Tests 37. If the Project Manager instructs the Contractor to carry out a test not specified in the Specification to check whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test and any samples. If there is no Defect, the test shall be a Compensation Event.
Appears in 14 contracts
Samples: Contract for Rehabilitation Works, Contract Agreement, Construction Contract
Tests 37. .1 If the Project Manager instructs the Contractor to carry out a test not specified in the Specification to check whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test and any samples. If there is no Defect, the test shall be a Compensation Event.
Appears in 3 contracts
Samples: Contract Agreement, Construction Contract, Construction Contract