Common use of Without prejudice to D& Clause in Contracts

Without prejudice to D&. B Co's rights under Clause 24 (Delay Events and Compensation Events), D&B Co shall only be relieved of its obligations under Clauses 12 (The Design Construction and Commissioning Process), 13 (Right of Access of Authority's Representative), 14 (Programme and Dates for Completion), 17 (Pre-Completion Commissioning and Completion) and 24 (Delay Events and Compensation Events) by Delay Events in accordance with Clause 24 (Delay Events and Compensation Events).

Appears in 5 contracts

Samples: Template Education Design & Build Development Agreement, Template Education Design & Build Development Agreement, Template Education Design & Build Development Agreement