USE OF THE WORK. (a) Project Co shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law or the Contract Documents and shall not unreasonably encumber the Work with Products. (b) Project Co shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work. (c) Owner shall have the right to occupy Phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, including the intended use of Owner before Substantial Completion of the Work, as provided for in the Construction Schedule. Project Co shall cooperate with Owner, the Owner’s Project Manager and the Consultant, so as to permit Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an acceptance of the Work or in any way relieve Project Co from responsibility to complete this Project Agreement. Subject to Section 11.19(d), Project Co is responsible to ensure the completion of Phases of the Work in accordance with the Phased Occupancy Dates and the Scheduled Substantial Completion Date and that the Phases of the Work are ready for occupancy by Owner in accordance with the Contract Documents including the requirements of paragraphs (b) and (c), and to the extent available, paragraph (d) of Section 1.196 of Schedule 1-Definitions and Interpretation “Substantial Completion”, as applicable to the respective Phase of the Work. Project Co acknowledges that Substantial Completion of the Work is only achieved in respect of the Work as a whole and not in respect of any Phase of the Work.
Appears in 2 contracts
Samples: Project Agreement, Project Agreement
USE OF THE WORK. (a) Project Co 3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Work with Products.
(b) Project Co 3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work.
(c) 3.12.3 The Owner shall have the right to occupy Phases phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, uses including the intended use of the Owner before Substantial Completion Performance of the Work, as provided for in the Construction Schedule. Project Co The Contractor shall cooperate with the Owner, the Owner’s Project Manager and the Consultant, so as to permit the Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an as acceptance of the Work or in any way relieve Project Co the Contractor from responsibility to complete this Project Agreementthe Contract. Subject to Section 11.19(d), Project Co The Contractor is responsible to ensure the completion of Phases phases of the Work in accordance with the Phased Occupancy Dates and the Scheduled Substantial Completion Date and that the Phases phases of the Work are ready for occupancy by the Owner in accordance with the Contract Documents including the requirements of paragraphs (b) subparagraphs .2 and (c).3 and, and to the extent available, paragraph (d) .4 of Section 1.196 the definition of Schedule 1-Definitions and Interpretation “Substantial Completion”, Performance of the Work as applicable to the respective Phase phase of the Work. Project Co The Contractor acknowledges that Substantial Completion Performance of the Work is only achieved in respect of to the Work as a whole and not in respect of any Phase phase of the Work.
3.12.4 The Contractor recognizes that part of the Work consists of the renovation of existing buildings and structures or the addition of a structure to an existing building and that the provision of patient care during construction is a priority for the Owner and acknowledges that it has reviewed the Contract Documents referred to in GC 3.12.5 below. The Contractor shall use all methods required to comply with the instructions set out in the Contract Documents including those referred to in GC 3.12.5 during the performance of the Work. The Contractor shall fully cooperate with the Owner in complying with the said instructions during the performance of the Work. Any costs incurred by the Contractor in complying with the said instructions shall be part of the Guaranteed Price.
3.12.5 The Contractor acknowledges that the Contract Documents include instructions titled “Special Procedures for Work in Hospitals” (Specification section 01390) which include instructions respecting Owner’s use of the Existing Hospital and infection control procedures including CSA Standard Z317.13-03 Infection Control During Construction or Renovation of Health Care Facilities and Risk Assessment and Preventive Measures Checklist for Health Care Facility Construction and Renovation. The Contractor acknowledges having read and understood the said instructions and agrees to comply with the procedures set out therein. The Contractor shall be responsible for any costs and expenses resulting from its failure to comply with these procedures.
Appears in 2 contracts
Samples: Guaranteed Price Contract, Guaranteed Price Contract
USE OF THE WORK. (a) Project Co 3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Work with Products.
(b) Project Co 3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work.
(c) 3.12.3 The Owner shall have the right to occupy Phases phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, uses including the intended use of the Owner before Substantial Completion Performance of the Work, as provided for in the Construction Schedule. Project Co The Contractor shall cooperate with the Owner, the Owner’s Project Manager and the Consultant, so as to permit the Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an as acceptance of the Work or in any way relieve Project Co the Contractor from responsibility to complete this Project Agreementthe Contract. Subject to Section 11.19(d), Project Co The Contractor is responsible to ensure the completion of Phases phases of the Work in accordance with the Phased Occupancy Dates date for Completion of the Phase 1A Work, and the Scheduled date for Substantial Completion Date Performance of the Work and that the Phases phases of the Work are ready for occupancy by the Owner in accordance with the Contract Documents including the requirements of paragraphs (b) subparagraphs .2 and (c).3 and, and to the extent available, paragraph (d) .4 of Section 1.196 the respective definitions of Schedule 1-Definitions Completion of the Phase 1A Work and Interpretation “Substantial Completion”, Performance of the Work as applicable to the respective Phase phase of the Work. Project Co The Contractor acknowledges that Substantial Completion Performance of the Work is only achieved in respect of to the Work as a whole and not in respect of any Phase phase of the Work.
3.12.4 The Contractor recognizes that part of the Work consists of the renovation of existing buildings and structures or the addition of a structure to an existing building and that the provision of patient care during construction is a priority for the Owner and acknowledges that it has reviewed the Contract Documents referred to in GC 3.12.5 below. The Contractor shall use all methods required to comply with the instructions set out in the Contract Documents including those referred to in GC 3.12.5 during the performance of the Work. The Contractor shall fully cooperate with the Owner in complying with the said instructions during the performance of the Work. Any costs incurred by the Contractor in complying with the said instructions shall be part of the Guaranteed Price.
3.12.5 The Contractor acknowledges that the Contract Documents include instructions titled under “IC- Construction & Renovation Precautions Guidelines” and “IC-Guidelines for Construction & Renovation Precaution Procedure - Xxxxxxxx Regional Hospitals - Infection Prevention & Control” (included as part of Document 0 Introductory section of the Specification) which include instructions respecting Owner’s use of the Existing Hospital and infection control procedures including CSA Standard Z317.13-03 Infection Control During Construction or Renovation of Health Care Facilities and Risk Assessment and
Appears in 1 contract
Samples: Guaranteed Price Contract
USE OF THE WORK. (a) Project Co 3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Work with Products.
(b) Project Co 3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work.
(c) 3.12.3 The Owner shall have the right to occupy Phases phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, uses including the intended use of the Owner before Substantial Completion Performance of the Work, as provided for in the Construction Schedule. Project Co The Contractor shall cooperate with the Owner, the Owner’s Project Manager and the Consultant, so as to permit the Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an as acceptance of the Work or in any way relieve Project Co the Contractor from responsibility to complete this Project Agreementthe Contract. Subject to Section 11.19(d), Project Co The Contractor is responsible to ensure the completion of Phases phases of the Work in accordance with the Phased Occupancy Dates date for Completion of the Interim Work and the Scheduled date for Substantial Completion Date of the Work and that the Phases phases of the Work are ready for occupancy by the Owner in accordance with the Contract Documents including the requirements of paragraphs (b) subparagraphs .2 and (c).3 and, and to the extent available, paragraph (d) .4 of Section 1.196 the definition of Schedule 1-Definitions and Interpretation “Substantial Completion”, Performance of the Work as applicable to the respective Phase phase of the Work. Project Co The Contractor acknowledges that Substantial Completion Performance of the Work is only achieved in respect of to the Work as a whole and not in respect of any Phase phase of the Work.
3.12.4 The Contractor recognizes that part of the Work consists of the renovation of existing buildings and structures or the addition of a structure to an existing building and that the provision of patient care during construction is a priority for the Owner and acknowledges that it has reviewed the Contract Documents referred to in GC 3.12.5 below. The Contractor shall use all methods required to comply with the instructions set out in the Contract Documents including those referred to in GC 3.12.5 during the performance of the Work. The Contractor shall fully cooperate with the Owner in complying with the said instructions during the performance of the Work. Any costs incurred by the Contractor in complying with the said instructions shall be part of the Guaranteed Price.
3.12.5 The Contractor acknowledges that the Contract Documents include instructions titled “Special Procedures for Work in Hospitals” (Specification section 01351) which include instructions respecting Owner’s use of the Existing Hospital and infection control procedures including CSA Standard Z317.13-03 Infection Control During Construction or Renovation of Health Care Facilities and Risk Assessment and
Appears in 1 contract
Samples: Guaranteed Price Contract
USE OF THE WORK. (a) Project Co 3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Work with Products.
(b) Project Co 3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work.
(c) 3.12.3 The Owner shall have the right to occupy Phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, uses including the intended use of the Owner before Substantial Completion Performance of the Work, as provided for in the Construction Schedule. Project Co The Contractor shall cooperate with the Owner, the Owner’s Project Manager and the Consultant, so as to permit the Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an as acceptance of the Work or in any way relieve Project Co the Contractor from responsibility to complete this Project Agreementthe Contract. Subject to Section 11.19(d), Project Co is responsible to ensure the completion of Phases of the Work in accordance with the Phased Occupancy Dates and the Scheduled Substantial Completion Date and that the Phases of the Work are ready for occupancy by Owner in accordance with the Contract Documents including the requirements of paragraphs (b) and (c), and to the extent available, paragraph (d) of Section 1.196 of Schedule 1-Definitions and Interpretation “Substantial Completion”, as applicable to the respective Phase of the Work. Project Co The Contractor acknowledges that Substantial Completion Performance of the Work is only achieved in respect of the Work as a whole whole.
3.12.4 The Contractor recognizes that part of the Work consists of the renovation of existing buildings and structures or the addition of a structure to an existing building and that the provision of patient care during construction is a priority for the Owner and acknowledges that it has reviewed the Contract Documents referred to in GC 3.12.5 below. The Contractor shall use all methods required to ensure that patient care services and all ancillary operations provided in the existing building are not in respect of any Phase disrupted during the performance of the Work. The Contractor shall fully cooperate with the Owner to ensure that the operations of the Owner are not at risk during the completion of the Work. Any costs incurred by the Contractor in ensuring ongoing coordination of the Project with the Owner’s existing operations shall be part of the Guaranteed Price.
3.12.5 The Contractor acknowledges that the Contract Documents include instructions titled “Renovations, Alterations and Repairs to Existing Building” under Section 01005 of Division 1 which includes instructions respecting Owner’s use of the existing building (Hospital) and Section 01150 of Division 1 which includes instructions pertaining to infection control procedures including CSA Standard Z317.13-03 Infection Control During Construction or Renovation of Health Care Facilities and Risk Assessment and Preventive Measures Checklist for Health Care Facility Construction and Renovation. The Contractor acknowledges having read and understood the said instructions and agrees to comply with the procedures set out therein. The Contractor shall be responsible for any costs and expenses resulting from its failure to comply with these procedures.
Appears in 1 contract
Samples: Guaranteed Price Contract
USE OF THE WORK. (a) Project Co 3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Work with Products.
(b) Project Co 3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work.
(c) 3.12.3 The Owner shall have the right to occupy Phases phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, uses including the intended use of the Owner before Substantial Completion Performance of the Work, as provided for in the Construction Schedule. Project Co The Contractor shall cooperate with the Owner, the Owner’s Project Manager and the Consultant, so as to permit the Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an as acceptance of the Work or in any way relieve Project Co the Contractor from responsibility to complete this Project Agreementthe Contract. Subject to Section 11.19(d), Project Co The Contractor is responsible to ensure the completion of Phases phases of the Work in accordance with the Phased Occupancy Dates and the Scheduled Substantial Completion Date and that the Phases phases of the Work are ready for occupancy by the Owner in accordance with the Contract Documents including the requirements of paragraphs (b) subparagraphs .2 and (c).3 and , and to the extent available, paragraph (d) .4 of Section 1.196 the definition of Schedule 1-Definitions and Interpretation “Substantial Completion”, Performance of the Work as applicable to the respective Phase phase of the Work. Project Co The Contractor acknowledges that Substantial Completion Performance of the Work is only achieved in respect of to the Work as a whole and not in respect of any Phase phase of the Work.
3.12.4 The Contractor recognizes that part of the Work consists of the renovation of existing buildings and structures or the addition of a structure to an existing building and that the provision of patient care during construction is a priority for the Owner and acknowledges that it has reviewed the Contract Documents referred to in GC 3.12.5 below. The Contractor shall use all methods required to comply with the instructions set out in the Contract Documents including those referred to in GC 3.12.5 during the performance of the Work. The Contractor shall fully cooperate with the Owner in complying with the said instructions during the performance of the Work. Any costs incurred by the Contractor in complying with the said instructions shall be part of the Guaranteed Price.
3.12.5 The Contractor acknowledges that the Contract Documents include instructions titled “Special Procedures for Work in Hospitals” (Specification section 01390) which include instructions respecting Owner’s use of the Existing Hospital and infection control procedures including CSA Standard Z317.13-03 Infection Control During Construction or Renovation of Health Care Facilities and Risk Assessment and Preventive Measures Checklist for Health Care Facility Construction and Renovation. The Contractor acknowledges having read and understood the said instructions and agrees to comply with the procedures set out therein. The Contractor shall be responsible for any costs and expenses resulting from its failure to comply with these procedures.
Appears in 1 contract
Samples: Guaranteed Price Contract
USE OF THE WORK. (a) Project Co 3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Work with Products.
(b) Project Co 3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work.
(c) 3.12.3 The Owner shall have the right to occupy Phases phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, uses including the intended use of the Owner before Substantial Completion Performance of the Work, as provided for in the Construction Schedule. Project Co The Contractor shall cooperate with the Owner, the Owner’s 's Project Manager and the Consultant, so as to permit the Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an as acceptance of the Work or in any way relieve Project Co the Contractor from responsibility to complete this Project Agreementthe Contract. Subject to Section 11.19(d), Project Co The Contractor is responsible to ensure the completion of Phases phases of the Work in accordance with the Phased Occupancy Dates date for Completion of the Phase 1 Work, and the Scheduled date for Substantial Completion Date of the Work as set out in the Contract Documents and that the Phases phases of the Work are ready for occupancy by the Owner in accordance with the Contract Documents including the requirements of paragraphs (b) and (c), and to the extent available, paragraph (d) definition of Section 1.196 Substantial Performance of Schedule 1-Definitions and Interpretation “Substantial Completion”, the Work as applicable to the respective Phase phase of the Work. Project Co The Contractor acknowledges that Substantial Completion Performance of the Work is only achieved in respect of the Work as a whole and not in respect of any Phase phase of the Work.
3.12.4 The Contractor recognizes that part of the Work consists of the renovation of existing buildings and structures or the addition of a structure to an existing building and that the provision of patient care during construction is a priority for the Owner and acknowledges that it has reviewed the Contract Documents referred to in GC 3.12.5 below. The Contractor shall use all methods required to comply with the instructions set out in the Contract Documents including those referred to in GC 3.12.5 during the performance of the Work. The Contractor shall fully cooperate with the Owner in complying with the said instructions during the performance of the Work. Any costs incurred by the Contractor in complying with the said instructions shall be part of the Guaranteed Price.
3.12.5 The Contractor acknowledges that the Contract Documents include sections within Division 1 of the Specifications respecting Owner’s use of the existing building (Hospital) and infection control procedures. The Contractor acknowledges having read and understood the said instructions and agrees to comply with the procedures set out therein. The Contractor shall be responsible for any costs and expenses resulting from its failure to comply with these procedures.
Appears in 1 contract
Samples: Guaranteed Price Contract
USE OF THE WORK. (a) Project Co 3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Work with Products.
(b) Project Co 3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work.
(c) 3.12.3 The Owner shall have the right to occupy Phases phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, uses including the intended use of the Owner before Substantial Completion Performance of the Work, as provided for in the Construction Schedule. Project Co The Contractor shall cooperate with the Owner, the Owner’s Project Manager and the Consultant, so as to permit the Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an as acceptance of the Work or in any way relieve Project Co the Contractor from responsibility to complete this Project Agreementthe Contract. Subject to Section 11.19(d), Project Co The Contractor is responsible to ensure the completion of Phases phases of the Work in accordance with the Phased Occupancy Dates and the Scheduled Substantial Completion Date and that the Phases phases of the Work are ready for occupancy by the Owner in accordance with the Contract Documents including the requirements of paragraphs (b) subparagraphs .2 and (c).3 and, and to the extent available, paragraph (d) .4 of Section 1.196 the definition of Schedule 1-Definitions and Interpretation “Substantial Completion”, Performance of the Work as applicable to the respective Phase phase of the Work. Project Co The Contractor acknowledges that Substantial Completion Performance of the Work is only achieved in respect of to the Work as a whole and not in respect of any Phase phase of the Work.
3.12.4 The Contractor recognizes that part of the Work consists of the renovation of existing buildings and structures or the addition of a structure to an existing building and that the provision of patient care during construction is a priority for the Owner and acknowledges that it has reviewed the Contract Documents referred to in GC 3.12.5 below. The Contractor shall use all methods required to comply with the instructions set out in the Contract Documents including those referred to in GC 3.12.5 during the performance of the Work. The Contractor shall fully cooperate with the Owner in complying with the said instructions during the performance of the Work. Any costs incurred by the Contractor in complying with the said instructions shall be part of the Guaranteed Price.
3.12.5 The Contractor acknowledges that the Contract Documents include instructions titled under “Special Procedures” and “Infection Prevention and Control” (Specification section 01 35 00 and 01 35 33) which include instructions respecting Owner’s use of the Existing Hospital and infection control procedures including CSA Standard Z317.13-03 Infection Control During Construction or Renovation of Health Care Facilities and Risk Assessment and
Appears in 1 contract
Samples: Guaranteed Price Contract
USE OF THE WORK. (a) Project Co 3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Work with Products.
(b) Project Co 3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work.
(c) 3.12.3 The Owner shall have the right to occupy Phases phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, uses including the intended use of the Owner before Substantial Completion Performance of the Work, as provided for in the Construction Schedule. Project Co The Contractor shall cooperate with the Owner, the OwnerHospital’s Project Manager and the Consultant, so as to permit the Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an as acceptance of the Work or in any way relieve Project Co the Contractor from responsibility to complete this Project Agreementthe Contract. Subject to Section 11.19(d), Project Co The Contractor is responsible to ensure the completion of Phases phases of the Work in accordance with the Phased Occupancy Dates Dates, the date for Completion of the Interim Work, and the Scheduled date for Substantial Completion Date of the Work as set out in the Contract Documents and that the Phases phases of the Work are ready for occupancy by the Owner in accordance with the Contract Documents including the requirements of paragraphs (b) subparagraphs .2 and (c).3 and, and to the extent available, paragraph (d) .4 of Section 1.196 the definition of Schedule 1-Definitions and Interpretation “Substantial Completion”, Performance of the Work as applicable to the respective Phase phase of the Work. Project Co The Contractor acknowledges that Substantial Completion Performance of the Work is only achieved in respect of to the Work as a whole and not in respect of any Phase phase of the Work.
3.12.4 The Contractor recognizes that part of the Work consists of the renovation of existing buildings and structures or the addition of a structure to an existing building and that the provision of patient care during construction is a priority for the Owner and acknowledges that it has reviewed the Contract Documents referred to in GC 3.12.5 below. The Contractor shall use all methods required to comply with the instructions set out in the Contract Documents including those referred to in GC 3.12.5 during the performance of the Work. The Contractor shall fully cooperate with the Owner in complying with the said instructions during the performance of the Work. Any costs incurred by the Contractor in complying with the said instructions shall be part of the Guaranteed Price.
3.12.5 The Contractor acknowledges that the Contract Documents include instructions titled “Special Procedures for Work in Hospitals” (Specification section 01390) which include instructions respecting Owner’s use of the Existing Hospital and infection control procedures including CSA Standard Z317.13-03 Infection Control During Construction or Renovation of Health Care Facilities and Risk Assessment and Preventive Measures Checklist for Health Care Facility Construction and Renovation. The Contractor acknowledges having read and understood the said instructions and agrees to comply with the procedures set out therein. The Contractor shall be responsible for any costs and expenses resulting from its failure to comply with these procedures.
Appears in 1 contract
Samples: Guaranteed Price Contract
USE OF THE WORK. (a) Project Co 3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of employees to limits indicated by Applicable Law laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Work with Products.
(b) Project Co 3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work.
(c) 3.12.3 The Owner shall have the right to occupy Phases phases of the Work as set out in the Contract Documents and to enter and occupy the Work in whole or in part for the purpose of placing fittings, furniture and equipment or for other uses, uses including the intended use of the Owner before Substantial Completion Performance of the Work, as provided for in the Construction Schedule. Project Co The Contractor shall cooperate with the Owner, the OwnerHospital’s Project Manager and the Consultant, so as to permit the Owner to occupy and to place such fittings, furniture and equipment in the most efficient manner possible. Such entry and occupation shall not be considered an as acceptance of the Work or in any way relieve Project Co the Contractor from responsibility to complete this Project Agreementthe Contract. Subject to Section 11.19(d), Project Co The Contractor is responsible to ensure the completion of Phases of the Work in accordance with the Phased Occupancy Dates date for Completion of the Interim Work and the Scheduled date for Substantial Completion Date and that the Phases of the Work are ready for occupancy by Owner in accordance with the Contract Documents including the requirements successful Commissioning of paragraphs (b) and (c), and to the extent available, paragraph (d) of Section 1.196 of Schedule 1such Work in accordance with GC 13.3-Definitions and Interpretation “Substantial Completion”, as applicable to the respective Phase of the WorkCOMMISSIONING. Project Co The Contractor acknowledges that Substantial Completion Performance of the Work is only achieved in respect of the Work as a whole and not in respect of any Phase phase of the Work.
3.12.4 The Contractor recognizes that part of the Work consists of the renovation of existing buildings and structures or the addition of a structure to an existing building and that the provision of patient care during construction is a priority for the Owner and acknowledges that it has reviewed the Contract Documents referred to in GC 3.12.5 below. The Contractor shall use all methods required to ensure that patient care services and all ancillary operations provided in the existing building is not disrupted during the performance of the Work. The Contractor shall fully cooperate with the Owner to ensure that the operations of the Owner are not at risk during the completion of the Work. Any costs incurred by the Contractor in ensuring ongoing coordination of the Project with the Owner’s existing operations shall be part of the Guaranteed Price.
3.12.5 The Contractor acknowledges that the Contract Documents include instructions titled “Work in Existing Building” (Section 01035 of Division 1) which include instructions respecting Owner’s use of the existing building (Hospital) and infection control procedures including CSA Standard Z317.13-03 Infection Control During Construction or Renovation of Health Care Facilities and Risk Assessment and Preventive Measures Checklist for Health Care Facility Construction and Renovation. The Contractor acknowledges having read and understood the said instructions and agrees to comply with the procedures set out therein. The Contractor shall be responsible for any costs and expenses resulting from its failure to comply with these procedures.
Appears in 1 contract
Samples: Guaranteed Price Contract