Termination for Failure to Meet Commercial Operation Deadline Sample Clauses

Termination for Failure to Meet Commercial Operation Deadline. If the Commercial Operation Date has not occurred on or before the Commercial Operation Deadline or any extension thereof as provided in Section 5.3(c) or (d) and a Party has not provided notice of termination pursuant to Section 5.3(d), each Party may terminate this Agreement without triggering the default provisions of this Agreement upon thirty (30) days’ written notice; provided, however, that such right to terminate shall not be available to if the terminating Party’s failure to fulfill any material obligations under this Agreement has been the cause of, or resulted in, the failure to achieve Commercial Operation.
AutoNDA by SimpleDocs
Termination for Failure to Meet Commercial Operation Deadline. If the Commercial Operation Date has not occurred on or before the Commercial Operation Deadline or any extension thereof as provided in Section 4.2(c) or resulting from a Force Majeure Event and System Owner has not provided notice of termination pursuant to Section 4.2(d), Host Customer may terminate this Agreement upon fifteen (15) days' written notice of such termination to System Owner; provided that such right to terminate shall not be available to Host Customer if Host Customer's failure to fulfill any material obligations under this Agreement has been the cause of, or resulted in, the failure of System Owner to achieve Commercial Operation. In the event of termination, System Owner shall remove all materials and return the premises, including grounds, to state prior to initiation of installation at its own cost.
Termination for Failure to Meet Commercial Operation Deadline. If the Commercial Operation Date has not occurred on or before the Commercial Operation Deadline, including any extension thereof as provided in Section 4.2.3, and System Owner has not provided notice of termination pursuant to Section 4.2.4, such failure to meet the Commercial Operation Deadline by System Owner shall be a failure to meet a material obligation and an Event of Default under Article XII of this Agreement for which Purchaser may terminate this Agreement by providing written notice to System Owner.

Related to Termination for Failure to Meet Commercial Operation Deadline

  • Termination for Cause with Notice to Cure Requirement Contractor may terminate this contract for the Department’s failure to perform any of its duties under this contract after giving the Department written notice of the failure. The written notice must demand performance of the stated failure within a specified period of time of not less than 30 days. If the demanded performance is not completed within the specified period, the termination is effective at the end of the specified period.

  • Termination for failure to pay If Company fails to make any payment due hereunder, Hospital shall have the right to terminate this Agreement upon [* * *] business days written notice, unless Company makes such payments plus any interest due, as set forth in Section 4.7, within said [* * *] day notice period. If payments are not made, Hospital may immediately terminate this Agreement at the end of said [* * *] day period. Company shall be entitled to only [* * *] such cure periods in a calendar year; for a [* * *] failure to make payment on time, Hospital shall have the right to terminate this Agreement immediately upon written notice.

  • Termination for continuing Force Majeure Event Either Party may, by written notice to the other, terminate this Framework Agreement if a Force Majeure Event endures for a continuous period of more than one hundred and twenty (120) Working Days.

  • Commercial Operation Date (COD 15.1.1 The Project shall be deemed to be complete when the Completion Certificate or the Provisional Certificate, as the case may be, is issued under the provisions of Article 14, and accordingly the commercial operation date of the Project shall be the date on which such Completion Certificate or the Provisional Certificate is issued (the “COD”). The Project shall enter into commercial service on COD whereupon the Concessionaire shall be entitled to demand and collect Annuity Payments in accordance with the provisions of this Agreement.

  • Termination Notice for Force Majeure Event If a Force Majeure Event subsists for a period of 180 (one hundred and eighty) days or more within a continuous period of 365 (three hundred and sixty five) days, either Party may in its discretion terminate this Agreement by issuing a Termination Notice to the other Party without being liable in any manner whatsoever, save as provided in this Article 34, and upon issue of such Termination Notice, this Agreement shall, notwithstanding anything to the contrary contained herein, stand terminated forthwith; provided that before issuing such Termination Notice, the Party intending to issue the Termination Notice shall inform the other Party of such intention and grant 15 (fifteen) days time to make a representation, and may after the expiry of such 15 (fifteen) days period, whether or not it is in receipt of such representation, in its sole discretion issue the Termination Notice.

  • Commercial Operation Date (COD) Bus Terminal and Commercial Complex shall be deemed to be complete when the Completion Certificate or the Provisional Certificate, as the case may be, is issued under the provisions of Article 14, and accordingly the commercial operation date of the Project shall be the date on which such Completion Certificate or the Provisional Certificate is issued (the “COD”). The Bus Terminal and Commercial Complex shall enter into commercial service on COD whereupon the Concessionaire shall be entitled to demand and collect Fee in accordance with provisions of Article 27 and that the entry of Bus Terminal or part thereof into commercial service shall always be subject to compliance with the provisions of Clause 18.3 and Clause 26.2.

  • Termination for Failure to Become Effective This Agreement and all obligations of the parties under it shall terminate if it has not entered into effect by the date ninety (90) days after the date of this Agreement, unless the World Bank, after consideration of the reasons for the delay, establishes a later date for the purpose of this Section. The World Bank shall promptly notify the Recipient of such later date.

  • Termination for Default The County may, by written notice to the Contractor terminate this contract for default in whole or in part (delivery orders, if applicable) if the Contractor fails to:

  • SUSPENSION & TERMINATION FOR DEFAULT Enterprise Services may suspend Contractor’s operations under this Master Contract immediately by written cure notice of any default. Suspension shall continue until the default is remedied to Enterprise Services’ reasonable satisfaction; Provided, however, that, if after thirty (30) days from such a suspension notice, Contractor remains in default, Enterprise Services may terminate Contractor’s rights under this Master Contract. All of Contractor’s obligations to Enterprise Services and Purchasers survive termination of Contractor’s rights under this Master Contract, until such obligations have been fulfilled.

  • Cure Period Prior to any claim for default being made, either the Buyer or Seller will have an opportunity to cure any alleged default. If either Buyer or Seller fails to comply with any provision of this Agreement, the other party will deliver written notice to the non- complying party specifying such non-compliance. The non-complying party shall have calendar days after delivery of such notice to cure the non-compliance.