Time for Submission of Requests for Extensions of Time Sample Clauses

Time for Submission of Requests for Extensions of Time. On or before the fifteenth (15th) day of each month of the Work, Contractor shall submit in writing a request for all time extensions to which it believes itself to be entitled for the preceding month, other than time extensions for Changes in the Work, which are to be submitted in accordance with the requirements of Article XIV. If Contractor’s request for time extension for Changes in the Work is denied and Contractor wishes to pursue the matter, Contractor shall submit in writing a request for that extension by the fifteenth (15th) day of the month following the denial. Any Claim for time extension not submitted in accordance with the terms herein shall be waived.
AutoNDA by SimpleDocs

Related to Time for Submission of Requests for Extensions of Time

  • Deadline for Submission of Bids 19.1 Bids must be received by the Purchaser at the address specified under ITB Clause 18.2 no later than the time and date specified in the Bid Data Sheet.

  • Requests for Extension The Borrower may, by notice to the Administrative Agent (who shall promptly notify the Lenders) not earlier than 90 days and not later than 35 days prior to an anniversary of the Closing Date (each, an “Applicable Anniversary Date”), request that each Lender extend such Lender’s Maturity Date for an additional year from the Maturity Date then in effect for such Lender hereunder (such Lender’s “Existing Maturity Date”). The Borrower may request such an extension no more than two times.

  • Requests for Swing Loans Borrower shall give Administrative Agent prior notice (which may be written or oral) no later than 12:00 Noon on the date upon which Borrower requests that any Swing Loan be made, of the amount and date of such Swing Loan, and, if applicable, the Interest Period requested therefor. Administrative Agent shall promptly advise the Swing Line Lender of any such notice received from Borrower. After receiving such notice, the Swing Line Lender shall in its discretion quote an interest rate to Borrower at which the Swing Line Lender would be willing to make such Swing Loan available to Borrower for the Interest Period so requested (the rate so quoted for a given Interest Period being herein referred to as “Swing Line Lender’s Quoted Rate”). Borrower acknowledges and agrees that the interest rate quote is given for immediate and irrevocable acceptance. If Borrower does not so immediately accept the Swing Line Lender’s Quoted Rate for the full amount requested by Borrower for such Swing Loan, the Swing Line Lender’s Quoted Rate shall be deemed immediately withdrawn and such Swing Loan shall bear interest at the rate per annum determined by adding the Applicable Margin for Base Rate Loans under the Revolving Credit to the Base Rate as from time to time in effect. Subject to the terms and conditions hereof, the proceeds of each Swing Loan extended to Borrower shall be deposited or otherwise wire transferred to Borrower’s Designated Disbursement Account or as Borrower, Administrative Agent, and the Swing Line Lender may otherwise agree. Anything contained in the foregoing to the contrary notwithstanding, the undertaking of the Swing Line Lender to make Swing Loans shall be subject to all of the terms and conditions of this Agreement (provided that the Swing Line Lender shall be entitled to assume that the conditions precedent to an advance of any Swing Loan have been satisfied unless notified to the contrary by Administrative Agent or the Required Lenders).

  • Time Limits for Submission of Claim Failure by Purchaser to submit a Claim within established time limits shall relinquish the United States from any and all obligations whatsoever arising under the contract or portions thereof. Purchaser shall file such Claim within the following time limits: (a) When Purchaser constructs Specified Road, Pur- chaser must file any Claim not later than 60 days after re- ceipt of Forest Service written notification of acceptance; (b) When Forest Service constructs Specified Road, Purchaser must file any Claim not later than 60 days after receipt of Forest Service written notification authorizing use of road; (c) For subdivisions or cutting units, Purchaser must file any Claim not later than 60 days after receipt of Forest Service written notification that subdivision or cutting unit has been accepted; and (d) In all other cases, Purchaser must file any Claim not later than 60 days after receipt of Contracting Officer written notification that timber sale is closed.

  • Timely Written Requests for Extensions CHSI may, in advance of the due date, submit a timely written request for an extension of time to perform any act or file any notification or report required by this CIA. Notwithstanding any other provision in this Section, if OIG grants the timely written request with respect to an act, notification, or report, Stipulated Penalties for failure to perform the act or file the notification or report shall not begin to accrue until one day after CHSI fails to meet the revised deadline set by OIG. Notwithstanding any other provision in this Section, if OIG denies such a timely written request, Stipulated Penalties for failure to perform the act or file the notification or report shall not begin to accrue until three business days after CHSI receives OIG’s written denial of such request or the original due date, whichever is later. A “timely written request” is defined as a request in writing received by OIG at least five business days prior to the date by which any act is due to be performed or any notification or report is due to be filed.

  • Requests for Loans (a) Borrower shall give to Agent written notice in the form of Exhibit D-1 hereto (or telephonic notice confirmed in writing in the form of Exhibit D-1 hereto) of each Loan (other than a Swing Line Loan) requested hereunder (a “Loan Request”) by 12:00 noon (Cleveland time) on the Business Day prior to the proposed Drawdown Date with respect to Base Rate Loans and three (3) Business Days prior to the proposed Drawdown Date with respect to LIBOR Rate Loans. Each such notice shall specify with respect to the requested Loan the proposed principal amount of such Loan, the Type of Loan, the initial Interest Period (if applicable) for such Loan and the Drawdown Date. Each such notice shall also contain a statement that the conditions to borrowing set forth in §11 hereof have been satisfied. Promptly upon receipt of any such notice, Agent shall notify each of Lenders thereof. Each such Loan Request shall be irrevocable and binding on Borrower and shall obligate Borrower to accept the Loan requested from Lenders on the proposed Drawdown Date. Subject to §2.1(c)(iv), each Loan Request shall be (a) for a Base Rate Loan in a minimum aggregate amount of $1,000,000 or an integral multiple of $100,000 in excess thereof; or (b) for a LIBOR Rate Loan in a minimum aggregate amount of $2,000,000 or an integral multiple of $100,000 in excess thereof; provided, however, that there shall be no more than eight (8) LIBOR Rate Loans outstanding at any one time. (b) Borrower shall give to Agent and Swing Line Lender written notice in the form of Exhibit D-2 hereto (or telephonic notice confirmed in writing in the form of Exhibit D-2 hereto) of each Swing Line Loan requested hereunder (a “Request for Swing Line Loan”) by 1:00 p.m. (Cleveland time) on the Business Day of the proposed borrowing of a Swing Line Loan. On the date of the requested Swing Line Loan and subject to satisfaction of the applicable conditions set xxxxx xx §00 for all borrowings, Swing Line Lender will make the proceeds of such Swing Line Loan available to Borrower in Dollars, in immediately available funds, at the account specified by Borrower in its Request for Swing Line Loan not later than 3:00 p.m. (Cleveland time) on such date. Each such Request for Swing Line Loan shall also contain a statement that the conditions to borrowing set forth in §11 hereof have been satisfied.

  • Claims for Additional Time If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

  • Requests for Exclusion 9.1 The provisions of this section shall apply to any request by a Class Member for exclusion from the Class. 9.2 Any Class Member may make a request for exclusion by submitting such request in writing as set forth in the Notice. 9.3 Any request for exclusion must be submitted no later than the date specified in the Court’s preliminary approval order. 9.4 Any request for exclusion shall (i) state the Class Member’s full name and current address, (ii) provide the model year and Vehicle Identification Number (“VIN”) of his/her/its Class Vehicle(s) and the approximate date(s) of purchase or lease, and (iii) specifically and clearly state his/her/its desire to be excluded from the Settlement and from the Class. 9.5 Failure to comply with these requirements and to timely submit the request for exclusion will result in the Class Member being bound by the terms of the Settlement Agreement. 9.6 Any Class Member who submits a timely request for exclusion may not file an objection to the Settlement and shall be deemed to have waived any rights or benefits under this Settlement Agreement. 9.7 The Settlement Administrator shall report the names of all Class Members who have submitted a request for exclusion to the Parties on a weekly basis, beginning 30 days after the Notice Date. 9.8 Co-Lead Class Counsel represent and warrant that they have no other agreements with other counsel respecting Class Members, including any agreements with respect to referring, soliciting, or encouraging any Class Members to request to be excluded (or “opt out”) from this agreement. 9.9 Upon certification of the Class in connection with the Preliminary Approval of this agreement, Co-Lead Class Counsel agree to seek in the Preliminary Approval Order from the Court a provision encouraging all written communications to multiple Class Members with respect to this Agreement to be reviewed and approved by Co-Lead Class Counsel and the Court, and Co- Lead Class Counsel agree to abide by that provision as may be required by the Court.

  • Filing of Amendments; Response to Commission Requests The Company will promptly advise the Representatives of any proposal to amend or supplement at any time the Initial Registration Statement, any Additional Registration Statement or any Statutory Prospectus and will not effect such amendment or supplementation without the Representatives’ consent; and the Company will also advise the Representatives promptly of (i) the effectiveness of any Additional Registration Statement (if its Effective Time is subsequent to the execution and delivery of this Agreement), (ii) any amendment or supplementation of a Registration Statement or any Statutory Prospectus, (iii) any request by the Commission or its staff for any amendment to any Registration Statement, for any supplement to any Statutory Prospectus or for any additional information, (iv) the institution by the Commission of any stop order proceedings in respect of a Registration Statement or the threatening of any proceeding for that purpose, and (v) the receipt by the Company of any notification with respect to the suspension of the qualification of the Offered Securities in any jurisdiction or the institution or threatening of any proceedings for such purpose. The Company will use its best efforts to prevent the issuance of any such stop order or the suspension of any such qualification and, if issued, to obtain as soon as possible the withdrawal thereof.

  • Extension of time for completion (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely: (a) delay in providing the Right of Way of Construction Zone, environmental clearances or approval of railway authorities, specified in Clause 3.1 (iv); (b) Change of Scope (unless an adjustment to the Scheduled Completion Date has been agreed under Article 13); (c) occurrence of a Force Majeure Event; (d) any delay, impediment or prevention caused by or attributable to the Authority, the Authority's personnel or the Authority's other contractors on the Site; and (e) any other cause or delay which entitles the Contractor to Time Extension in accordance with the provisions of this Agreement. (ii) The Contractor shall, no later than 15 (fifteen) business days from the occurrence of an event or circumstance specified in Clause 10.5 (i), inform the Authority’s Engineer by notice in writing, with a copy to the Authority, stating in reasonable detail with supporting particulars, the event or circumstances giving rise to the claim for Time Extension in accordance with the provisions of this Agreement. Provided that the period of 15 (fifteen) business days shall be calculated from the date on which the Contractor became aware, or should have become aware, of the occurrence of such an event or circumstance. Provided further that notwithstanding anything to the contrary contained in this Agreement, Time Extension shall be due and applicable only for the Works which are affected by the aforesaid events or circumstances and shall not in any manner affect the Project Completion Schedule for and in respect of the Works which are not affected hereunder. (iii) On the failure of the Contractor to issue to the Authority’s Engineer a notice in accordance with the provisions of Clause 10.5 (ii) within the time specified therein, the Contractor shall not be entitled to any Time Extension and shall forfeit its right for any such claims in future. For the avoidance of doubt, in the event of failure of the Contractor to issue notice as specified in this clause 10.5 (iii), the Authority shall be discharged from all liability in connection with the claim. (iv) The Authority’s Engineer shall, on receipt of the claim in accordance with the provisions of Clause 10.5 (ii), examine the claim expeditiously within the time frame specified herein. In the event the Authority’s Engineer requires any clarifications to examine the claim, the Authority’s Engineer shall seek the same within 15 (fifteen) days from the date of receiving the claim. The Contractor shall, on receipt of the communication of the Authority’s Engineer requesting for clarification, furnish the same to the Authority’s Engineer within 10 (ten) days thereof. The Authority’s Engineer shall, within a period of 30 (thirty) days from the date of receipt of such clarifications, forward in writing to the Contractor its determination of Time Extension. Provided that when determining each extension of time under this Clause 10.5, the Authority’s Engineer shall review previous determinations and may increase, but shall not decrease, the total Time Extension. (v) If the event or circumstance giving rise to the notice has a continuing effect: (a) a fully detailed claim shall be considered as interim; (b) the Contractor shall, no later than 10 (ten) days after the close of each month, send further interim claims specifying the accumulated delay, the extension of time claimed, and such further particulars as the Authority’s Engineer may reasonably require; and (c) the Contractor shall send a final claim within 30 (thirty) days after the effect of the event or the circumstance ceases. Upon receipt of the claim hereunder, the Authority’s Engineer shall examine the same in accordance with the provisions of Clause 10.5 (iv) within a period of 30 (thirty) days of the receipt thereof

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!