Treatment of Multiple Requests for Same Pole. If District receives permit applications for the same Pole from two or more prospective licensees within sixty (60) calendar days of the initial request, and accommodating their respective requests would require modification or replacement of the Pole, District will equitably allocate among such licensees the applicable costs associated with such modification or replacement. Such allocation applies only to those Attachments involving cable/wire and not Risers and/or other equipment.
Appears in 2 contracts
Samples: Pole Attachment License Agreement, Pole Attachment License Agreement
Treatment of Multiple Requests for Same Pole. If District Utility receives permit applications Permit Applications for the same Pole from two or more prospective licensees within sixty (60) calendar days of the initial request, and accommodating their respective requests would require modification or replacement of the Pole, District Utility will equitably allocate among such licensees the applicable costs associated with such modification or replacement. Such allocation applies only to those Attachments involving cable/wire and not Risers and/or other equipment.
Appears in 2 contracts
Samples: Pole Attachment License Agreement, Pole Attachment License Agreement
Treatment of Multiple Requests for Same Pole. If District City receives permit applications Permit Applications for the same Pole from two or more prospective licensees within sixty (60) calendar days of the initial request, and accommodating their respective requests would require modification or replacement of the Pole, District City will equitably allocate among such licensees the applicable costs associated with such modification or replacement. Such allocation applies only to those Attachments involving cable/wire and not Risers and/or other equipment.
Appears in 1 contract
Samples: Pole Attachment License Agreement
Treatment of Multiple Requests for Same Pole. If the District receives permit applications Permit Applications for the same Pole from two or more prospective licensees Licensees within sixty (60) calendar days of the initial request, and accommodating their respective requests would require modification or replacement of the Pole, the District will equitably allocate among such licensees Licensees the applicable costs associated with such modification or replacement. Such allocation applies only Allocation of Costs. Make Ready Costs shall be allocated to those Attachments involving cable/wire and not Risers and/or other equipment.the District and/or
Appears in 1 contract
Samples: Pole Attachment License Agreement
Treatment of Multiple Requests for Same Pole. If District Town receives permit applications Complete Permit Applications for the same Pole from two or more prospective licensees within sixty (60) calendar days of the initial request, and accommodating their respective requests would require modification or replacement of the Pole, District Town will equitably allocate among such licensees the applicable costs associated with such modification or replacement. Such allocation applies only to those Attachments involving cable/wire and not Risers and/or other equipment.
Appears in 1 contract
Samples: Pole Attachment License Agreement