TRENCH SHORING. If this Contract is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor must submit and obtain District’s approval and acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 40 contracts
Samples: Site Lease, Site Lease, Construction Contract
TRENCH SHORING. If this Contract is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor must submit and obtain District’s approval and District acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 26 contracts
Samples: Construction Agreement, Construction Services Agreement, Construction Agreement
TRENCH SHORING. If this Contract Agreement is in excess of Twenty-Five Thousand Dollars ($25,000 25,000) and is for the excavation of any trench deeper than five (5) feet, Contractor must submit and obtain District’s approval and acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 9 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
TRENCH SHORING. If this Contract is in excess of $25,000 and is for includes the excavation of any trench deeper than five (5) feet, pursuant to Labor Code section 6705, Contractor must submit and obtain District’s approval and Judicial Council acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 6 contracts
Samples: Agreement for Elevator Modernization, Agreement for Elevator Modernization, Agreement for Elevator Modernization
TRENCH SHORING. If this Contract Agreement is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor must submit and obtain District’s approval and District acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 4 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
TRENCH SHORING. If this Contract is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor Design-Builder must submit and obtain District’s approval and District acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 3 contracts
Samples: Design, Installation and Commissioning Agreement, Design, Installation and Commissioning Agreement, Master Design Build Contract
TRENCH SHORING. If this Contract is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor Provider must submit and obtain District’s approval and District acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 2 contracts
TRENCH SHORING. If this Contract is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor Design-Builder must submit and obtain District’s approval and District acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.trench
Appears in 1 contract
Samples: Energy Services Agreement
TRENCH SHORING. If this Contract Agreement is in excess of $25,000 and is for the Contract Documents include excavation of any trench deeper than five (5) feet, Contractor Design-Builder must submit and obtain District’s approval and District acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 1 contract
Samples: Agreement for Design, Installation and Commissioning of Energy Systems
TRENCH SHORING. If this Contract is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor must submit and obtain District’s approval and acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.be
Appears in 1 contract
Samples: Cupccaa Contract
TRENCH SHORING. If this Contract is in excess of Twenty Five Thousand Dollars ($25,000 25,000) and is for the excavation of any trench deeper than five (5) feet, Contractor Designer/Builder must submit and obtain District’s District acceptance and approval and acceptanceof, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 1 contract
Samples: Contract for Energy Efficiency Design / Build Services
TRENCH SHORING. If this Contract is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor Designer/Builder must submit and obtain District’s approval and District acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 1 contract
Samples: Design and Construction Contract
TRENCH SHORING. If this Contract is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor Designer/Builder must submit and obtain District’s approval and Customer acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
Appears in 1 contract
Samples: Contract for Design and Construction
TRENCH SHORING. If this Contract is in excess of $25,000 and is for the excavation of any trench deeper than five (5) feet, Contractor must submit and obtain District’s approval and District acceptance, in advance of excavation, of a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If the plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
15. GENERAL PERMIT FOR STORM WATER DISCHARGES ASSOCIATED WITH
Appears in 1 contract
Samples: Construction Services Agreement