Examples of Affected System Study Report in a sentence
Within ten (10) Business Days of providing the Affected System Study Report to Affected System Interconnection Customer(s), System Operator, Interconnecting Transmission Owner and Affected System Interconnection Customer(s) shall meet to discuss the results of the Affected System Study.
System Operator and Interconnecting Transmission Owner shall complete the Affected System Study and provide the Affected System Study Report to Affected System Interconnection Customer(s) and the host transmission provider with whom interconnection has been requested within one hundred fifty (150) Calendar Days after the receipt of the Affected System Study Agreement and deposit.
Upon Affected System Interconnection Customer(s)’ receipt of the Affected System Study Report, Affected System Interconnection Customer(s) shall compensate System Operator and Interconnecting Transmission Owner for the actual cost of the Affected System Study.
If Interconnection Customer has not received its Affected System Study Report from the Affected System Operator prior to the date that it would be required to execute its LGIA (or request that its LGIA be filed unexecuted) pursuant to Section 11.1 of this LGIP, System Operator shall, upon request of Interconnection Customer, extend this deadline to thirty (30) Calendar Days after Interconnection Customer’s receipt of the Affected System Study Report.
SPP shall provide a copy of its Affected System Study Report to Entergy at the same time such study report is made available to the customer.
When SPP or the SPP customer executes the Affected System Study Agreement, the ICT will perform an Affected System Study in accordance with the Entergy OATT and will post on Entergy’s OASIS the Affected System Study Report by the 60th day after execution of the Affected System Study Agreement.
When the customer executes the Affected System Study Agreement, the ICT will post the Affected System Study Report on Entergy’s OASIS by the 60th day after execution of the Affected System Study Agreement.
The ICT will provide a copy of its Affected System Study Report to SPP at the same time such study is made available to the customer to the extent that these entities are distinct.
Transmission Provider will tender to Affected System Interconnection Customer an Affected System Facilities Construction Agreement within thirty (30) Calendar Days of providing the Affected System Study Report.
The Debtor shall make sure it has personnel adequate in number and sophistication so that it does not incur any additional bank fees for overdrafts and/or insufficient funds, as reflected in its monthly bank statement.