Common use of Work Progress Clause in Contracts

Work Progress. The Developer and Connecting Transmission Owner will keep each other advised periodically as to the progress of their respective design, procurement and construction efforts. Either Party may, at any time, request a progress report from the other Party. If, at any time, the Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In-Service Date, the Developer will provide written notice to the Connecting Transmission Owner of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 7 contracts

Samples: Interconnection Agreement, Service Agreement, Service Agreement

Work Progress. The Developer and Connecting Transmission Owner will keep each other advised periodically as to the progress of their respective design, procurement and construction efforts. Either Any Party may, at any time, request a progress report from the other PartyDeveloper or Connecting Transmission Owner. If, at any time, the Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In-Service Date, the Developer will provide written notice to the Connecting Transmission Owner of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 5 contracts

Samples: Transmission Facility Interconnection Agreement, Transmission Facility Interconnection Agreement, Transmission Facility Interconnection Agreement

Work Progress. The Developer and Connecting Transmission Owner will keep each other advised periodically as to the progress of their respective design, procurement and construction efforts. Either Party may, at any time, request a progress report from the other Party. If, at any time, the Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In-Service Date, the Developer will provide written notice to the Connecting Transmission Owner of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.

Appears in 4 contracts

Samples: Interconnection Agreement, Transmission Facility Interconnection Agreement, Interconnection Agreement

Work Progress. The Developer and Connecting Transmission Owner will keep each other advised periodically as to the progress of their respective designother, procurement and construction efforts. Either Any Party may, at any time, request a progress report from the other PartyDeveloper or Transmission Owner. If, at any time, the Developer determines that the completion of the Connecting Transmission Owner’s 's Attachment Facilities will not be required until after the specified In-Service Date, the Developer will provide written notice to the Connecting Transmission Owner and NYISO of such later date upon which the completion of the Connecting Transmission Owner’s 's Attachment Facilities will be required.

Appears in 3 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Work Progress. The Developer and Connecting Transmission Owner will keep each other advised periodically as to the progress of their respective design, procurement and construction efforts. Either Any Party may, at any time, request a progress report from the other PartyDeveloper or Connecting Transmission Owner. If, at any time, the Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In-Service Date, the Developer will provide written notice to the Connecting Transmission Owner of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.determines

Appears in 1 contract

Samples: Transmission Facility Interconnection Agreement

Work Progress. The Developer and Connecting Transmission Owner will keep each other advised periodically as to the progress of their respective design, procurement and construction efforts. Either Party may, at any time, request a progress report from the other Party. If, at any time, the Developer determines that the completion of the Connecting Transmission Owner’s Attachment Facilities will not be required until after the specified In-Service Date, the Developer will provide written notice to the Connecting Transmission Owner of such later date upon which the completion of the Connecting Transmission Owner’s Attachment Facilities will be required.Connecting

Appears in 1 contract

Samples: Transmission Facility Interconnection Agreement