Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the HRRH Representative and the Independent Certifier a works report (each, a “Works Report”), which will include: (i) an executive summary describing the general status of the Works and progress made over the relevant month; (ii) an updated Works Schedule, in both summary and detailed formats; (iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes; (iv) in accordance with Section 22.2, a LEED progress report; and (v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to HRRH, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated/revised Works Schedule. (b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by HRRH.
Appears in 1 contract
Sources: Project Agreement
Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the HRRH CAMH Representative and the Independent Certifier a works report (each, a “Works Report”), which will include:
(i) an executive summary describing the general status of the Works and progress made over the relevant month;
(ii) an updated Works Schedule, in both summary and detailed formats;
(iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes;
(iv) in accordance with Section 22.222.3, a LEED progress report; and
(v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to HRRHCAMH, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated/updated or revised Works Schedule.
(b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by HRRHCAMH.
Appears in 1 contract
Sources: Project Agreement
Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the HRRH HHS Representative and the Independent Certifier a works report (each, a “Works Report”), which will include:
(i) an executive summary describing the general status of the Works and progress made over the relevant month;
(ii) an updated Works Schedule, in both summary and detailed formats;
(iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes;
(iv) in accordance with Section 22.2, a LEED progress report; and
(v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to HRRHHHS, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated/revised Works Schedule.
(b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by HRRHHHS.
Appears in 1 contract
Sources: Project Agreement
Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the HRRH WCH Representative and the Independent Certifier a works report (each, a “Works Report”), which will include:
(i) an executive summary describing the general status of the Works and progress made over the relevant month;
(ii) an updated Works Schedule, in both summary and detailed formats;
(iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes;
(iv) in accordance with Section 22.2, a LEED progress report; and
(v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to HRRHWCH, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated/revised Works Schedule.
(b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by HRRHWCH.
Appears in 1 contract
Sources: Project Agreement
Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the HRRH MHCP Representative and the Independent Certifier a works report (each, a “Works Report”), which will include:
(i) an executive summary describing the general status of the Works and progress made over the relevant month;
(ii) an updated Works Schedule, in both summary and detailed formats;
(iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes;
(iv) in accordance with Section 22.222.3, a LEED progress report; and
(v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to HRRHMHCP, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated/updated or revised Works Schedule.
(b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by HRRHMHCP.
Appears in 1 contract
Sources: Project Agreement
Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the HRRH HMQ Representative and the Independent Certifier a works report (each, a “Works Report”), which will include:
(i) an executive summary describing the general status of the Works and progress made over the relevant month;
(ii) an updated Works Schedule, in both summary and detailed formats;
(iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes;
(iv) in accordance with Section 22.2, a LEED progress report; and
(viv) an update on those matters set out in Schedule 34 17 – Works Report Requirements; , all in form and substance satisfactory to HRRHHMQ, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated/updated or revised Works Schedule.
(b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by HRRHHMQ.