Suspension of Work and Termination. 15.01 Owner May Suspend Work A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than 60 consecutive days by written notice to Contractor and Engineer. Such notice will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be entitled to an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension.
Appears in 4 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Suspension of Work and Termination. 15.01 14.01 Owner May Suspend Work
A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than 60 sixty (60) consecutive days by written notice to Contractor and EngineerFacilities Manager. Such notice will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be entitled to an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension.
Appears in 1 contract
Samples: Construction Contract
Suspension of Work and Termination. 15.01 Owner May Suspend Work
A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than 60 sixty (60) consecutive days by written notice to Contractor and EngineerProject Manager. Such notice will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be entitled to an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension.
Appears in 1 contract
Samples: Construction Contract
Suspension of Work and Termination. 15.01 14.1 Owner May Suspend Work
A. Work At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than 60 consecutive 90 days by written notice in writing to Contractor and Engineer. Such notice that will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be entitled to allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspensionsuspension if Contractor makes a Claim therefor as provided in Article 9.
Appears in 1 contract
Samples: Comprehensive Agreement
Suspension of Work and Termination. 15.01 Owner 16.01 OWNER May Suspend Work
Work A. At any time and without cause, Owner OWNER may suspend the Work or any portion thereof for a period of not more than 60 consecutive days by written notice in writing to Contractor and Engineer. Such notice NEI which will fix the date on which Work will be resumed. Contractor NEI shall resume the Work on the date so fixed. Contractor NEI shall be entitled to allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspensionsuspension if NEI makes a Claim therefore as provided in Paragraph 13.03.
Appears in 1 contract