Common use of Treatment of Multiple Requests for Same Pole Clause in Contracts

Treatment of Multiple Requests for Same Pole. If Utility receives Permit Applications for the same Pole from two or more prospective licensees within sixty (60) calendar days of the initial request, and accommodating their respective requests would require modification or replacement of the Pole, Utility will allocate among such licensees the applicable costs associated with such modification or replacement. Such allocation applies only to those Attachments involving cable/wire and not Risers and/or other equipment.

Appears in 2 contracts

Samples: Pole Attachment License Agreement, Pole Attachment License Agreement

AutoNDA by SimpleDocs

Treatment of Multiple Requests for Same Pole. If Utility receives Permit Applications for the same Pole from two or more prospective licensees within sixty (60) calendar days of the initial request, and accommodating their respective requests would require modification or replacement of the Pole, Utility will allocate among such licensees the applicable costs associated with such modification or replacement. Such allocation applies only to those Attachments involving cable/wire and not Risers and/or other equipment.

Appears in 1 contract

Samples: Pole Attachment License Agreement

Treatment of Multiple Requests for Same Pole. If the Electric Utility receives completed Permit Applications for the same Pole from two or more prospective licensees Licensees within sixty (60) calendar days of the initial request, and accommodating their respective requests would require modification of the Pole or replacement of the Pole, Electric Utility will allocate among such licensees Licensees the applicable costs associated with such modification or replacement. Such allocation applies only to those Attachments involving cable/wire and not Risers and/or other equipment.otherequipment. Placement of New Poles

Appears in 1 contract

Samples: Attachment License Agreement

Treatment of Multiple Requests for Same Pole. If Utility receives Permit Applications for the same Pole from two or more prospective licensees within sixty (60) calendar days of the initial request, and accommodating their respective requests would require modification of the Pole or replacement of the Pole, Utility will allocate among such licensees the applicable costs associated with such modification or replacement. Such allocation applies only to those Attachments involving cable/wire and not Risers and/or other equipment.

Appears in 1 contract

Samples: stillwater.org

AutoNDA by SimpleDocs

Treatment of Multiple Requests for Same Pole. If Utility receives Permit Applications for the same Pole from two (2) or more prospective licensees within a sixty (60) calendar days of the initial requestday period, and accommodating their respective requests would require modification or replacement of the Pole, Utility will evenly allocate among such licensees the applicable costs associated with such modification or replacement. Such allocation applies only to those Attachments involving cable/wire and not Risers and/or other equipment.

Appears in 1 contract

Samples: Licensing Agreement