Examples of Guaranteed Commercial Operation Deadline in a sentence
Failure to achieve Commercial Operation on or before the Guaranteed Commercial Operation Deadline shall constitute an Event of Default by Owner.
In no event will the Substantial Completion Deadline be extended beyond the Guaranteed Commercial Operation Deadline.
The “Substantial Completion Deadline” is September 1, 2022, which date may be extended due to Force Majeure up to the Guaranteed Commercial Operation Deadline.
Owner shall undertake such activities in sufficient time to achieve Commercial Operation of the Project by the Guaranteed Commercial Operation Deadline and CHGE will reasonably cooperate with Owner to meet such deadline.
This Agreement shall terminate automatically at midnight on the Guaranteed Commercial Operation Deadline if Commercial Operation has not occurred on or before the Guaranteed Commercial Operation Deadline, and Owner shall owe to CHGE a Termination Payment calculated in accordance with Section 10.3(a)(i).
Agreement execution timing subject to change depending on the Agreement modification requested and issues requiring negotiations but will not impact the Guaranteed Commercial Operation Deadline.
The “Substantial Completion Deadline” is September 1, 2025, which date may be extended due to Force Majeure up to the Guaranteed Commercial Operation Deadline.
Either Party shall be permitted to disclose the following terms with respect to this Agreement: (A) Party names, (B) technology type, (C) Delivery Period, (D) Project location, (E) Contract Capacity, (F) Guaranteed Commercial Operation Deadline, and (G) the Project’s expected electric energy deliveries.
Owner shall undertake such activities in sufficient time to achieve Commercial Operation of the Project by the Guaranteed Commercial Operation Deadline and RG&E will reasonably cooperate with Owner to meet such deadline.
Preference will be given to Offers that most closely adhere to the Agreement to ensure timely execution of the Agreement and the Commercial Operation of the Project prior to the Guaranteed Commercial Operation Deadline.