offer, and submit a deposit for of $750 (if the estimated costs facility is larger than 20 kW but not larger than 100 kW) or $1,000 (if the facility is larger than 100 kW but not larger than 2 MW), or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental reviewSupplemental Review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental reviewSupplemental Review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall ask if the customer agrees to make the necessary modifications. The customer will be given 10 Business Days to agree, in writing, to the required modifications. The Utility will forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) 15 Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. .
3.4.1.4 If so, but the costs of interconnection including System Upgrades and Interconnection Facilities cannot be determined without further study or review, the Utility will notify the Interconnection Customer that the Utility will need to complete a Facilities Study under Section 4.5 to determine the necessary costs of interconnection.
3.4.1.5 If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 2 contracts
Samples: Interconnection Procedures, Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental reviewSupplemental Review, the Interconnection Customer shall agree in writing within 15 ten (10) Business Days of the offer, and submit a deposit for of $750 (if the estimated costs facility is larger than 20 kW but not larger than 100 kW) or $1,000 (if the facility is larger than 100 kW but not larger than 2 MW), or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental reviewSupplemental Review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental reviewSupplemental Review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall ask if the customer agrees to make the necessary modifications. The customer will be given 10 Business Days to agree, in writing, to the required modifications. The Utility will forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) 15 Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. .
3.4.1.4 If so, but the costs of interconnection including System Upgrades and Interconnection Facilities cannot be determined without further study or review, the Utility will notify the Interconnection Customer that the Utility will need to complete a Facilities Study under Section 4.4 to determine the necessary costs of interconnection.
3.4.1.5 If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 2 contracts
Samples: Interconnection Procedures, Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall will agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall will be deemed to be withdrawn. The Interconnection Customer shall will be responsible for the UtilityCooperative's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility Cooperative will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following After receipt of the deposit for a supplemental review, the Utility Cooperative will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall Cooperative will forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business DaysCustomer.
3.4.1.2 If so, and but Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall Cooperative will forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and but minor modifications to the UtilityCooperative’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall Cooperative will forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 1 contract
Samples: Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the UtilityAuthority's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility Authority will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility Authority will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility Authority shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility Authority shall forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the UtilityAuthority’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility Authority shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 1 contract
Samples: Generator Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected ELECTRONICALLY FILED - 2020 November 17 4:39 PM - SCPSC - Docket # 2019-326-E - Page 23 of 196 DEC/DEP Application - Attachment 1 Docket No. 2019-326-E consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. .
3.4.1.4 If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 1 contract
Samples: Generator Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the 15 ten (10) Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) 15 Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost. Commented [A67]: Additional Comment: IREC supports a robust, structured, and transparent supplemental review process that relies on defined screens. Supplemental review would include three screens: (1) 100% minimum load, (2) voltage and power quality screen, and (3) safety and reliability screen. If the project passes these screens, the utility will proceed with the application under the Fast Track process; otherwise, the application proceeds to full study under Section 4. This process would replace the existing procedure, which does not define how the utility will determine if the project can be interconnected safety and reliably, leaving customers in the dark regarding whether to elect to proceed with the cost of supplemental review and preventing assurance that supplemental review will be applied in a way that prevents unnecessary study. This process is likely to become more important if the size of the standard offer contract changes. The procedure IREC proposes has been adopted by FERC, Ohio, Iowa, Illinois, California, Massachusetts, and Hawaii. Many of these states, like North Carolina, experience high penetration and have found supplemental review to be an effective tool at screening projects for further review and preventing queue backlogs.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days. IREC (Fast Track WG3/4) has submitted the following revision to section 3.4.
Appears in 1 contract
Samples: Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental reviewreviewSupplemental Review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs costs$2,000 study fee or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental reviewreviewSupplemental Review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit fee for a supplemental reviewreviewSupplemental Review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
. 3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall ask if the customer agrees to make the necessary modifications. The customer will be given 10 Business Days to agree, in writing, to the required modifications. The Utility will forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 1 contract
Samples: Generator Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawncosts. The Interconnection Customer shall be responsible for the Utility's Transmission Provider’s actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility Transmission Provider will return such excess within 20 Business Days of the invoice without interest.
3.4.1 2.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility Transmission Provider will determine if the Small Generating Facility can be interconnected safely and reliably.
3.4.1.1 2.4.1.1 If so, the Utility Transmission Provider shall forward an executable Interconnection Agreement an interconnection agreement to the Interconnection Customer within ten (10) five Business Days.
3.4.1.2 2.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Small Generating Facility to be interconnected consistent with safety, Small Generator Interconnection Procedures (SGIP) 9 reliability, and power quality standards under these procedures, the Transmission Provider shall forward an executable interconnection agreement to the Interconnection Customer within five Business Days after confirmation that the Interconnection Customer has agreed to make the necessary changes at the Interconnection Customer’s cost.
2.4.1.3 If so, and minor modifications to the Transmission Provider’s electric system are required to allow the Small Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these proceduresthe Fast Track Process, the Utility Transmission Provider shall forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement interconnection agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System system modifications prior to interconnection. .
2.4.1.4 If not, the Interconnection Request will continue to be evaluated under the Section 4 section 3 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 1 contract
Samples: Standard Small Generator Interconnection Agreement (Sgia)
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected ELECTRONICALLY FILED - 2019 April 22 5:05 PM - SCPSC - Docket # 2019-130-E - Page 21 of 115 consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 1 contract
Samples: Generator Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) 15 Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 1 contract
Samples: Interconnection Procedures
Supplemental Review. If the Interconnection Customer agrees to a supplemental review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs or the request shall be deemed to be withdrawncosts. The Interconnection Customer shall be responsible for the UtilityTransmission Provider's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility Transmission Provider will return such excess within 20 Business Days of the invoice without interest.
3.4.1 2.4.1 Within ten (10) Business Days following receipt of the deposit for a supplemental review, the Utility Transmission Provider will determine if the Small Generating Facility can be interconnected safely and reliably.
3.4.1.1 2.4.1.1 If so, the Utility Transmission Provider shall forward an executable Interconnection Agreement interconnection agreement to the Interconnection Customer within ten (10) five Business Days.
3.4.1.2 2.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Small Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility Transmission Provider shall forward an executable Interconnection Agreement interconnection agreement to the Interconnection Customer within fifteen (15) five Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications changes at the Interconnection Customer’s 's cost.
3.4.1.3 2.4.1.3 If so, and minor modifications to the Utility’s System Transmission Provider's electric system are required to allow the Small Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these proceduresthe Fast Track Process, the Utility Transmission Provider shall forward an executable Interconnection Agreement interconnection agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System system modifications prior to interconnection. .
2.4.1.4 If not, the Interconnection Request will continue to be evaluated under the Section 4 section 3 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.
Appears in 1 contract
Samples: Small Generator Interconnection Procedures and Agreement
Supplemental Review. If the Interconnection Customer agrees to a supplemental reviewreviewSupplemental Review, the Interconnection Customer shall agree in writing within 15 Business Days of the offer, and submit a deposit for the estimated costs costs$2,000 study fee or the request shall be deemed to be withdrawn. The Interconnection Customer shall be responsible for the Utility's actual costs for conducting the supplemental review. The Interconnection Customer must pay any review costs that exceed the deposit within 20 Business Days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the Utility will return such excess within 20 Business Days of the invoice without interest.
3.4.1 Within ten (10) Business Days following receipt of the deposit depositfee for a supplemental reviewreviewSupplemental Review, the Utility will determine if the Generating Facility can be interconnected safely and reliably.
3.4.1.1 If so, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days.
. SC Generator Interconnection Procedures 23 3.4.1.2 If so, and Interconnection Customer facility modifications are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall ask if the customer agrees to make the necessary modifications. The customer will be given ten (10) Business Days to agree, in writing, to the required modifications. The Utility will forward an executable Interconnection Agreement to the Interconnection Customer within fifteen (15) Business Days after confirmation that the Interconnection Customer has agreed to make the necessary modifications at the Interconnection Customer’s cost.
3.4.1.3 If so, and minor modifications to the Utility’s System are required to allow the Generating Facility to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the Utility shall forward an executable Interconnection Agreement to the Interconnection Customer within ten (10) Business Days that requires the Interconnection Customer to pay the costs of such System modifications prior to interconnection. If not, the Interconnection Request will continue to be evaluated under the Section 4 Study Process, provided the Interconnection Customer indicates it wants to proceed and submits the required deposit within 15 Business Days.