Work Change Directives. 12.4.1 A Work Change Directive is a written order prepared and signed by Design-Builder directing a change in the Work prior to agreement on an adjustment in the Contract Price and/or the times for completion of the Work. 12.4.2 Design-Builder and Design-Build Subcontractor shall negotiate in good faith and as expeditiously as possible the appropriate adjustments for the Work Change Directive. Upon reaching an agreement, the parties shall prepare and execute an appropriate Change Order reflecting the terms of the agreement.
Appears in 4 contracts
Samples: Standard Form of Agreement Between Design Builder and Design Build Subcontractor Lump Sum, Design Build Subcontract Agreement, Standard Form of Agreement Between Design Builder and Design Build Subcontractor
Work Change Directives. 12.4.1 9.2.1 A Work Change Directive is a written order prepared and signed by Design-Builder Owner, directing a change in the Work prior to agreement on an adjustment in the Contract Price and/or the times for completion of the WorkContract Time(s).
12.4.2 9.2.2 Owner and Design-Builder and Design-Build Subcontractor shall negotiate in good faith and as expeditiously as possible the appropriate adjustments for the Work Change Directive. Upon reaching an agreement, the parties shall prepare and execute an appropriate Change Order reflecting the terms of the agreement.
Appears in 4 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder—lump Sum (Aventine Renewable Energy Holdings Inc), Standard Form of Agreement Between Owner and Design Builder—lump Sum (Aventine Renewable Energy Holdings Inc), Standard Form of Agreement Between Owner and Design Builder (Lump Sum) (Little Sioux Corn Processors LLC)
Work Change Directives. 12.4.1 9.2.1 A Work Change Directive is a written order prepared and signed by Design-Builder Owner directing a change in the Work prior to agreement on an adjustment in the Contract Price and/or the times for completion of the WorkContract Time(s).
12.4.2 Design-Builder and Design-Build Subcontractor shall negotiate in good faith and as expeditiously as possible the appropriate adjustments for the Work Change Directive. Upon reaching an agreement, the parties shall prepare and execute an appropriate Change Order reflecting the terms of the agreement.
Appears in 3 contracts
Samples: Progressive Design Build Agreement, Contract Between Owner and Design Builder Lump Sum, Form of Agreement Between Owner and Design Builder
Work Change Directives. 12.4.1 9.2.1 A Work Change Directive is a written order prepared and signed by Design-Builder Owner, directing a change in the Work prior to agreement on an adjustment in the Contract Price and/or the times for completion of the WorkContract Time(s).
12.4.2 Design-Builder and Design-Build Subcontractor shall negotiate in good faith and as expeditiously as possible the appropriate adjustments for the Work Change Directive. Upon reaching an agreement, the parties shall prepare and execute an appropriate Change Order reflecting the terms of the agreement.
Appears in 3 contracts
Samples: Design Build Contract, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder Lump Sum (Golden Grain Energy)
Work Change Directives. 12.4.1 7.2.1 A Work Change Directive is a written order prepared and signed by Design-Builder Owner, directing a change in the Work prior to agreement on an adjustment in the Contract Price and/or the times for completion of the WorkContract Time(s).
12.4.2 Design-Builder and Design-Build Subcontractor shall negotiate in good faith and as expeditiously as possible the appropriate adjustments for the Work Change Directive. Upon reaching an agreement, the parties shall prepare and execute an appropriate Change Order reflecting the terms of the agreement.
Appears in 3 contracts
Samples: Progressive Design Build Agreement, Design Build Agreement, Progressive Design Build Agreement
Work Change Directives. 12.4.1 9.2.1 A “Work Change Directive Directive” is a written order prepared and signed by Design-Builder Owner, directing a change in the Work prior to agreement on an adjustment in the Contract Price and/or the times for completion of the WorkContract Time(s).
12.4.2 Design-Builder and Design-Build Subcontractor shall negotiate in good faith and as expeditiously as possible the appropriate adjustments for the Work Change Directive. Upon reaching an agreement, the parties shall prepare and execute an appropriate Change Order reflecting the terms of the agreement.
Appears in 1 contract
Samples: Construction Contract