The Contractor’s Obligations. 2.1 Programme for the Works, Commence, Complete and Remedy Defects in the Works: The Contractor: 2.1.1 must prior to commencing the Works, the Contractor shall prepare a programme for the Works and submit it to the Principal’s Representative. The Programme shall demonstrate how the Contractor proposes to meet the Due Date for Completion. The Contractor shall use the programme to track and report actual progress against planned dates and to forecast the likely dates for Practical Completion of the Works. No payment otherwise due under the Contract shall become payable until the Contractor has submitted the programme to the Principal’s Representative. From time to time the Principal’s Representative may require the Contractor to amend its programme to take account of the actual progress of the Works so as to achieve completion by the Due Date for Completion or as soon as reasonably practicable thereafter. The Principal’s Representative may further require the Contractor to indicate the means by which the programmed progress will be achieved; 2.1. 1A agrees that the Principal’s condition report attached as Appendix 14 to this Contract accurately reflects the condition of the Relocatable Buildings prior to the commencement of the Works; 2.1.2 must commence the Works on the Commencement Date or as soon thereafter as the Principal makes the [applicable part of the ]Site available and the necessary consents are in place; 2.1.3 must provide all services, labour, materials, plant, temporary works, {. .
Appears in 2 contracts
Samples: Medium Works Contract, Medium Works Contract
The Contractor’s Obligations. 2.1 Programme for the Works, Commence, Complete and Remedy Defects in the Works: The Contractor:
2.1.1 must prior to commencing the Works, the Contractor shall prepare a programme for the Works and submit it to the Principal’s Representative. The Programme shall demonstrate how the Contractor proposes to meet the Due Date for Completion. The Contractor shall use the programme to track and report actual progress against planned dates and to forecast the likely dates for Practical Completion of the Works. No payment otherwise due under the Contract shall become payable until the Contractor has submitted the programme to the Principal’s Representative. From time to time the Principal’s Representative may require the Contractor to amend its programme to take account of the actual progress of the Works so as to achieve completion by the Due Date for Completion or as soon as reasonably practicable thereafter. The Principal’s Representative may further require the Contractor to indicate the means by which the programmed progress will be achieved;
[2.1. 1A agrees that the Principal’s condition report attached as Appendix 14 to this Contract accurately reflects the condition of the Relocatable Buildings prior to the commencement of the Works;; ]
2.1.2 must commence the Works on the Commencement Date or as soon thereafter as the Principal makes the [applicable part of the ]Site available and the necessary consents are in place;
2.1.3 must provide all services, labour, materials, plant, temporary works, {. .
Appears in 1 contract
Samples: Medium Works Contract
The Contractor’s Obligations. 2.1 Programme for the Works, Commence, Complete and Remedy Defects in the Works: The Contractor:
2.1.1 must prior to commencing the Works, the Contractor shall prepare a programme for the Works and submit it to the Principal’s Representative. The Programme shall demonstrate how the Contractor proposes to meet the Due Date for Completion. The Contractor shall use the programme to track and report actual progress against planned dates and to forecast the likely dates for Practical Completion of the Works. No payment otherwise due under the Contract shall become payable until the Contractor has submitted the programme to the Principal’s Representative. From time to time the Principal’s Representative may require the Contractor to amend its programme to take account of the actual progress of the Works so as to achieve completion by the Due Date for Completion or as soon as reasonably practicable thereafter. The Principal’s Representative may further require the Contractor to indicate the means by which the programmed progress will be achieved;
[2.1. 1A agrees that the Principal’s condition report attached as Appendix 14 12 to this Contract accurately reflects the condition of the Relocatable Buildings prior to the commencement of the Works;; ]
2.1.2 must commence the Works on the Commencement Date or as soon thereafter as the Principal makes the [applicable part of the ]Site available and the necessary consents are in place;
2.1.3 must provide all services, labour, materials, plant, temporary works, {. .
Appears in 1 contract
Samples: Medium Works Contract
The Contractor’s Obligations. 2.1 Programme for the Works, Commence, Complete and Remedy Defects in the Works: The ContractorContractor must:
2.1.1 must prior to commencing the Works, the Contractor shall prepare a programme for the Works and submit it to the Principal’s Representative. The Programme shall demonstrate how the Contractor proposes to meet the Due Date for Completion. The Contractor shall use the programme to track and report actual progress against planned dates and to forecast the likely dates for Practical Completion of the Works. No payment otherwise due under the Contract shall become payable until the Contractor has submitted the programme to the Principal’s Representative. From time to time the Principal’s Representative may require the Contractor to amend its programme to take account of the actual progress of the Works so as to achieve completion by the Due Date for Completion or as soon as reasonably practicable thereafter. The Principal’s Representative may further require the Contractor to indicate the means by which the programmed progress will be achieved;
2.1. 1A agrees that the Principal’s condition report attached as Appendix 14 to this Contract accurately reflects the condition of the Relocatable Buildings prior to the commencement of the Works;
2.1.2 must commence the Works on the Commencement Date or as soon thereafter as the Principal makes the [applicable part of the ]Site available and the necessary consents are in place;
2.1.3 must provide all services, labour, materials, plant, temporary works, {. .
Appears in 1 contract
Samples: Medium Works Contract
The Contractor’s Obligations. 2.1 Programme for the Works, Commence, Complete and Remedy Defects in the Works: The ContractorContractor must:
2.1.1 must prior to commencing the Works, the Contractor shall prepare a programme for the Works and submit it to the Principal’s Representative. The Programme shall demonstrate how the Contractor proposes to meet the Due Date for Completion. The Contractor shall use the programme to track and report actual progress against planned dates and to forecast the likely dates for Practical Completion of the Works. No payment otherwise due under the Contract shall become payable until the Contractor has submitted the programme to the Principal’s Representative. From time to time the Principal’s Representative may require the Contractor to amend its programme to take account of the actual progress of the Works so as to achieve completion by the Due Date for Completion or as soon as reasonably practicable thereafter. The Principal’s Representative may further require the Contractor to indicate the means by which the programmed progress will be achieved;
2.1. 1A agrees that the Principal’s condition report attached as Appendix 14 to this Contract accurately reflects the condition of the Relocatable Buildings prior to the commencement of the Works;
2.1.2 must commence the Works on the Commencement Date or as soon thereafter as the Principal makes the [applicable part of the ]Site available and the necessary consents are in place;
2.1.3 must provide all services, labour, materials, plant, temporary works, {. transport and everything necessary to undertake and complete the Works except for any Principal supplied items as stated in the Special Conditions, and shall not be entitled to substitute any product specified in the Drawings or Specifications without the Principal's prior written approval;
2.1.4 proceed with the Works with due care and diligence and in a proper and workmanlike manner and must complete the Works in accordance with the Contract by the Due Date for Completion;
2.1.5 ensure the Works on completion are fit for the purpose for which they are intended as can reasonably be ascertained from the Contract; and
2.1.6 promptly remedy defects in accordance with section 6 of the Contract.
Appears in 1 contract
Samples: Medium Works Contract
The Contractor’s Obligations. 2.1 Programme for the Works, Commence, Complete and Remedy Defects in the Works: The Contractor:
2.1.1 must prior to commencing the Works, the Contractor shall prepare a programme for the Works and submit it to the Principal’s Representative. The Programme shall demonstrate how the Contractor proposes to meet the Due Date for Completion. The Contractor shall use the programme to track and report actual progress against planned dates and to forecast the likely dates for Practical Completion of the Works. No payment otherwise due under the Contract shall become payable until the Contractor has submitted the programme to the Principal’s Representative. From time to time the Principal’s Representative may require the Contractor to amend its programme to take account of the actual progress of the Works so as to achieve completion by the Due Date for Completion or as soon as reasonably practicable thereafter. The Principal’s Representative may further require the Contractor to indicate the means by which the programmed progress will be achieved;
[2.1. 1A agrees that the Principal’s condition report attached as Appendix 14 13 to this Contract accurately reflects the condition of the Relocatable Buildings prior to the commencement of the Works;]
2.1.2 must commence the Works on the Commencement Date or as soon thereafter as the Principal makes the [applicable part of the ]Site available and the necessary consents are in place;
2.1.3 must provide all services, labour, materials, plant, temporary works, {. .,
Appears in 1 contract
Samples: Medium Works Contract