Common use of Three Month Rolling Clause in Contracts

Three Month Rolling. Programme (1) The Three Month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation and execution of the work within these periods. In particular, the Contractor shall expand each activity planned to occur during the next three(3) month period, if necessary to a daily level of detail. (2) The Three Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram format. Bar charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall be derivatives of and directly related to tasks in the approved Works Programme.

Appears in 19 contracts

Samples: Contract Agreement, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Three Month Rolling. Programme (1) The Three Month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation organization and execution of the work within these periods. In particular, the Contractor shall expand each activity planned to occur during the next three(3) month period, if necessary to a daily level of detail. (2) The Three Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram format. Bar charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall be derivatives of and directly related to tasks in the approved Works Programme.

Appears in 2 contracts

Samples: Contract Agreement, Contract Agreement

Three Month Rolling. Programme (1) The Three Month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation and execution of the work within these periods. In particular, the Contractor shall expand each activity planned to occur during the next three(3three (3) month period, if necessary to a daily level of detail. (2) The Three Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram format. Bar charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall be derivatives of and directly related to tasks in the approved Works Programme.

Appears in 2 contracts

Samples: Contract Agreement, Construction Contract

AutoNDA by SimpleDocs

Three Month Rolling. Programme (1) The Three Three-Month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Three- Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation organization and execution of the work within these periods. In particular, the Contractor shall expand each activity planned to occur during the next three(3three (3) month period, if necessary to a daily level of detail. (2) The Three Three-Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram format. Bar charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall be derivatives of and directly related to tasks in the approved Works Programme.

Appears in 1 contract

Samples: Construction Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!