Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the CAMH Representative and the Independent Certifier a works report (each, a “Works Report”), which will include: (i) an executive summary describing the general status of the Works and progress made over the relevant month; (ii) an updated Works Schedule, in both summary and detailed formats; (iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes; (iv) in accordance with Section 22.3, a LEED progress report; and (v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to CAMH, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated or revised Works Schedule. (b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by CAMH.
Appears in 1 contract
Samples: Project Agreement
Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the CAMH WCH Representative and the Independent Certifier a works report (each, a “Works Report”), which will include:
(i) an executive summary describing the general status of the Works and progress made over the relevant month;
(ii) an updated Works Schedule, in both summary and detailed formats;
(iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes;
(iv) in accordance with Section 22.322.2, a LEED progress report; and
(v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to CAMHWCH, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated or updated/revised Works Schedule.
(b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by CAMHWCH.
Appears in 1 contract
Samples: Project Agreement
Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the CAMH HRRH Representative and the Independent Certifier a works report (each, a “Works Report”), which will include:
(i) an executive summary describing the general status of the Works and progress made over the relevant month;
(ii) an updated Works Schedule, in both summary and detailed formats;
(iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes;
(iv) in accordance with Section 22.322.2, a LEED progress report; and
(v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to CAMHHRRH, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated or updated/revised Works Schedule.
(b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by CAMHHRRH.
Appears in 1 contract
Samples: Project Agreement
Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the CAMH MHCP Representative and the Independent Certifier a works report (each, a “Works Report”), which will include:
(i) an executive summary describing the general status of the Works and progress made over the relevant month;
(ii) an updated Works Schedule, in both summary and detailed formats;
(iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes;
(iv) in accordance with Section 22.3, a LEED progress report; and
(v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to CAMHMHCP, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated or revised Works Schedule.
(b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by CAMHMHCP.
Appears in 1 contract
Samples: Project Agreement
Works Report. (a) Project Co shall continuously monitor the progress of the Works in relation to the Works Schedule and, within 15 Business Days following the end of each calendar month from Financial Close until the Final Completion Date, Project Co shall provide to the CAMH HHS Representative and the Independent Certifier a works report (each, a “Works Report”), which will include:
(i) an executive summary describing the general status of the Works and progress made over the relevant month;
(ii) an updated Works Schedule, in both summary and detailed formats;
(iii) a narrative description of any Disputes related to the Works, including any action that has taken place over the relevant month to resolve such Disputes;
(iv) in accordance with Section 22.322.2, a LEED progress report; and
(v) an update on those matters set out in Schedule 34 – Works Report Requirements; all in form and substance satisfactory to CAMHHHS, acting reasonably. For greater certainty, for all updates and revisions to the Works Schedule, Project Co must provide a revised critical path reflecting the updated or updated/revised Works Schedule.
(b) Project Co shall use, and shall ensure that the Construction Contractor uses, the project management software system specified by CAMHHHS.
Appears in 1 contract
Samples: Project Agreement