AMENDED AND RESTATED DESIGN-BUILD AGREEMENT FOR GUARANTEED MAXIMUM PRICE ARCHITECTURAL, ENGINEERING AND CONSTRUCTION SERVICES DATED SEPTEMBER 14, 2005 CHANGE ORDER AND AMENDMENT
Exhibit 10.5
AMENDED AND RESTATED
DESIGN-BUILD AGREEMENT FOR GUARANTEED MAXIMUM PRICE ARCHITECTURAL,
ENGINEERING AND CONSTRUCTION SERVICES
DATED SEPTEMBER 14, 2005
CHANGE ORDER AND AMENDMENT
25 MAY 2006
Project: Xxxx Resorts Macau |
Change Order No.: 3 | |
“Contractor”: jointly and severally |
“Owner”: | |
LEIGHTON CONTRACTORS (ASIA) LIMITED 39th Floor, Sun Hung Kai Centre 00 Xxxxxxx Xxxx Xxxxx Xxxxxxx Xxxx Xxxx |
WYNN RESORTS (MACAU) S.A. 335-341, Alameda Dr. Carlos d’Asumpcao 0xx Xxxxx, Xxxxxxx Xxxxxx Xxxxx | |
CHINA STATE CONSTRUCTION ENGINEERING (HONG KONG) LIMITED 00xx Xxxxx, Xxxxx Overseas Xxxxxxxx 000 Xxxxxxxx Xxxx Xxxx Xxxx |
||
XXXXX CONSTRUCTION ENGINEERING (MACAU) COMPANY LIMITED Rua do Xxxxx Xx. 00 Xxxxxxxx Xxxxxxxxxx Xxxxx Xxxx, 00 andar Macau |
Pursuant to Article XVIII of that certain Amended and Restated Design-Build Agreement for Guaranteed Maximum Price Architectural, Engineering and Construction Services between Owner and Contractor for the design and construction of a luxury resort/hotel/casino complex in Macau known as Wynn Resorts Macau, executed and delivered as a deed on September 14, 2005 (the “Contract”), and the desire of the Owner and Contractor to amend and supplement certain terms and provisions of the Contract, the Contract is hereby modified by this agreement and all related drawings, plans and specifications attached hereto (collectively, the “Change Order”), made as a deed effective as of the date set forth above.
1
1. Scope of Work. The Scope of Work is changed as follows;
Masterplan Drawings for the following modifications and additions/deletions (collectively the “Masterplan Modifications):
WM/ASK/0325/22 | Basement Floor Plan | |
WM/ASK/0326/31 | Ground Floor Plan | |
WM/ASK/0327/31 | First Floor Plan | |
WM/ASK/0328/24 | Second Floor Plan | |
WM/ASK/0329/22 | Third Floor Plan |
Expansion Area Modifications
Plan No. SK NO.8.2.1.0237/06 dated 17 May 06 defines Area 7 for the purposes of this Change Order.
The interior fit-out works and building services installations, as further defined below, are deleted from the scope of works. Area 7 on the referenced plan is to be treated as a “shell” space with no floor, wall or ceiling finishes installed. Building Services central plant installation and primary distribution and trunking shall be provided, as well as all life safety systems installation as required to achieve code compliance.
The following describes the extent of works to be installed by the Contractor:
a. | Architecture: |
All external architectural elements and finishes as documented on the above referenced Masterplans are to be constructed.
Temporary Walls shall be provided to separate operational and unfitted areas. These walls shall provide sound and dust separation, and shall be finished to a FOH standard on one side.
b. | Interior Design: |
No Interior Design shall be provided for Area 7. Interior Design documents shall be issued for all of the temporary wall locations, and the Contractor shall be responsible for installation of these temporary walls and finishes.
The Contractor shall provide any walls, doors, or other fixtures required to achieve fire and smoke separation/compartmentation in Area 7.
c. | Structure: |
All structural works as documented on the above referenced Masterplans are to be constructed.
d. | Mechanical Services: |
All Central Plant as documented on the above referenced Masterplans are to be installed.
Mechanical services (HVAC) primary distribution ductwork and equipment shall be installed. Flexible branch ducts and grilles are deleted.
e. | Electrical Services: |
All Central Plant as documented on the above referenced Masterplans are to be installed.
2
Electrical services primary distribution shall be installed up to and including meter room locations. Emergency lighting and life safety system and signage shall also be provided. Final circuits and trunking is deleted.
A comprehensive sub-floor trunking system (Xxxxxx Duct) shall be provided for the entire area for laying of power and data cabling. This shall include topping screed.
f. | Fire Services: |
Fire Services shall be installed through out in compliance with code and with adequate capacity to meet future requirements. Upper layer sprinklers and provision for extending lower layer sprinklers are to be provided throughout.
g. | Plumbing and Drainage Services: |
Plumbing and Drainage installation shall be provided including cold & hot water system, soil & waste disposal, storm water, and LPG distribution. Primary distribution to local areas shown on the above referenced Masterplans (toilet, kitchen, service bar, etc. locations) are to be installed.
h. | Elevators and Escalators: |
Elevators and Escalators are to be installed and commissioned as documented on the referenced Masterplans.
i. | Building Maintenance Services: |
Building Management System shall be installed and integrated with existing system. The system shall be sized to accommodate reasonable no. of points in fully fitted out space.
j. | Extra Low Voltage Systems: |
Extra Low Voltage systems shall be installed including comprehensive IT, BGM/PA and security cabling up to the TR rooms. Wireless data infrastructure shall be provided throughout. Distributed final cabling from TR rooms to final points are deleted.
k. | Builder’s Work in connection with Services: |
Maintenance and access catwalks are to be installed.
All Building Services shall be zoned appropriately to allow uninterrupted operation of the remainder of the property whilst future fit-out occurs.
Decrease to the Guaranteed Maximum Price: |
HKD54,025,109 / USD6,926,296 |
3
2. | Change to the Expansion Project Guaranteed Maximum Price |
Expansion Project
Expansion Project Guaranteed Maximum Price |
US$ | 156,759,326 | ||
Total of previous Change Orders |
US$ | 17,719,374 | ||
Previous Expansion Project Guaranteed Maximum Price (Subtotal) |
US$ | 174,478,700 | ||
Total of this Change Order |
US$ | (6,926,296 | ) | |
Less – Transfer from Original Project Owner Contingency |
US$ | (0 | ) | |
Revised Expansion Project Guaranteed Maximum Price thru Change Order No. 3 |
US$ | 167,552,404 |
The Expansion Project Guaranteed Maximum Price set forth in Section 3.1(b) of the Contract is, pursuant to the terms of this Change Order, hereby decreased from US$ 174,478,700 to US$ 167,552,404 based on the Changes described above. The detailed breakdown of the foregoing increase is contained in the revised Expansion Project Guaranteed Maximum Price Breakdown labeled as Revised Exhibit F, dated 25 May 2006 and attached to this Change Order. Accordingly, the Expansion Project Guaranteed Maximum Price Breakdown attached as Exhibit F to the Contract is hereby deleted in its entirety and replaced with the Revised Expansion Project Guaranteed Maximum Price Breakdown attached hereto. From and after the date of this Change Order, all references in the Contract Documents to the “Expansion Project Guaranteed Maximum Price Breakdown” attached as Exhibit F to the Contract, shall mean and refer to the Revised Expansion Project Guaranteed Maximum Price Breakdown attached hereto as Revised Exhibit F. From and after the date of this Change Order, any and all references in the Contract Documents to the “Expansion Project Guaranteed Maximum Price” shall mean the amount of US$ 167,552,404.
3. | Project Schedule |
The Contract Time of 726 calendar days from Expansion Project Date of Commencement and the Guaranteed Date of Expansion Project Substantial Completion, as defined in Section 4.1.9 of the Contract each remain unchanged by this Change Order.
The Expansion Project Schedule, included as Attachment 5 of Exhibit B to the Contract, is hereby deleted in its entirety and replaced with the amended Attachment 5 of Exhibit B attached to this Change Order.
4. | Miscellaneous |
(a) | In the event of any inconsistency between the terms of the Contract and the terms of this Change Order, the terms of this Change Order will prevail. |
(b) | The obligations of Contractor hereunder are joint and several. |
(c) | Except as otherwise expressly modified hereby, the Contract will remain in full force and effect, and all of the terms and provisions of the Contract, as herein modified, are hereby ratified and reaffirmed. |
4
(d) | The parties acknowledge and agree that this Change Order will constitute both an amendment to the Contract and a “Change Order” as defined under the Contract. |
(e) | This Change Order may be executed in as many counterparts as may be deemed necessary and convenient, and by the different parties hereto on separate counterparts, each of which, when so executed, will be deemed an original, but all such counterparts shall constitute one and the same instrument. |
(f) | All initial capitalized terms used in this Change Order shall have the meaning ascribed to them in the Contract, unless otherwise defined herein. |
(g) | This Change Order is effective as of 25 May 2006. |
(h) | This Change Order shall be governed by, and construed in accordance with, the laws of England. |
(i) | This Change Order is subject to the approval and consent of the Lender’s. |
[signature page follows]
5
IN WITNESS whereof this Change Order has been duly executed and delivered as a deed the day and year first above written.
EXECUTED as a Deed on behalf of XXXX RESORTS (MACAU) S.A., a company incorporated in the Macau Special Administrative Region, by Xxxxx Xxxxx, being a person who, in accordance with the laws of that territory, is acting under the authority of the company in the presence of: |
) ) ) ) ) ) ) ) |
|||||
/s/ X.X. Xxxxxx Signature and name of witness |
||||||
SIGNED, SEALED and DELIVERED by Xxx Xxxxxxxx as attorney for LEIGHTON CONTRACTORS (ASIA) LIMITED under power of attorney dated August 18, 2005 in the presence of: |
) ) ) ) ) ) |
By executing this deed the attorney states that the attorney has received no notice of revocation of the power of attorney | ||||
/s/ Xxxxxx Xxxx Xxxx Signature and name of witness |
||||||
THE COMMON SEAL of CHINA STATE CONSTRUCTION ENGINEERING (HONG KONG) LIMITED was affixed to this Deed in the presence of: |
) ) ) ) |
|||||
/s/ CN YIP Signature and name of witness |
||||||
Signature of authorized person |
/s/ O.P. Kong Signature of authorized person | |||||
Office held |
Chairman Office held | |||||
Name of authorized person (block letters) |
O.P. Kong Name of authorized person (block letters) |
6
EXECUTED by Xx Xxxx Ping in his capacity as auxiliar of, and with authority to bind, CHINA CONSTRUCTION ENGINEERING (MACAU) COMPANY LIMITED a limited company incorporated in the Macau Special Administrative Region, pursuant to a resolution by the General Shareholders Meeting dated in the presence of: |
) ) ) ) ) ) ) ) ) |
By executing this deed the signatory warrants that the signatory is duly authorized to execute this deed on behalf of CHINA CONSTRUCTION ENGINEERING (MACAU) COMPANY LIMITED | ||||
/s/ Xxxx Xxx Signature and name of witness |
7