Examples of Contract Substantial Completion Date in a sentence
Owner may grant time extensions only if a Change Proposal affects the activities on the Longest Path of an Owner approved Work Progress Schedule; i.e., when the Work impacts the "Contract Substantial Completion Date".
The parties agree that the Owner will be substantially damaged in amounts that will be difficult or impossible to determine if Substantial Completion or Final Acceptance is not achieved by the Contractor on or before the Contract Substantial Completion Date and/or Contract Final Acceptance Date set forth herein.
Contractor Groathouse Construction, Inc.Laramie, WYGuaranteed Maximum Price $19,800,000 Contract Substantial Completion Date January 15, 2015 (In Thousands)TotalAdminConstrDesignTechFF&EMiscCntngcyBudget26,91991219,8002,922974974637700Expended4,2895032,5741,19700150Obligated17,969017,226523000220Un-obligated4,66140901,202974974622480 Remarks Foundation construction and related earthwork is generally in place, including drilled piers and grade beams.
The parties therefore agree that if Substantial Completion does not occur by the Contract Substantial Completion Date for any reason not the fault of the Owner or otherwise constituting an excusable delay, the Owner shall be entitled to liquidated damages in the amount of $1000 per calendar day for each day the Substantial Completion of the project, or any phase thereof, is delayed beyond the Contract Substantial Completion Date in lieu of actual damages for such delays.
Contractor Haselden Wyoming Constructors Casper, WYGuaranteed Maximum Price $7,099,599 Contract Substantial Completion Date September 29, 2014 (In Thousands)TotalAdminConstrDesignTechFF&EMiscCntngcyBudget12,85041510,2921,06525042740361Expended3523203200000Obligated7,78707,1006870000Un-obligated4,7113833,1925825042740361 Remarks Bid packages for video boards, scoreboards and seating are being prepared for early bid advertising due to long lead times on production and procurement.
The date which is 60 calendar days past the Notice to Proceed shall be the Contract Substantial Completion Date.
Energy Innovation Center Construction Manager at Risk G E Johnson Construction CompanyJackson, WYGuaranteed Maximum Price $18,926,514 Contract Substantial Completion Date June 4, 2012 Extended June 7, 2013 (In Thousands)TotalAdminConstrDesignTechFF&EMiscCntngcyBudget25,40068619,3481,8551,0701,007507927Expended28,66360622,7051,8551,070993507927Obligated00000000Other Funding3,35703,35700000Un-obligated94800001400 Remarks Warranty review was done in November.
Powell Seed Analysis LaboratoryContractor: Jim’s Building ServiceBid Price: $254,618.00Original Completion Date: 11 April 2003 Contract Substantial Completion Date: N/A TotalAdministrationConstructionDesignContingencyBudget325,00012,731254,61820,98036,671Expended39,9286,04518,14815,735-Obligated241,715-236,4705,245-Un-obligated43,3576,686--36,671Remarks: Laboratory and Germination Room HVAC design services are being provided by the Facilities Planning Office.
Construction Manager at Risk FCI Constructors, Inc.Longmont, COGuaranteed Maximum Price $38,075,000 Contract Substantial Completion Date August 31, 2009 (In Thousands)TotalAdminConstrDesignFF&EMiscCntngcyBudget50,0301,34638,0752,7004,4301,7881,691Expended33,83558028,0772,4311,9707770Obligated11,419011,37247000Other Funding2,29402,2940000Un-obligated7,0707669202222,4601,0111,691 Remarks Finish work continues in the addition.
Contractor Groathouse Construction, Inc.Laramie, WYGuaranteed Maximum Price $19,800,000 Contract Substantial Completion Date January 15, 2015Extended March 31, 2015 (In Thousands)TotalAdmin Remarks Occupancy of the Phase I eastern reconstruction/addition portion of the Half Acre Recreation and Wellness Center is expected take place the week of March8.