Examples of Fixed Storage Charge in a sentence
In the event that the Reliability in a quarter exceeds 1 (one) Forced Closure in the Silo Complex, the Concessionaire shall pay to the Authority Damages equal to 2.5% (two point five per cent) of the Fixed Storage Charge payable for the storage Capacity of the Silo Complex in accordance with the provisions of Clause 15.1 and 15.2 for each such Forced Closure in excess of 1 (one).
Year Fixed Storage Charge in Rs per MT per Month 2012-13 57.50 2013-14 62.45 2014-15 66.04 2015-16 67.02 2016-17 67.70 2017-18 71.09 2018-19 74.64 2019-20 78.37 Note: Fixed Storage Charge till Financial Year 2016-17 has been calculated based on the actual variation in Price Index, however from Financial Year 2017-18 onwards, the Fixed Storage Charge has been estimated based on Average Price index of @5% annually.
The illustration for calculation of Fixed storage charge is provided in Schedule E For the avoidance of doubt and by way of illustration, the Fixed Storage Charge for the Accounting Year commencing from April 1, 2019 shall be calculated by taking into account the total variation in the price index from the based index year duly factoring the annual escalation over the years as per price Index and the same shall be as per following table for that Accounting Year.
For the avoidance of doubt, the Parties agree that the base Fixed Storage Charge mentioned in Clause 25.1.4 has been fixed with reference to Accounting Year in which COD occurs.
The Financial Quote shall be the Fixed Storage Charge, in Rupees per ton per year, required by the Bidder for implementing the Project and payable by the Authority as per the terms and conditions of this RFP and provisions of the Concession Agreement.
The Bidder shall specify in Indian Rupees the Fixed Storage Charge for the Base Year to undertake the Project in accordance with this RFP and the provisions of the Concession Agreement.
For the avoidance of doubt and by way of illustration, the Parties agree that if the pro rata Fixed Storage Charge for 1% (one per cent) of Normative Availability is Rs. x, the Damages payable for reduction of 1% (one per cent) in Actual Availability below the level of Normative Availability shall be Rs. 0.5x, which shall be in addition to the pro rata reduction of Rs. x in the Fixed Storage Charge payable for the relevant month.
The Project shall be awarded to the Bidder quoting the Lowest Fixed Storage Charge.
Shortfall in Availability below Normative Availability levels (as per Section 11.9.2) In the event that Actual Availability at any time is less than the Normative Availability, the Fixed Storage Charge payable for the relevant month shall be proportionately reduced and in addition, such reduction shall be multiplied by a factor of 0.5 (zero point five) for determination of Damages.
In this RFP, the term “Lowest Bidder” shall mean the Bidder who has quoted the lowest Fixed Storage Charge.