Suspension of Project. The Council may, in its sole discretion, suspend the Project by written notice. The Construction Manager will be compensated for Services performed prior to notice of suspension. 13.6.1. If the Project is suspended by the Council for less than one hundred and eighty (180) consecutive days, the Construction Manager will reduce or suspend its services as directed by the Council. 13.6.2. If the Project is suspended by the Council for more than one hundred and eighty (180) consecutive days, then when the Project is resumed, the schedule will be adjusted and the Construction Manager’s compensation will be equitably adjusted to provide for expenses incurred in the resumption of the Construction Manager’s Services. 13.6.3. Upon resumption of the Project after suspension, the Construction Manager will take all reasonable efforts to maintain the same Project personnel.
Appears in 3 contracts
Samples: Construction Management Services Agreement, Construction Management Services Agreement, Construction Manager Agreement
Suspension of Project. The 26.8.1. Judicial Council may, in its sole discretion, suspend the Project by written noticeNotice. The Construction Manager will be compensated for Services performed prior to notice Notice of suspension.
13.6.126.8.2. If the Project is suspended by the Judicial Council for less than one hundred and eighty (180) consecutive days, the Construction Manager will reduce or suspend its services as directed by the Judicial Council.
13.6.226.8.3. If the Project is suspended by the Judicial Council for more than one hundred and eighty (180) consecutive days, then when the Project is resumed, the schedule will be adjusted adjusted, and the Construction Manager’s compensation will be equitably adjusted to provide for expenses incurred in the resumption of the Construction Manager’s Services.
13.6.326.8.4. Upon resumption of the Project after suspension, the Construction Manager will take all reasonable efforts to maintain the same Project personnel.personnel.
Appears in 1 contract
Suspension of Project. The 27.8.1. Judicial Council may, in its sole discretion, suspend the Project by written noticeNotice. The Construction Manager will be compensated for Services performed prior to notice Notice of suspension.
13.6.127.8.2. If the Project is suspended by the Judicial Council for less than one hundred and eighty (180) consecutive days, the Construction Manager will reduce or suspend its services as directed by the Judicial Council.
13.6.227.8.3. If the Project is suspended by the Judicial Council for more than one hundred and eighty (180) consecutive days, then when the Project is resumed, the schedule will be adjusted adjusted, and the Construction Manager’s compensation will be equitably adjusted to provide for expenses incurred in the resumption of the Construction Manager’s Services.
13.6.327.8.4. Upon resumption of the Project after suspension, the Construction Manager will take all reasonable efforts to maintain the same Project personnel.
Appears in 1 contract
Suspension of Project. The Council may, in its sole discretion, suspend the Project by written notice. The Construction Manager will shall be compensated for Services services performed prior to notice of suspension.
13.6.1. If the Project is suspended by the Council for less than one hundred and eighty (180) consecutive days, the Construction Manager will reduce or suspend its services as directed by the Council.
13.6.2. If the Project is suspended by the Council for more than one hundred and eighty (180) consecutive days, then when the Project is resumed, the schedule will shall be adjusted and the Construction Manager’s compensation will shall be equitably adjusted to provide for expenses incurred in the resumption of the Construction Manager’s Servicesservices.
13.6.3. Upon resumption of the Project after suspension, the Construction Manager will take all reasonable efforts to maintain the same Project personnel.
Appears in 1 contract