Common use of Work Change Directives Clause in Contracts

Work Change Directives. 7.2.1 A Work Change Directive cannot change GMP or Contract Time, but is evidence that the Parties agree that a change, ordered by directive, will be incorporated in a subsequently issued Change Order as to its effect, if any, on a CGMP, the GMP, or Contract Time. 7.2.2 Failure by XXXX to commence work identified in a Work Change Directive within the time specified by Director, or to complete the work in a reasonable period of time, may be determined by Director to be a material breach of this Contract. 7.2.3 A Work Change Directive is used in the absence of total agreement of the terms of a Change Order. Interim payments are made in accordance with Article 9. XXXX may include a request for payment for undisputed Work under a Work Change Directive with Applications for Payment submitted in accordance with the Contract Documents. 7.2.4 If XXXX signs a Work Change Directive, then XXXX agrees to its terms including adjustment in a CGMP or the GMP (as applicable) and Contract Time or method for determining them. Contract by the Parties to adjustments in a CGMP or the GMP (as applicable) and Contract Time shall be recorded as a Change Order. 7.2.5 Director, by Work Change Directive, may direct XXXX to take measures as necessary to expedite construction to achieve Date of Substantial Completion on or before expiration of Contract Time. When the Work is expedited solely for convenience of the City and not due to XXXX’x failure to prosecute timely completion of the Work, then XXXX is entitled to an adjustment in the GMP equal to actual costs determined in accordance with Article 7.

Appears in 1 contract

Samples: Construction Manager at Risk Contract

AutoNDA by SimpleDocs

Work Change Directives. 7.2.1 A Work Change Directive cannot change a GMP or Contract Time, but is evidence that the Parties agree that a change, ordered by directive, will be incorporated in a subsequently issued Change Order as to its effect, if any, on a CGMP, GMP or the GMP, or Contract Time. 7.2.2 Failure by XXXX to commence work identified in a Work Change Directive within the time specified by DirectorHFH, or to complete the work in a reasonable period of time, may be determined by Director HFH to be a material breach of this the Contract. 7.2.3 A Work Change Directive is used in the absence of total agreement of the terms of a Change Order. Interim payments are made in accordance with Article 9§9.6.1. XXXX may include a request for payment for undisputed Work under a Work Change Directive with Applications applications for Payment payment submitted in accordance with the Contract Documents. 7.2.4 If XXXX signs a Work Change Directive, then XXXX agrees to its terms including adjustment in a CGMP or the GMP (as applicable) and Contract Time or method for determining them. Contract Agreement by the Parties to adjustments in a CGMP GMP or the GMP (as applicable) and Contract Time shall immediately be recorded as a Change Order. 7.2.5 DirectorHFH, by Work Change Directive, may direct XXXX to take measures as necessary to expedite construction to achieve Date of Substantial Completion on or before expiration of Contract Time. When the Work is expedited solely for convenience of the City HFH and not due to XXXX’x failure to prosecute timely completion of the Work, then XXXX is entitled to an adjustment in the GMP equal to actual costs determined Cost of the Work described in accordance with Article 7§11.8 of the Agreement. XXXX’x agreed to fee, as defined in §6.4 of the Agreement, shall be applied to the incremental increase in the Cost of the Work, if any, resulting from any such Work Change Directive.

Appears in 1 contract

Samples: Construction Agreement

Work Change Directives. 7.2.1 A Work Change Directive cannot change GMP a CGMP, the GMP, or Contract Time, but is evidence that the Parties agree that a change, ordered by directive, will be incorporated in a subsequently issued Change Order as to its effect, if any, on a CGMP, the GMP, or Contract Time. 7.2.2 Failure by XXXX DESIGN-BUILD CONTRACTOR to commence work identified in a Work Change Directive within the time specified by Director, or to complete the work in a reasonable period of time, may be determined by Director to be a material breach of this Contract. 7.2.3 A Work Change Directive is used in the absence of total agreement of the terms of a Change Order. Interim payments are made in accordance with Article 9. XXXX DESIGN-BUILD CONTRACTOR may include a request for payment for undisputed Work under a Work Change Directive with Applications for Payment submitted in accordance with the Contract Documents. 7.2.4 If XXXX DESIGN-BUILD CONTRACTOR signs a Work Change Directive, then XXXX DESIGN-BUILD CONTRACTOR agrees to its terms including adjustment in a CGMP or the GMP (as applicable) and Contract Time or method for determining them. Contract Agreement by the Parties to adjustments in a CGMP or the GMP (as applicable) and Contract Time shall be recorded as a Change Order. 7.2.5 Director, by Work Change Directive, may direct XXXX DESIGN-BUILD CONTRACTOR to take measures as necessary to expedite construction to achieve Date of Substantial Completion on or before expiration of Contract Time. When the Work is expedited solely for convenience of the City and not due to XXXX’x DESIGN-BUILD CONTRACTOR’s failure to prosecute timely completion of the Work, then XXXX DESIGN-BUILD CONTRACTOR is entitled to an adjustment in the GMP equal to actual costs determined in accordance with Article 7.

Appears in 1 contract

Samples: Design Build Contract

Work Change Directives. 7.2.1 A Work Change Directive cannot change GMP or Contract Time, but is evidence that the Parties agree that a change, ordered by directive, will be incorporated in a subsequently issued Change Order as to its effect, if any, on a CGMP, the GMP, or Contract Time. 7.2.2 Failure by XXXX to commence work identified in a Work Change Directive within the time specified by Director, or to complete the work in a reasonable period of time, may be determined by Director to be a material breach of this Contract. 7.2.3 A Work Change Directive is used in the absence of total agreement of the terms of a Change Order. Interim payments are made in accordance with Article 9. XXXX may include a request for payment for undisputed Work under a Work Change Directive with Applications for Payment submitted in accordance with the Contract Documents. 7.2.4 If XXXX signs a Work Change Directive, then XXXX agrees to its terms including adjustment in a CGMP or the GMP (as applicable) and Contract Time or method for determining them. Contract Agreement by the Parties to adjustments in a CGMP or the GMP (as applicable) and Contract Time shall be recorded as a Change Order. 7.2.5 Director, by Work Change Directive, may direct XXXX to take measures as necessary to expedite construction to achieve Date of Substantial Completion on or before expiration of Contract Time. When the Work is expedited solely for convenience of the City and not due to XXXX’x failure to prosecute timely completion of the Work, then XXXX is entitled to an adjustment in the GMP equal to actual costs determined in accordance with Article 7.

Appears in 1 contract

Samples: Construction Management at Risk Agreement

AutoNDA by SimpleDocs

Work Change Directives. 7.2.1 A Work Change Directive cannot change GMP or Contract Time, but is evidence that the Parties agree that a change, ordered by directive, will be incorporated in a subsequently issued Change Order as to its effect, if any, on a CGMP, the GMP, GMP or Contract Time. 7.2.2 Failure by XXXX to commence work identified in a Work Change Directive within the time specified by Director, or to complete the work in a reasonable period of time, may be determined by Director to be a material breach of this Contract. 7.2.3 A Work Change Directive is used in the absence of total agreement of the terms of a Change Order. Interim payments are made in accordance with Article 9. XXXX may include a request for payment for undisputed Work under a Work Change Directive with Applications for Payment submitted in accordance with the Contract DocumentsContract. 7.2.4 If XXXX signs a Work Change Directive, then XXXX agrees to its terms including adjustment in a CGMP or the GMP (as applicable) and Contract Time or method for determining them. Contract Agreement by the Parties to adjustments in a CGMP or the GMP (as applicable) and Contract Time shall be recorded as a Change Order. 7.2.5 Director, by Work Change Directive, may direct XXXX to take measures as necessary to expedite construction to achieve Date of Substantial Completion on or before expiration of Contract Time. When the Work is expedited solely for convenience of the City and not due to XXXX’x failure to prosecute timely completion of the Work, then XXXX is entitled to an adjustment in the GMP equal to actual costs determined in accordance with Article 7.

Appears in 1 contract

Samples: Construction Management at Risk Agreement